MISO Transmission Expansion Plan (MTEP)

Great River Energy
MISO to Re-examine Schedule for Reviewing Expedited Tx Projects
MISO’s Planning Subcommittee will tackle possible modifications to expedited project reviews, the process that allows transmission developers to begin construction earlier than usual.
Grid North Partners
FERC Approves Dairyland Incentives for Minn.-Wis. Transmission Line
FERC OKd Dairyland Power Coop’s requested rate incentives for the Wilmarth-North Rochester-Tremval project, a 169-mile line spanning Minnesota and Wisconsin.
© RTO Insider LLC
MISO Year in Review: 2023 — and Likely 2024 — Dedicated to Deflecting Reliability Issues
MISO juggled several projects over 2023 designed to fend off imminent reliability problems and will keep up the multitasking in 2024.
© RTO Insider LLC
MISO Board Approves $9B MTEP 23; Members Deliberate on New Expedited Review Rules
The MISO board approved the $9 billion, 572-project 2023 Transmission Expansion Plan, which contains the most expedited project reviews ever.
© RTO Insider LLC
MISO to Focus on LRTP, Congestion for MTEP 24
MISO says its 2024 Transmission Expansion Plan will look much the same as last year’s MTEP.
MISO
3 MISO Sectors Vote to Recommend MTEP 23, Majority Silent
Just three of MISO’s 11 member sectors voted to support the RTO’s $9 billion 2023 Transmission Expansion Plan.
© RTO Insider LLC
FERC OKs MISO Removal of Annual Reviews for Long-term Tx Projects
MISO is off the hook as far as having to conduct annual cost-benefit analyses for its major transmission projects, FERC has ruled.
Malouf Construction
MISO Postpones Meeting for More Analysis on Entergy Expedited Substation Work
MISO announced it must conduct more analysis on three new substations proposed by Entergy for expedited treatment in the RTO’s annual planning cycle.
© RTO Insider LLC
MISO: Expect More Expensive Annual Transmission Packages
MISO’s lead planners told the Board of Directors that more expensive annual Transmission Expansion Plans will become the norm, saying MTEP 23’s $9.4 billion package is a sign of future scattershot load growth in the footprint.
Entergy
MTEP 23 Catapults to $9.4B; MISO Replaces South Reliability Projects
MISO's $9.4 billion 2023 Transmission Expansion Plan  makes for its largest-ever annual planning cycle and includes a substitution for two MISO South reliability projects.