MTEP 24 Reaches $6.7B; MISO Ending Rush Island Reliability Agreement in Mid-October
MISO’s 2024 transmission planning cycle is shaping up to include 459 new projects totaling $6.7 billion.
Ameren
Ameren: MISO Missouri Capacity Shortfall Likely Inconsequential
Ameren executives have reassured shareholders that Missouri’s capacity shortfall beginning this summer is no cause for panic.
Massman Construction Co.
Court: Ameren Still Without Remedy for Years of Rush Island Air Pollution
After more than two years, Ameren Missouri has not yet delivered suitable redress for more than a decade’s worth of Clean Air Act violations via its Rush Island coal plant.
Ameren
Ameren Files to Recoup Rush Island Closure Costs from Customers
Ameren Missouri appears to be making good on plans to close its Rush Island coal plant, which has racked up multiple Clean Air Act violations.
Ameren Missouri
FERC Approves Lower MISO Reliability Payments to Ameren Coal Plant
FERC OK'd a settlement to reduce payments to a Missouri coal plant under its system support resource agreement with MISO.
Ameren Missouri
MISO Poised to Extend Missouri Coal Plant’s Life
MISO announced that it will likely be forced to renew the system support resource agreement of a Missouri coal plant for almost two more years.
Power Techniques Inc.
FERC: Rush Island Plant’s Extension Essential to MISO Reliability
FERC approved an agreement that will keep an Ameren Missouri coal plant online past its planned retirement date to maintain MISO grid reliability.
McCarthy Construction
Hearing May Settle Ameren, DOJ Clash over Coal Plant
A federal judge has scheduled a hearing next month to settle a dispute between Ameren and the DOJ over the closure of a St. Louis-area coal plant.