Search
`
November 23, 2024

Artificial Island

PSEG Wins $300M Artificial Island Project
PJM planners today recommended PSE&G be awarded the contract to fix the Artificial Island stability problem with a new 500kV line at a cost of about $300 million.
Contestants Make Last Pitch for Artificial Island Prize
Sea turtles, sturgeon, wetlands and shipping accidents — transmission developers seeking the contract to fix the Artificial Island stability problem invoked all of them and more last week in arguments against their competitors.
Delaware Unhappy with Artificial Island Cost Allocation
By David Jwanier With PJM planners nearing a proposed fix for the Artificial Island stability problem, the issue of who will pay for the project took center...
Planners Near Artificial Island Pick
PJM is close to naming a developer to fix the Artificial Island transmission stability problem, with LS Power’s proposal for an overhead crossing of the Delaware River holding on as the lowest-cost choice.
Artificial Island Price Tag Rising?
The solution to the Artificial Island transmission stability problem may be more costly than originally estimated, PJM officials said last week.
PJM Narrows Artificial Island Proposals
PJM has narrowed the list of favored solutions to the Artificial Island stability problems, officials told the Transmission Expansion Advisory Committee.
Eight Companies Vie for Artificial Island Project
The diversity of solutions and costs proposed for Artificial Island validates FERC’s view that competition reduces costs and increases innovation.
PJM: We’ll Be Cautious on Transmission Project Disclosures
PJM “will err on the side of caution” in disclosing details from transmission developers’ project proposals when implementing their first proposal window.
FERC Orders Rules on Geomagnetic Disturbances
FERC Said that the electric transmission system needs more protections against geomagnetic disturbances like the 1989 solar storm that caused the collapse of the Hydro-Quebec grid.

Want more? Advanced Search