CARMEL, Ind. — MISO said its next capacity auction in spring 2026 will feature more rigorous testing for its demand response that registers to provide capacity.
The grid operator said it will discontinue its practice of allowing its demand resources to provide hypothetical, mock tests as a performance indicator, except where state regulations might allow, for the 2026/27 Planning Resource Auction.
The end of mock testing follows MISO enforcing stricter registration requirements ahead of the 2025/26 capacity auction offer window, which ran from March 26-31. (See Following DR Exploitation, MISO Announces Stiffer Requirements Before Capacity Auction.) Taken together, the more unyielding rules are a response to five recent instances of disciplinary action from FERC regarding companies deceitfully offering demand response in MISO’s capacity auctions. (See Voltus Agrees to $18M Fine to Settle DR Tariff Violations in MISO.)
“There are concerns about the mock test, how it’s being used and the information around it,” MISO Market Design Economist Joshua Schabla said during an April 9 Resource Adequacy Subcommittee. “Frankly, it’s something we’re uncomfortable with.”
Schabla said at times, mocks tests are “little more than a function in an Excel file.”
MISO said all demand resources that plan to provide capacity beginning in June 2026 should be prepared to prove their capabilities via actual demand reductions to at least 50% of their stated seasonal values or down to a firm service level, if they specified one. Tests that show less than a 100% result need to be backed up with documentation explaining why a full reduction wasn’t possible.
MISO said it wasn’t foreclosing the possibility that mock tests won’t ever be allowed among its demand response fleet in the future. So far, the testing requirement would apply only to the 2026/27 capacity auction.
Schabla said MISO plans to require a real test of its load modifying resources (LMRs) once per year. The tests can be completed on the resource owner’s time and would count as one deployment. MISO’s LMRs currently are bound to deploy if necessary five times apiece in the summer and winter and three times apiece in spring and fall.
Erik Hanser, of the Michigan Public Service Commission, said the new testing requirements won’t give resource owners much time because real power tests for the 2026/27 planning year begin in summertime up until LMR registration for the 2026/27 Planning Resource Auction begins Dec. 15.
Schabla said MISO has not called LMRs since December 2022. The three-year downtime provides further justification that it’s time for LMRs to make a demonstration of their abilities, he said.
“We need to see something positive, that this demand resource is real and can perform to requirements. … We need to see that it can do what we’re paying it to do,” Schabla said.
MISO Independent Market Monitor David Patton said terminating the mock test practice is critical because the IMM has noticed mock test results submitted from LMRs with reduction levels that are “difficult to believe.” He said in some cases, LMRs appeared to fail a real power test and then decided to conduct a mock test instead. Patton said at this point, MISO likely is hosting and paying several megawatts of LMRs that either aren’t real or can’t achieve what they say they can.
Patton said it’s “entirely fair” for MISO to provide notice now that it will enact stricter testing requirements, even if it doesn’t yet have FERC approval to end mock testing. He said LMRs should use the time to prepare for actual testing.
Patton said MISO’s proposed 50% benchmark testing is “far too lax.” MISO pays LMRs too much to accept a 50% performance, Patton argued.
“We’re going to continue to talk to MISO and stakeholders about that dimension of this proposal,” he said.
MISO to Allow LMR Capacity Substitutions
MISO also said it will permit load modifying and demand response resources to replace their auction-cleared capacity with other, uncleared capacity in the event they’re unable to deliver promised load reductions. The change would also take effect in the 2026/27 planning year auction.
MISO allows its more traditional resource types to replace zonal resource credits, but that allowance doesn’t extend to demand response resources and LMRs. In MISO, resources’ accredited capacity values are converted to zonal resource credits that are used in auction trading.
MISO said it will allow LMRs to make similar, limited replacements if: the end-use customers it contracted for reductions must terminate contracts; regulations prevent the LMR from performing; or a change in ownership occurs in an end-use facility that the resource was banking on to shrink load. For behind-the-meter generation registered as LMRs, MISO said a planned outage longer than 31 days or a catastrophic outage would present the opportunity for replacements.
MISO said in all cases, it may require documentation or evidence.
Schabla said resources “must have a good reason to replace” and must be prepared to explain their situations to MISO and the IMM.
MISO staff said they intentionally drafted narrow criteria for replacement conditions so auction commitments remain binding, and market participants don’t have a route to avoid obligations.
Some stakeholders have said MISO’s replacement proposal is encouraging and will be helpful if facilities close and zonal resource credits need to be replaced.