Search
March 16, 2025

FERC to Rule on SPP’s RA Requirement for Winter

FERC is expected to rule on SPP’s proposed tariff revisions adding a winter season resource adequacy requirement (RAR) during its monthly open meeting March 20 (ER24-2397). 

The commission in November 2023 rejected the proposed revisions, finding SPP’s proposal did not contain any requirement that the resources included in load-responsible entities’ workbooks are expected to be available. FERC also said the grid operator had not demonstrated it is reasonable to permit LREs to rely on resources that are not expected to be available to satisfy their winter season RARs. 

SPP filed a response June 28, asking for an effective date of Jan. 1, 2025. 

The RTO’s Board of Directors approved the winter season obligation in August 2023. (See “Board, RSC Endorse Winter Obligation,” SPP Board/Members Committee Briefs: July 24-25, 2023.) 

In February, the board approved a 38% planning reserve margin for the 2029 winter season. The 2029 summer season has a 17% PRM. 

The commission has also placed on its agenda an order that may be related to requests for rehearing by MISO and Montana-Dakota Utilities of a 2024 order that denied their complaints over a North Dakota cryptomining facility’s burdening a jointly owned flowgate with SPP (EL24-61). 

MISO and MDU sought to have market-to-market coordination on the line lifted after the Atlas Power Data Center added a 200-MW load to an SPP load pocket in northwestern North Dakota. They maintain that congestion management should not extend beyond SPP’s responsibility. (See MISO Argues to FERC for 2nd Look at Crypto-stressed Flowgate Management.) 

MISO in January filed a review petition with the D.C. Circuit Court of Appeals (25-1011) after FERC denied rehearing requests in November 2024, saying they “will be addressed in a future order.” MISO says the “future order” has not yet been issued in any of the underlying proceedings. 

FERC’s agenda also includes: 

    • a response to SPP’s compliance filing in its effort to facilitate RTO membership for nine Western Interconnection entities. The commission found the grid operator’s tariff for its Western RTO to be deficient in October 2024 (ER24-2185). (See FERC Issues Deficiency Letter for SPP’s RTO West Tariff.) FERC asked for further clarifications on six issues, including transitioning the expansion members’ transmission service request queues into SPP’s existing transmission service study processes and how LMPs on both sides of the West DC ties will inform how the RTO optimizes the interties’ use. SPP is trying to be the first grid operator with markets in both the Western and Eastern Interconnections. RTO West is scheduled to go live in April 2026. 
    • an order related to SPP’s request to incorporate a mark-to-auction collateral requirement for its transmission congestion rights markets. The RTO asked for an effective date of May 1 to allow for enough time to add the collateral requirement before the TCR annual auction (ER24-2906). 

Experts Urge Texas Policymakers to Go Big with 765-kV Transmission

ERCOT already operates a power system as large as those in several European countries, but demand growth is expected to bring it up to the level of PJM and MISO, which has the industry considering building a new system of 765-kV lines to transmit power around Texas. 

“When you think about PJM’s high-voltage overlay, they have this huge 765- and 500-kV system to move power back and forth and back and forth,” Grid United President Kris Zadlo said on a webinar March 13 hosted by Americans for a Clean Energy Grid. “And I think that’s kind of what we need to start thinking about if we’re going to be going to such a large system.” 

In the next decade, peak demand could double on ERCOT’s grid while overall consumption of power triples, said Michael Webber, professor of mechanical engineering at the University of Texas at Austin. 

The new demand is being driven by different factors. Data centers are part of the picture, but other sources include the need to electrify more of the oil and gas production in the booming Permian Basin and keep up with the general population and economic growth in Texas. ERCOT has grown 1 to 2% per year recently, when much of the rest of the country grew little to none, but now growth rates are up to 3 to 4% annually, Webber said. 

CenterPoint Energy is forecasting that demand in and around Houston will grow by 10 GW, which is the equivalent of adding Belgium’s total power demand to the system. 

“So, we have to add a Belgium to Houston, but we also have to add a Belgium to West Texas, and maybe half of Belgium to Abilene for data centers, or whatever,” Webber said. “If you start to add it up, and maybe a 10th of a Belgium here and there for LNG export terminals, which all say they’ll be electrified … it’s a lot of demand.” 

If all the demand were in one part of Texas, it could be met by building one power plant, but given how spread out it is across the state, transmission needs to be part of the picture, Webber said. 

“All of this adds up to this new estimate of 150 GW of load coming down the pipe,” said Conservative Texans for Energy Innovation’s Michael Jewell. “When the legislature heard about that, I think it really kind of freaked them out and got them to say, ‘You know, maybe there really is something that needs to happen.’ And I think it really has changed the dynamic to, ‘We do need to think about, how are we going to address this?’” 

Building transmission is part of the answer, but policymakers could decide to stick to 345-kV lines, as they did when Texas last did a major buildout of transmission more than 15 years ago with the Competitive Renewable Energy Zone lines to bring wind to customers. 

“One of the early questions was, should we be looking at 500-kV lines?” Jewell said. “And that kind of fell to the wayside as the advantages of 765 and the greater ability to move power there kind of outweighed almost what one could think of as an interim step in that regard.” 

The idea of building out 765-kV lines was first broached in the legislature with the aim of helping Permian Basin drillers continue to electrify, but once the focus was widened to the entire state, 765 kV only made more sense, he added. 

While 765 kV is the largest voltage used in the U.S., China has built an overlay system with 1,100-kV lines, Webber said. Voltages that high start to come up against manufacturing issues, Zadlo said. 

“Once you go above 345, whether it’s 500 or 765, it’s the same thing,” Zadlo said. “My understanding is the 765 breakers come out of the same factories that are making 345 breakers. So really, there’s no difference there. I think the only big difference is when it comes to transformer production.” 

Building a series of 765-kV lines also takes about the same amount of time as building 345, he added. 

Forecasting demand growth always comes with uncertainty, but given that some of the new loads can come online in a year while power plants take three or four, and transmission in Texas takes at least six, it makes sense to start planning for it now, Zadlo said. 

“You can’t accelerate a transmission line, right? You just can’t,” Zadlo said. “It’ll be disastrous if we’re wrong; if we don’t build that line on time. … But you can always slow it down if the load doesn’t materialize. You can always pull back the plans.” 

Another reason to move with big infrastructure buildouts is that they are almost always used to their capacity, Webber said. Railroads, broadband, the highways and other historical examples all involved some overbuilding, with only massive technological changes like the advent of automobiles and highways making the railroads less useful a century later. 

“If you’re going to go to the trouble [of building] capacity, you might as well build more capacity, and the higher voltage gives you more capacity,” Webber said. “So, I’d argue that this is actually the American way of doing things, and it would just give us more ability to move things around.” 

MISO Members Grapple with 54 GW in Incomplete Gen, Predict Storage Expansion

NEW ORLEANS — MISO members haven’t landed on easy answers in getting the approximately 54 GW of unfinished generation that has cleared the interconnection queue online sooner. 

MISO’s Advisory Committee convened March 12 during Board Week to focus on the footprint’s lagging generation projects and how future delays could be prevented. (See MISO Members to Explore Ways to Rev Up Stalled Generation Builds.) 

Despite the focus on commercial operation delays, members agreed later in the meeting that energy storage will eventually flourish in the footprint. 

Illinois Commerce Commissioner Michael Carrigan said some increased transparency from MISO about the challenges in getting generation online would be helpful. He said he appreciated the RTO’s new reporting on the status of approved projects’ commercial operation dates but said more detail on the delays would be valuable for stakeholders. 

Wisconsin Public Service Commissioner Marcus Hawkins said he has observed delayed projects inch past their original budgets into cost overruns. “So, ratepayers are affected by these delays.” 

Multiple stakeholders also said the delays are set to affect states’ resource plans. 

Clean Grid Alliance’s Beth Soholt said states and load-serving entities might consider speeding up their procurement timelines or consider changing their permitting processes. She said that she, like many, “underappreciated” how decisively the COVID-19 pandemic upended the generation development cycle. Soholt said some developers struggled with virtual meetings while land agreements languished without construction. “There’s still a hangover there.” 

CGA Executive Director Beth Soholt speaks (background) as NextEra Energy’s Erin Murphy takes notes | © RTO Insider

Soholt also noted that MISO has introduced several rule changes in its interconnection queue over the last few years, which may have some developers scrambling. 

“Interconnection customers have been living by the rules that MISO has set,” she said. 

Hawkins suggested that the full effect of the RTO’s latest rule changes — the stepped-up fees, automatic withdrawal penalties, more rigorous proof of land rights and annual megawatt cap — have yet to settle in. Hawkins said he thinks projects that are processed in the stricter environment will arrive better vetted. However, he said, stakeholders might have to accept that the energy transition may be interspersed with failed plans for generation projects. 

“I think this just might be some of the new normal … this presence of stalled or delayed resources,” Hawkins said. 

Soholt said that while a lot of the responsibility for delayed projects is “rightly” on interconnection customers, she asked for a dialogue with transmission owners on what can be done about their own staff shortages and supply chain woes that grind network upgrades to a halt. 

“All it says is, ‘TO Delay.’ So, can we get more granular?” Soholt asked of TOs’ reports to FERC. She also requested that more light be shed on how TOs prioritize construction of network upgrades. She said interconnection customers don’t know enough about what causes network upgrade bottlenecks. 

Pelican Power’s Tia Elliott suggested that stakeholders and MISO create a method to match existing projects in the queue to a nearby LSE’s forecasted needs.  

The Union of Concerned Scientists’ Sam Gomberg asked if it was worth examining the RTO’s generator interconnection agreement contracts to see if there are any impediments or out-of-date language. 

Alliant Energy’s Mitchell Myhre said MISO’s proposed resource addition lane for its queue should help get projects online faster. (See MISO Says Queue Fast Track Design Settled, Ready for FERC.) The RTO is set to file that proposal imminently. 

But Gomberg said he did not see how an express lane in the queue would keep those projects from running into the same “buzz saws” of delays that plague projects in the traditional queue. 

Soholt said MISO should have been focused on its existing queue all along instead of introducing “chaos” with a fast lane, in which projects will need transmission capacity alongside the projects in the regular queue.  

At a meeting of the MISO Board of Directors’ System Planning Committee on March 11, Aubrey Johnson, the RTO’s vice president of system planning and competitive transmission, said members have recently been picking up the pace on generation additions despite the delays. He said members managed to add a record 7.5 GW in nameplate capacity in 2024, up from 5.6 GW in 2023 and 3.5 GW in 2022. In the first half of 2025, the RTO expects to have 5 GW in new nameplate capacity. Members have added 1.4 GW in nameplate capacity since the beginning of the year. 

The interconnection queue contains 308 GW across 1,695 projects; 145 GW of that is solar generation. 

Johnson also said he hopes the recently approved megawatt cap on annual entrants in the queue ends the “mad rush” of projects in recent years and leads to more thoughtful development. 

Storage in the Wings

Later in the Advisory Committee meeting, members agreed that while storage might be a slow burn now, it will heat up in the 2030s.  

MISO should contemplate new rules now, they agreed. 

The RTO has just 164 MW of operational storage in its market, with about 2.7 GW approved and waiting to come online. Its interconnection queue contains 61 GW of nameplate capacity across 388 storage project proposals. 

Executive Director of Markets Innovation and Strategy Zak Joundi said that although storage is in its “infancy” and growing modestly in the footprint, the RTO expects 12 GW of storage around 2030 to become 53 GW by 2043. 

Zak Joundi, MISO | © RTO Insider

Gomberg predicted a rapid deployment of storage in the coming years and said MISO needs to hammer out appropriate market rules to compensate the “versatile” resources that can supply capacity, as well as relieve transmission constraints. 

Myhre said he anticipates the jump in storage will mimic the rise in wind capacity that began about two decades ago. He said megawatts will quickly multiply into gigawatts, with the RTO and stakeholders “learning together” to draw up participation rules. 

Jim Dauphinais, representing a collection of MISO end-use customers, said that while battery storage will prove important, the current technology is still limited to about four hours of output. 

“It doesn’t give us the same thing as a generation with a sustained supply of fuel. … While it can plug the gap, it can’t solve the exit of large generation resources,” he said. 

Dauphinais also said storage technologies are only going to be pursued to the extent that they earn revenues. He urged the RTO to begin forming market signals. 

NextEra Energy’s Erin Murphy said storage developers right now may be hesitant to build in MISO because of the investment uncertainty over their accreditation values. 

Joundi acknowledged that the RTO has work to do on modeling how storage would contribute to the grid. But he also said current storage volumes are low. 

Murphy pressed MISO to begin modeling work even with a small sample size.  

“We have to say, ‘We’re going to put a stake in the ground and begin,’” Murphy said. 

Calif. Officials Approve New Safety Measures for Battery Storage

The California Public Utilities Commission on March 13 voted to approve stricter safety standards on battery storage following a series of incidents at battery facilities. 

CPUC passed the new standards as an update to General Order 167, which became effective in 2005 and sets safety standards for electric generating facilities. The five-member commission voted unanimously to approve the update. 

The update provides “a method to implement and enforce maintenance and operation standards for electric generating facilities, in order to add new safety standards for the maintenance and operation of battery energy storage systems,” according to a news release.  

Additionally, the update requires battery storage facility owners to develop emergency plans in coordination with local authorities. It also imposes new technical logbook standards for battery storage systems, among other requirements. (See Calif. Officials Propose New Safety Measures for Battery Storage.) 

Commissioner John Reynolds said the resolution comes as battery storage grows rapidly in California. Battery storage capacity in the state grew from 500 MW in 2019 to over 13,000 MW in 2024, he noted. 

But the expansion of battery storage has caused safety concerns. The commissioners brought up the Jan. 16 fire at Vistra’s 300-MW energy storage facility at Moss Landing in Monterey County. The lithium-ion facility is one of the world’s largest battery energy storage systems. 

The fire, which prompted the evacuations of 1,200 people, is under investigation. Staff from CPUC’s Safety and Enforcement Division visited the site Jan. 22 as part of its probe.  

CPUC has previously listed nine other safety incidents at facilities since 2021, including four in 2024. In one incident in September 2024, a fire at a San Diego Gas & Electric facility in Escondido prompted evacuations.  

Evacuations also were ordered in May 2024 during a fire at REV Renewables’ Gateway Energy Storage facility in Otay Mesa.  

“The broad effect of updating this general order is to extend existing safety standards for generation assets to grid scale energy storage systems, including grid scale batteries, this update will support the CPUC role in advancing battery safety and will help to keep Californians safe,” Reynolds said. 

CPUC also noted the importance of storage in California’s transition from fossil fuels.  

“Battery storage systems are one of the key technologies California relies on to enhance reliability and reduce dependency on polluting fossil fuel plants,” the news release stated. 

NY Sells First Build-Ready Site for Renewables

A former iron mining operation once considered the largest of its type in the world has a new distinction: It will host the first site auctioned in New York’s Build-Ready program for large-scale renewables. 

The New York State Energy Research and Development Authority announced March 13 that CleanCapital had won rights to build and operate a 12-MW solar array in Benson Mines in the Adirondack Mountains region. 

Build-Ready is designed to address multiple state policy goals, including renewable energy development and brownfield reuse. 

NYSERDA assesses the viability of sites suggested for the program, then works with the landowners to design a customized benefits package and to advance the design, permitting and interconnection processes, then offers it as ready to construct. Ideally, this offers prospective developers a much-simplified path compared with starting from scratch on their own. 

The pre-auction process still can be lengthy, however. The Benson Mines project was announced in April 2021 with a planned early 2024 auction date, for example. And it initially was envisioned as a 20-MW project but was scaled back to avoid the need for system upgrades. 

NYSERDA said it has screened more than 5,000 sites and moved only a handful into more-advanced stages of potential development. Just three other sites besides Benson Mines are listed as having reached Build-Ready status: a former landfill, the grounds of an airport and an unused city property. 

Benson Mines began mining in the 1800s. It was a powerhouse for the region’s economy in its day, ranking as the world’s largest open pit iron mine by 1950. But it closed in 1978, leaving one more cluster of crumbling industrial structures in a region where tourists and seasonal residents far outnumber industrial workers. 

The former mine has been cleared of the rusting relics. Benson Mines now runs a 1,500-acre timber operation there, and sells aggregate crushed from the estimated 60 million tons of rock on site. 

The solar array will be placed on a tailings pile and is a good fit for the long-term goals for the site, company President Stuart Carlisle said in a news release: “This project has allowed us to put an underutilized portion of the Benson property back into productive use, bringing new investment, infrastructure development and economic benefits to the local community.” 

It will be one of the largest photovoltaic projects in the Adirondack Park, which with its highly regulated land use and rugged wilderness terrain does not lend itself to massive solar arrays. 

In a telling bit of geography, the state’s forest ranger training academy is held just down the road. 

But more importantly, a National Grid substation is even closer. 

NYSERDA President Doreen Harris said as the first of its kind, the Benson Mines project has value beyond its 12 MW of carbon-free power generation capacity: “We have now completed our first auction and are supporting the transformation of this underutilized site into something that is, in fact, build-ready. The Build-Ready program is helping to reimagine sites across the state so that communities can benefit from these otherwise-abandoned spaces.” 

CleanCapital will finance, construct, own and operate the project and has entered into a 20-year Renewable Energy Certificate agreement with NYSERDA. 

ISO-NE Gives Updates on Prompt, Seasonal Capacity Market Changes

ISO-NE provided stakeholders with a high-level overview of its proposed prompt capacity market design and discussed several other aspects of its capacity auction reform (CAR) project at a two-day meeting of the NEPOOL Markets Committee on March 11 and 12.

The CAR project aims to transform the region’s Forward Capacity Market, with auctions held over three years prior to each yearlong capacity commitment period (CCP), into a prompt and seasonal capacity market, held a month or two prior to each CCP, which would be split into summer and winter periods with separately procured capacity. (See ISO-NE Refines Scope, Schedule for Capacity Auction Reforms.)

Chris Geissler, director of economic analysis at ISO-NE, said the RTO would run the first prompt auction in April or May 2028 for the CCP beginning on June 1, 2028. It would finalize resources’ qualified capacity values in early 2028.

New resources would need to be in service prior to the auction to sell capacity, Geissler said. One of the motivations behind the prompt auction format is to eliminate “phantom entry,” in which an in-development resource secures a capacity supply obligation (CSO) but does not come online in time for the CCP.

Geissler said ISO-NE would provide “as much opportunity for new resources to demonstrate being in service as possible.” The RTO would allow non-commercial resources to participate in auction qualification and intends to set the latest possible deadline for resources to demonstrate they have achieved commercial operation.

He emphasized that the fundamentals of the demand curve and bid formulation will stay the same in a prompt market.

“Under either a forward or a prompt auction, a resource’s competitive capacity offer price should consider the incremental costs associated with taking on a CSO,” Geissler said.

He noted that some costs that would be included in offers in a forward auction — such as investment costs for a new resource — could not be included in offers in a prompt market. While this could lower some offer prices, Geissler said he does not expect this to lower overall market prices.

“Resources that are considering investment costs will only incur those costs if they expect to recover them via the markets, whether those markets are forward or prompt,” Geissler said. “We would therefore expect similar quantities of capacity to be sold in a forward or prompt market, producing comparable capacity prices.”

Seasonal Market Update

Jennifer Engelson, supervisor of resource qualification at ISO-NE, provided additional information on the RTO’s plans for the seasonal divide of the CCP.

ISO-NE would split the annual CCP into six-month summer and winter seasons beginning and ending at the ends of April and October, respectively. These periods would be aligned with the seasons used in NYISO’s capacity market. ISO-NE would run separate seasonal auctions for the next CCP each spring.

Dividing the CCP into two seasons is intended to help ISO-NE mitigate growing winter reliability risks, driven by heating electrification and gas supply issues. While ISO-NE considered using more than two seasons, it determined that “two longer seasons with clear peaks would be more economically efficient for the region” because of the concentration of risks in the winter and summer, Engelson said.

Resource Deactivations

Under ISO-NE’s existing tariff, the resource retirement process is tied to the FCM, and resources planning to retire signal their intent about four years prior to their exit from the market.

Because a prompt auction would provide little time to address potential system issues caused by the retirement, ISO-NE plans to decouple the retirement process from the capacity market. (See NEPOOL Markets Committee Briefs: Feb. 11, 2025 and ISO-NE Introduces Proposed Resource Retirement Changes.)

Under the new process, deactivation notices would be due two years prior to each CCP. Notices would be binding and set off a review process to evaluate potential reliability and market power issues created by the resource’s retirement.

The reliability review — triggered for all resources with more than 20 MW of capacity — would include an evaluation of local transmission security. If issues are identified, ISO-NE could retain the resource through an out-of-market agreement. The RTO has said repeatedly it plans to consider resource retentions only to address local transmission security issues and will not retain resources for energy security.

To evaluate and mitigate market power, the ISO-NE Internal Market Monitor would review deactivation submissions “to determine whether the retirement is justified by economics or potentially motivated by benefits to a portfolio.”

Retiring resources would be subject to a conduct test to evaluate the economics of the retirement and a net portfolio benefits (NPB) test to assess whether retiring a profitable resource would increase revenue for the resource owner’s remaining portfolio.

“When a participant fails both the conduct and the NPB test, this suggests that the deactivation represents an exercise of market power,” said Zeky Murra-Anton, an economist at ISO-NE.

When market power is identified, ISO-NE plans to impose a 1.5-times multiplier on the projected increase in portfolio-wide revenue caused by the retirement. Murra-Anton said this multiplier is intended “to effectively deter deactivations for market power purposes without being excessively punitive.”

Treatment of Repowering Resources

ISO-NE also discussed how the CAR changes would affect resource repowering efforts.

The RTO’s interconnection procedures and FCM have mechanisms for evaluating changes to existing resources. Both the interconnection process and the FCM are undergoing major reform efforts, which will necessitate changes to the treatment of resource repowering.

Alex Rost, director of transmission services at ISO-NE, assured stakeholders that the RTO is committed to retaining “a path for repowering projects as the CAR design is set.”

“At a fundamental level, [interconnection customers] with repowering projects that seek to change/replace an original generating facility with a new generating facility, where the new generating facility assumes its needed interconnection service from the original generating facility, will maintain the ability to do so,” Rost wrote in a memo issued prior to the meeting.

NEPGA Tie Benefits Concerns

Bruce Anderson, general counsel for the New England Power Generators Association, presented some concerns about how ISO-NE’s capacity market accounts for tie benefits, which the RTO has defined as “the assumed amount of emergency assistance from neighboring control areas that New England could rely on … in the event of a capacity shortage.”

“The current market design ‘assumes away’ approximately 2,000 MW of capacity demand based on the belief that system energy from neighboring control areas is equivalent to ‘firm capacity,’” Anderson said, adding that these assumed tie benefits reduce the region’s installed capacity requirement.

Because tie benefits are not subject to the same obligations, audits and nonperformance charges as resources with CSOs, Anderson said treating tie benefits as “equal to actual capacity” creates risks of price suppression and capacity under-procurement.

Anderson added that price suppression increases the likelihood of “uneconomic retirements of resources important to system reliability.”

He said NEPGA will propose alternatives intended to improve ISO-NE’s tie benefits accounting methodology in the coming months.

Flexible Response Services

Also at the meeting, Matthew White, vice president of market development and settlements at ISO-NE, discussed the RTO’s long-term plan to improve its flexible response capabilities “to address greater operational uncertainties with an increasingly weather-dependent resource mix.”

In a memo issued prior to the meeting, White wrote that ISO-NE is “assessing a combination of new probabilistic forecasts and enhancements to the co-optimized energy and reserve markets.”

On March 1, ISO-NE launched a new day-ahead ancillary services market, which procures reserves to help grid operators cope with load variability and fill any energy gaps that arise between the day-ahead energy market and the load forecast. (See FERC Approves ISO-NE’s Day-Ahead Ancillary Services Initiative.)

Looking forward, ISO-NE is considering how to improve its real-time forecasting of ramping needs and may look to procure “dynamically determined incremental quantities” of 10- and 30-minute reserves and new longer-response reserve products, potentially in the 60- or 90-minute range, White said.

“New England’s power system is becoming increasingly dynamic, and extending conceptually familiar market designs with new probabilistic modeling capabilities appears to be a promising next step to reliably address increasing operational uncertainties,” White wrote.

“By carrying less incremental reserves when net load uncertainty or ramping needs are forecast to be low, unnecessary costs can be avoided; and by increasing incremental reserves when net load uncertainty or ramping needs are forecast to be higher, reliability can be maintained,” he added.

Fall Markets Report

Finally, the IMM’s Kathryn Lynch presented the Monitor’s fall quarterly markets report, which found that wholesale market costs during the quarter increased by 8% relative to fall 2023, up to nearly $1.5 billion in total costs.

Market costs increased despite a 13% decrease in natural gas prices and the lowest recorded fall season power demand.

The increase was driven by increased emissions costs for the Regional Greenhouse Gas Initiative and decreased imports and domestic nuclear generation, Lynch said. Average hourly nuclear generation decreased by about 423 MW compared to the prior fall “due to planned and forced outages,” while net imports dropped by an hourly average of 892 MW because of “dry weather in Québec and a nuclear generator outage in New Brunswick.”

Overall, market pricing outcomes were competitive, and “there was no evidence of impactful capacity withholding,” Lynch said.

Ahead of Crossover Day, Energy Bills Stalled in Md. General Assembly

State energy policy was supposed to be a top priority for the Maryland General Assembly’s 2025 session, but it appears to be taking a backseat to more pressing fiscal matters.  

With lawmakers in Annapolis mostly focused on producing a budget that can fill the state’s projected $3 billion deficit, many energy bills appear stalled in advance of “crossover day” on March 17, when bills introduced in one house must be approved in that chamber and cross over to the other.  

Dozens of energy bills have been introduced in both houses, but few have taken the first step of being approved by their appropriate committees, let alone moved to a floor vote. 

The budget is taking up a lot of time and “mental space,” said Kim Coble, executive director of the Maryland League of Conservation Voters. But the bigger issue is the complexity of the energy issues addressed by the bills state delegates and senators are considering. 

“There’s a lot of need to educate members and to bring them along, and the number of bills and topics that are trying to be addressed [is] major,” Coble said. “They are getting lots of phone calls from constituents about their electricity bills; they’re getting lots of calls about clean energy and trying to balance it all.  

“So, I am trying to stay optimistic,” she said. “The fact that things haven’t moved yet is not a delay tactic. It’s because it is a tough, complicated topic that they want to get right.” 

Both Coble and Katie Mettle, policy principal for Maryland at Advanced Energy United, also note that any bills not crossing over by March 17 still can move forward in the legislature via a special vote in the Rules Committee in either house. 

“I think they honestly just are not sweating the crossover deadline for their top, most important bills, because they know they can take longer if they want to,” Mettle said. “They just want to make sure that everything is to their liking. … There [are] still negotiations going on.” 

Coble pointed to the Abundant, Affordable Clean Energy (AACE) Act (HB 398, SB 316), sponsored by Del. Lorig Charkoudian (D) and Sen. Benjamin Brooks (D). The bill’s multiple provisions include a mandate for the Maryland Public Service Commission to open two rounds of applications each for 150 MW of distribution-tied energy storage and 1,600 MW of front-of-the-meter, transmission-tied storage, as well as incentives for 3,000 MW each of utility- and small-scale solar projects.  

The bill also seeks to support the state’s existing nuclear plants via license extensions and zero-emission credits, and calls for coordinated planning for transmission to bring offshore wind energy to the homes and business that need it. It requires prevailing wage standards for workers employed on energy storage projects. 

The goal, Charkoudian said is “to ensure resource adequacy, with protecting ratepayers and with clean energy.” 

As of March 13, the bill was sitting in committees in both houses, but both Coble and Charkoudian said negotiations are underway to incorporate parts of AACE into another major bill, the Next Generation Energy Act, which is one of three major energy bills being supported by House and Senate leadership. 

The Leadership Package

Referred to as “the leadership package,” the three bills include: 

    • The Energy Resource Adequacy and Planning Act (SB 909), which would require the PSC to establish an Integrated Resource Planning Office, which would conduct a 25-year comprehensive energy forecast aimed at meeting state clean energy and emission reduction goals, while ensuring reliability and affordability. 
    • The Renewable Energy Certainty Act (SB 931), which would set rigorous standards for solar and storage projects seeking a certificate of public necessity and convenience from the PSC, to ensure careful siting and community engagement. The bill also would prohibit city or county governments from passing zoning or other laws blocking solar and storage projects. 
    • The Next Generation Energy Act (SB 937), which would promote the development of nuclear energy, and the extension of the licenses of existing reactors, as a matter of state policy, while also encouraging regional collaboration between states to share costs on the development of new reactors. The bill also calls for the procurement of 3,100 MW of “dispatchable energy generation capacity” and a temporary expedited permitting process for these projects. 

Advocates like Mettle have raised red flags about those 3,100 MW of dispatchable generation, which she presumes would be natural gas. “The thing about gas [is] we just don’t need it,” she said. “I just don’t think from a technological standpoint or an economic standpoint that it’s remotely necessary.” 

Mettle would first like to see PJM clear the solar and storage projects sitting in its interconnection queue and then ensure the state is ready to support projects as they are approved for interconnection. She supports SB 931 and the AACE Act as ways to “turbocharge” the solar and storage industry.  

Both Charkoudian and Coble are concerned any expedited permitting will strip out requirements for community engagement and attention to environmental justice issues. 

Charkoudian is working on amendments that will incorporate parts of AACE into SB 937. “So, I think what you’re going to see, when they kind of come out or start going through the process in committee, is just a lot of amendments to add, to improve, take the best ideas and move them on,” she said. “I think it’s possible that that won’t happen before crossover.” 

Crossovers So Far

The Maryland Clean Energy Center tracks energy and climate bills in the General Assembly and issues weekly reports. As of March 13, the following bills have crossed over: 

    • SB 37, another Charkoudian bill, would require utilities to report to the PSC on their votes at all PJM stakeholder and other meetings. Its House counterpart, HB 121, still is in committee. 
    • HB 270 calls for a state-level data center impact analysis report to be developed by the Department of the Environment, the Maryland Energy Administration and the University of Maryland School of Business, and to be submitted to the governor and General Assembly by Sept. 1, 2026. 
    • SB 120 and HB 4, approved in both houses, prohibits community or condo associations from putting restrictions on solar installations that would increase the cost of the projects by 5% or reduce their electrical output by 10%. 
    • HB 61 would require the design for any new school construction or major renovation to evaluate installing solar parking canopies.  
    • SB 399 would allow transmission lines to be run through certain state-designated “wildlands.”  

Maryland LCV is opposing the bill, which Coble said is tailored to the Mid-Atlantic Resiliency Link, which is being developed by NextEra Energy. Wildlands are particularly pristine areas and account for less than 1% of the state’s land, she said. 

“This would be the first time the state of Maryland has ever opened up wildlands from new transmission lines. So that, in and of itself, is bad,” she said. “These wildlands are pretty special lands, and they do need and deserve extra consideration.” 

EPE’s Markets+ Decision ‘Not Transparent,’ NM Regulators Say

A New Mexico Public Regulation Commission workshop March 13 aimed to restore trust between the commission and El Paso Electric after the utility’s surprise announcement in January that it planned to join SPP’s Markets+.

The PRC held a series of workshops last year to explore issues related to two competing day-ahead markets in the West: Markets+ and CAISO’s Extended Day-Ahead Market.

During a workshop in August, El Paso Electric representatives said they hoped to conduct further studies comparing benefits of the two markets. They indicated they’d present results of the new studies to the commission before choosing a market, a decision they expected to make in the third quarter of 2025, according to Commissioner Gabriel Aguilera.

When EPE announced its choice of Markets+ on Jan. 24, many were taken by surprise — including the New Mexico commissioners. (See El Paso Electric to Join SPP’s Markets+ in 2028.)

“The last thing I wanted was a surprise filing or announcement by a utility that they’re joining ‘X’ market,” said Aguilera, who has been leading the workshops. “EPE’s announcement surprised me. And it surprised a lot of people.”

“It was not transparent,” Aguilera added. “And I really hope to bring transparency back into this by having this workshop.”

Commission Chair Pat O’Connell said the workshop was important to “reset” the relationship between the PRC and El Paso Electric.

“When you say you’re going to do something, you’ve created the expectation. And then when you don’t do it, it breaks the trust,” O’Connell said.

Emmanuel Villalobos, EPE’s director for market development and resource strategy, said the utility had “misrepresented ourselves” in saying the new study results would be shared before making a market announcement.

“We are deeply sorry for that miscommunication,” Villalobos said.

In addition to hosting the series of workshops last year, the PRC issued a set of “guiding principles” in late October intended to help utilities make a day-ahead market choice. (See NM PRC Issues ‘Guiding Principles’ for Electricity Market Participation.)

Brattle Group Study

During the workshop, Brattle Group principal John Tsoukalis presented results of a recent study completed for El Paso Electric, which looked at benefits of day-ahead market participation if EPE joined Markets+ and Public Service Company of New Mexico (PNM) joined EDAM.

PNM announced its choice of EDAM in November. (See PNM Picks CAISO’s EDAM.)

The new study was a follow-up to Brattle’s previous study that projected annual benefits for EPE of $19.1 million a year if both New Mexico utilities joined EDAM, versus $9.1 million if they joined Markets+. (See Brattle New Mexico Study Shows EDAM Benefits Outpacing Markets+.)

The updated study projected annual benefits of $6.6 million for EPE if the utility joins Markets+ but PNM goes with EDAM.

But Brattle’s figures changed when the consultant incorporated estimates of the value of the Eddy County tie, a 345-kV transmission line that connects EPE with the Eastern Interconnection. With the Eddy County tie value factored in, EPE’s annual benefits would be $19.3 million if both New Mexico utilities join EDAM, $20.1 million if they join Markets+, and $18.8 million if EPE goes with Markets+ while PNM joins EDAM, Brattle projected.

With the new study showing a smaller difference in monetary benefits among the different market scenarios, EPE weighed other factors in its market decision, including governance, reliability and resource adequacy. And Markets+ seemed to be a better fit.

“Market participation must be viewed holistically, considering both financial and operational realities,” EPE said in a presentation.

Data Centers’ Need for Speed Clashing with Plodding Pace of Regulation

WASHINGTON — Even if demand forecasts from new data centers are twice as large as what ends up being built, the growth is going to be at a scale where the power industry’s regulations need to change to keep up with it, former FERC Commissioner Allison Clements said at the Energy Bar Association’s Northeast Chapter Winter Summit on March 12. 

“You have a desire for AI dominance, and then you still have this slow-churning, difficult regulatory process to get through,” said Clements, who since leaving FERC has started working part time at ASG, which helps build data centers. 

The power industry is among the most regulated in the country, and anytime a decision has to be made or money spent, it has to go through at least couple of proceedings, she added. The exuberance around data center expansion and artificial intelligence’s potential is starting to clash with that. 

“The reality is, whether or not Stargate is actually going to deploy $500 billion in the U.S. depends on all those regulatory check marks,” Clements said. “Nobody has stood up in this moment of exuberance and said, ‘I’m going to spend the money no matter what. That money is still going to go through each individual company and investment community, right? You’re still going to have to check all these boxes.” 

In the next few years, as Orders 2023 and 1920 are only being implemented; new natural gas turbines are taking five years to get installed; and clean, firm power supply options are not commercially viable, the industry is going need to get creative to serve new large loads, Clements said. 

“This isn’t a technological problem; it’s a political will, operational kind of structural/institutional issue,” Clements said. 

The existing grid can have its capacity maximized with new software and hardware; interconnections could be optimized across seams; and the industry could look to the new large customers themselves to help, she added. 

FERC Chair Mark Christie is split by the issue, with Clements saying he understands the concerns about holding other customers harmless from the infrastructure expansions required by large data centers but he also sees the other side. “He’s very clear about the political pressure and the market pressure to get something done, to unlock the jam.” 

Co-location has dominated the issue at FERC so far, with Christie saying he wants a proposed rulemaking, issued at February’s open meeting, to be finished quickly. (See FERC Launches Rulemaking on Thorny Issues Involving Data Center Co-Location.) 

The nuclear plants in PJM initially were paid for by ratepayers, and many wound up being subsidized to keep running by their states as cheap shale gas ate into their profits, but Clements noted they often are in fully restructured states. 

“Now those resources have found better commercial opportunities,” Clements said. “The way the market, if it was a fully functioning market, should work is that we facilitate those opportunities.” 

Co-located load can either be served entirely by its unit or get backup from the grid, said Jennifer Mansh, Talen Energy senior vice president of regulatory affairs. While the concept has been pursued around PJM and in other markets, so far Talen’s Susquehanna nuclear plant in Pennsylvania is the only one to have a co-located data center. 

FERC rejected an expansion of that co-located data center when it launched a broader look at the issue, and Talen is challenging the rejection in court, she added. The industry should get more clarity as PJM and other parties respond to the rulemaking and its dozens of questions in the next week, Mansh said. 

“There’s an acknowledgement that we need to move urgently, but then you see so many questions about the detail of how this might work,” said Carrie Allen, deputy general counsel for Constellation Energy, referring to FERC’s co-location proceeding. “And I would just suggest to the commission, if I had a chance to talk to all of them, that not every single one of those 39 questions needs to be addressed … in order to figure out the broader contours of a policy framework.” 

FERC says it wants to move quickly on the issue, but so far that has not been the case, said Nicholas Gladd, partner at Wilson Sonsini Goodrich & Rosati. “I also think what’s on their minds, based on that lengthy list of questions, is they want to do something big and great because they think this is a big problem,” he added. 

But not all of those questions need to be answered immediately, he said. Gladd would prefer to let the market work and bring its own solutions to the fore, rather than have too many top-down regulations around co-location. PJM is facing some resource adequacy issues, but throttling down large loads does not get to the markets’ root problems, in addition to being bad for national security, he said. 

“Given the capacity market has those flaws, and the interconnection queue has those flaws, the fact that there’s new large growth is an opportunity, not a risk,” Gladd said. “What better investment signal, or what better factor to indicate that an investor signal is robust, than hundreds of megawatts of load?” 

After years of flat load growth in most of the country that came with many traditional, thermal generators retiring and replaced by intermittent renewables, the growth in data centers has exposed some underlying tensions on the grid, said Mike Twomey, senior consultant for Charles River Associates. 

“This increased demand for electric service by data centers in many parts of the country is causing a lot of friction on issues that have been largely, I guess the right word is … ‘underground’ for the last 20 years,” Twomey said. 

Some parts of the grid might even be incapable of serving massive new load unless they bring supply along with the new demand, he added. Many of the data center developers want to be supplied by clean energy, but if they need it, they will not hesitate to supply a facility with natural gas generation, Twomey said. 

While some data centers can shop around for the best places to plug into the grid, that will not be possible in every case because of issues around latency, said Michael Armm, managing director of BlackChamber Group. Latency refers to the lag that happens when data is sent across long distances, which requires proximity for some applications. 

The need for latency has kept the sector growing in Data Center Alley in Virginia and nearby. Latency will be an even bigger issue as autonomous vehicles move beyond the pilot project stage. 

“Thinking about autonomous vehicles, if you’re at an intersection and there’s four cars and one’s going to start moving, the other one is going to react to it; you can’t wait for that signal to go 500 miles away to a data center to … go through an algorithm and [be] sent to the car next to you,” Armm said. “That timing is much faster, so you’re going to see more edge computing.” 

Autonomous vehicles could require smaller, distributed data centers sprinkled around cities that can handle a few blocks worth of traffic, he added. 

FERC Approves New York Transco’s Formula Rate, Sets ROE for Hearing

FERC on March 11 approved including additional expense accounts in New York Transco’s new company-wide formula rate over the protests of the New York Public Service Commission and New York City, but set its proposed return on equity for hearing and settlement procedures (ER25-885).

Transco was formed by Consolidated Edison, Avangrid, National Grid and Central Hudson Gas & Electric in 2014 in response to a state solicitation for transmission projects in case the Indian Point nuclear plant retired (which it did in 2021). The company’s rate formula and ROE for those Transmission Owner Transmission Solutions (TOTS) projects were approved, but it has had to submit project-specific cost recoveries for each new project since then.

The company proposed a new formula rate across all of its projects and a company-wide ROE of 10.9%. Included in the rate were expense accounts under FERC’s Uniform System of Accounts related to general transmission operations and maintenance, including interconnection service studies.

Transco said these expenses were already included in its project-specific rates but under a different account for third-party vendors. It argued “that its significant growth suggests that it may be more efficient and cost effective if [it] were to open its own control center and utilize its own employees to perform these and other tasks.” Other NYISO transmission owners have the accounts as part of their approved formula rates, it contended.

The PSC argued that the rate change had not been vetted enough to ensure it would not raise rates for consumers. New York City and Multiple Intervenors, a group of industrial consumers, jointly claimed that Transco was improperly booking the expenses in the third-party vendor account, allowing the company to improperly collect transmission operating expenses via its formula rate.

FERC dismissed these arguments. In response to the PSC, FERC noted that Transco was not seeking to raise its rates through the new accounts, but to change the accounts under which certain expenses are booked. “We find no evidence in this record to conclude that this change will necessarily lead to cost increases,” it said.

The commission also said that the city and Multiple Intervenors’ concerns were beyond the scope of the proceeding. “Challenges to costs included in the formula rate may be raised in the annual update process in accordance with New York Transco’s formula rate protocols,” it said.

FERC found that Transco’s proposed base ROE was not demonstrably just and reasonable and set the matter for hearing and settlement judge procedures.

The company said the new ROE would apply to its existing transmission assets, including TOTS, and any future projects it develops and owns. This excludes the Propel NY Energy project, in development with the New York Power Authority, because its cost recovery is the subject of a separate settlement agreement.

Transco submitted testimony from an expert witness, which determined the zone of reasonableness to be 9.08 to 12.72%, resulting in a 10.9% midpoint. For comparison, Transco’s ROE for TOTS is 9.65%.