A recently filed proposal by ISO-NE to increase the collateral requirements for generators with capacity supply obligations has received strong pushback from the New England Power Generators Association.
FERC partially reversed a 2023 order allowing PJM to modify a parameter for the 2024/25 Base Residual Auction to avoid a substantial increase in capacity prices in the DPL South transmission zone.
The Operating Committee was briefed on one of NYISO’s most humdrum winters, characterized by high temperatures, low gas prices and below-average loads.
The 3rd Circuit vacated FERC’s order allowing PJM to revise a capacity market parameter for the DPL South zone after the 2024/25 auction had been conducted but prior to the publication of its results, ruling that it constituted retroactive ratemaking.