Search
`
August 15, 2024

Maryland PSC Approves Grid Upgrades for New Data Center

Maryland is setting itself up to compete with Northern Virginia’s Data Center Alley with a 2,100-acre data center campus in Frederick County, and on July 31, the Maryland Public Service Commission granted a waiver for Potomac Edison Co. to install two 230-kV lines to help connect four data centers from the campus to a new substation. 

The 3-1 vote on the waiver allows Potomac Edison to begin construction on the lines in September without first requesting a certificate of public convenience and necessity (CPCN), a much longer and more expensive process.  

Commissioner Bonnie Suchman cast the single no vote, arguing the waiver could open the door for more waiver requests for similar line additions for more data centers, with other customers picking up the bill. 

Potomac Edison’s customers in Frederick County don’t need the upgrades at present, Suchman said. “Upgrades are only coming because of this new data center. … You’re going to get more data centers coming in, and more data centers are going to put more burdens on the system, and then you’re going to come to us for a waiver, and we’re going to sort of rush all this stuff through. 

“The data center may come or not, but the one thing I am seeing is an increase in the cost for the network that’s going to be borne by the ratepayer,” she said. 

According to commission staff, however, the project meets specific legal standards in the state’s public utilities code that require the PSC to grant the waiver: The new lines won’t require the utility to secure new property or rights-of-ways or to install bigger or taller structures for increased voltage or larger conductors. 

The Potomac Edison lines will be “loop lines” that run from an existing 230-kV line to a new substation to be built for the data center and then back to the main line. Each line will be 1,100 feet long and use the same type of wires as the existing line, and will include eight new poles, none of which will be taller than existing poles.  

The staff report also said the new lines and other system upgrades, including a switching station expansion, will mitigate potential thermal overloads and voltage violations the new data centers could cause on the main line, as identified by PJM. 

“PJM did that specifically for reliability reasons … not only to take into consideration [the data center’s] anticipated load, but the other load currently being served and to be served in that area, altogether about 1,350 MW,” said Joey Tsu-Yi Chen, corporate counsel for Potomac Edison. “We do not want to see a situation, in fact, cannot, where we have no more than 300 MW of load that would be interrupted by any particular criteria.” 

However, PJM spokesperson Jeff Shields said the RTO neither planned nor approved the two lines. Rather, FirstEnergy, which owns Potomac Edison, included the project in a supplemental filing to the RTO’s Transmission Expansion Advisory Committee in October 2023. 

Data Center Alley North?

Reliability aside, Chen told the commission the waiver was needed so the new lines could be built to meet the data center’s timeline. A full CPCN review would not meet “their timing needs for their project,” he said ― underlining the disconnect between digital and regulatory time frames, and Suchman’s concern Potomac Edison’s waiver request could be the first of many. 

Maryland has been promoting itself as a nearby, attractive alternative to Northern Virginia, home to hundreds of data centers and skyrocketing power demand. Gov. Wes Moore (D) rolled out the welcome mat in May when he signed the Critical Infrastructure Streamlining Act of 2024 (S.B. 474), waiving the need for data centers to get CPCNs for their fossil fuel-powered backup generators.  

The Frederick County data centers could provide a glimpse of what’s to come. The developer for the project is Rowan Digital Infrastructure, which provides “turnkey data center campus solutions” with “de-risked development timelines,” according to the company website. 

The data centers will cover about 145 acres in the larger, 2,100-acre Quantum Frederick data center campus being planned by developer Quantum Loophole. Rowan’s website describes its project as a multi-building facility with 300 MW of power to start and the potential to expand to 450 MW. 

The Frederick County site offers “near-term power interconnection dates [and] competitive power pricing … [and can] deliver the initial 300 MW by late 2025, providing a high-value alternative to the congested Ashburn corridor” in Northern Virginia. 

Quantum also has big plans for the site, which it intends to connect to its data center hub in Northern Virginia with a 40-mile fiber optic network ring. 

“At full capacity, the 34 conduits will hold more than 235,000 strands of fiber to transmit data between the two hubs in under one millisecond Round Trip Time (RTT),” a company press release said.  

Opposing Sides Want to Speed, Slow NY Cap-and-invest

Dueling visions for New York’s proposed cap-and-invest system are being offered as state officials continue the lengthy process of codifying its details.

Environmental advocates, alarmed by the state’s lagging progress toward its decarbonization goals, are calling for a robust scheme to be put in place as soon as possible.

Business, labor and industry representatives, alarmed by the escalating, yet still unknown costs of those decarbonization efforts, are calling for a pause to assess what realistically is possible and affordable in New York.

Both statements were issued July 30 and are keyed to the fifth anniversary of the state’s landmark Climate Leadership and Community Protection Act, signed into law in 2019.

The CLCPA mandates a 40% reduction of greenhouse gas emissions by 2030 over 1990 levels and an 85% reduction by 2050. Cap-and-invest is intended to incentivize carbon-emitting industries to reduce their emissions.

The CLCPA scoping plan finalized in December 2022 recommended the cap-and-invest system as one way to help achieve those goals.

Gov. Kathy Hochul (D) announced details of a cap-and-invest concept in early 2023.

The state Department of Environmental Conservation and the New York State Energy Research and Development Authority are developing the proposal. It still is a pre-proposal, having reached Stage 4 of an eight-step process that already has generated nearly 5,000 public comments.

Meanwhile, the clock is ticking.

NYSERDA and the state Public Service Commission on July 1 issued a draft report saying the state would miss the CLCPA target of 70% renewable energy by 2030, perhaps by a wide margin, thanks to a variety of factors both local and global. (See NY Expects to Miss 2030 Renewable Energy Target.)

An audit released July 17 by the Office of State Comptroller made the same point, and faulted the state for offering no estimate of what the overall effort would cost, or how much of that cost would fall on utility customers who already have some of the highest rates in the country. (See Audit Faults NY on Climate Act Progress.)

These delays and costs were cited in the competing wish lists issued July 30.

The Environmental Defense Fund and 28 like-minded organizations urged Hochul to advance an ambitious set of regulations as soon as possible:

“The health and safety of our communities and of future generations depends on bold leadership and meaningful action to implement and fund our nation-leading climate law. Our organizations call on Governor Hochul to propose draft regulations for a cap-and-invest program that delivers on the promise and requirements of the CLCPA without further delay.”

Kate Courtin, senior manager of New York’s climate policy and strategy team, told NetZero Insider that “the pre-proposal is a helpful first step,” but advocates want a formal rulemaking to be put in place.

She said the cost concerns raised by opponents and skeptics miss the point — the cap-and-invest program should be viewed not in terms of its costs but the larger savings it will yield in the short and long term.

Cap-and-invest would provide economywide market signals and give the state money it could invest in the clean-energy transition, Courtin said.

“The reality right now is we’re just not investing enough,” she said.

Preliminary state analysis shows cap-and-invest would yield $6 billion to $12 billion a year in revenue. That would come from the industries generating the emissions, which presumably would pass the cost along to New Yorkers.

Hochul recently took a controversial step to cushion New Yorkers from the cost of the state’s climate-protection efforts, placing an indefinite pause on a congestion-pricing system meant to limit vehicle traffic in New York City.

Courtin said the call for expedited action by the environmental advocates was not in concern that a similar pause is in the works for cap-and-invest, but because the new program is taking too long to devise. Hochul’s initial proposal called for the regulations to be in place by the end of 2023.

But such a time-out is exactly what the Business Council of New York State would like to see. It and 61 other business, union and industrial organizations called on the state to make mid-course corrections to its implementation of the CLCPA, based on the significant economic and market changes seen since it became law.

The Business Council wrote:

“Since the start of the CLCPA implementation efforts five years ago, many have called for a more comprehensive, publicly accessible assessment of implementation costs, the comparative costs of policy alternative programs and the impact of new policies on residential and business energy consumers. We are renewing those demands today.”

It clarified that it is not criticizing the goals of the CLCPA.

“We are not opposing further state investments in emission reductions, renewable generation and energy efficiency, nor are we opposing the adoption of a ‘cap and invest’ program. However, the state needs to ensure that its push toward emission reductions and the electrification of major sectors are technically and economically achievable.”

The vision for cap-and-invest in New York goes beyond greenhouse gas emissions.

Its architects are charged with designing a program that simultaneously targets benefits to disadvantaged communities, channels money to New Yorkers to defray the higher costs that would accompany the program, invests in industries of the future and supports the transition to a less carbon-intensive economy.

Manchin-Barrasso Permitting Bill Easily Clears Committee

The Senate Energy and Natural Resources Committee voted 15-4 on July 31 to advance the Energy Permitting Reform Act of 2024 to the floor. 

The bill, S.4753, was backed by committee Chair Joe Manchin (I-W.Va.) and Ranking Member John Barrasso (R-Wyo.) and includes changes to transmission siting and planning, mining, oil and gas drilling, and judicial review. 

The committee worked on the legislation over the course of this congressional session, holding many hearings on permitting and related issues, Manchin said at the committee’s business meeting. 

“I think the need for permitting reform has come up in almost every hearing that we’ve had this Congress,” Manchin said. “No matter what side of the fence you may be on, everyone knows it can’t happen unless we reform our permitting — how we do things. So, the time to act is now.” 

While the bill awaits a potential vote on the floor, the Senate’s actual working days left this Congress are dwindling as lawmakers will take extended time off for the election this fall. The Senate leaves for summer break at the end of this week and is scheduled to be in session for only three more weeks before the election, with five weeks of a lame duck session on the schedule. 

Numerous amendments were offered during the business meeting, but only one on forest restoration from Sen. Steve Daines (R-Mont.) passed. The committee voted down several others, including ones offered by Sen. Ron Wyden (D-Ore.) and Sen. Angus King (I-Maine) to ban offshore drilling off the West Coast and New England. 

Sen. Josh Hawley (R-Mo.) offered the day’s only amendment on transmission, which the main bill would give FERC authority to site. Hawley’s amendment would have required any lines the commission sites to go through a regional planning process. Manchin said the language would threaten the existing backstop siting FERC implemented with Order 1977 and the committee rejected the amendment. 

Other amendments, including one offered by Sen. Lisa Murkowski (R-Alaska) to make it easier for remote communities in her state to use small-scale hydroelectric and hydrokinetic generation, were withdrawn with promises from Manchin that changes could be made on the floor. 

“After more than a year of bipartisan negotiations with Chairman Manchin, we are now one step closer to getting the bipartisan Energy Permitting Reform Act signed into law,” Barrasso said. “Our bill is a true, all-of-the-above energy policy — targeted, timely and good for all Americans.” 

American Clean Power Association CEO Jason Grumet welcomed the bill, which he said would increase the resilience of the power sector and accelerate the deployment of clean energy. 

“The leadership from the Senate Energy and Natural Resources Committee is critical to ensure that our nation can meet rapidly growing electricity demand,” Grumet said. “The legislation is both bold and balanced, creating an effective policy framework for building new high-voltage transmission. Building out new transmission will help ensure affordable, reliable energy for American businesses and consumers.” 

The transmission language in the bill includes some language backed by Democrats and even environmentalists, with the House Sustainable Energy and Environmental Coalition’s Reps. Sean Casten (D-Ill.) and Mike Levin (D-Calif.) welcoming those provisions. The two have introduced the Clean Electricity and Transmission Acceleration Act, which includes similar transmission reforms. 

“While there are aspects of the bill that can be improved upon and provisions that we have concerns about, we are eager to continue the critical discussion on permitting reform as we strive to enact a law that will equitably accelerate adoption of clean energy and transmission,” Casten and Levin said in a statement. 

The Sierra Club found its opposition to the offshore drilling language and changes to permitting on federal law outweighed whatever benefits the transmission language would bring, saying it preferred the Casten-Levin legislation in the House. 

“There are existing proposals that would offer real solutions to accelerate the deployment of clean energy without sacrificing the climate and public health for fossil fuel executives’ profits,” Sierra Club Beyond Fossil Fuels Policy Director Mahyar Sorour said in a statement. “It is possible, and necessary, to unleash renewable energy and supercharge the clean economy without undermining bedrock environmental laws. Congress must see through this ruse to give handouts to polluters and reject the Dirty Deal.” 

PSEG Planning for EV, Data Center Growth

Public Service Enterprise Group is seeing “slow but steady” electric vehicle growth in New Jersey but has yet to turn down any interconnection requests for EV chargers to handle the increase, CEO Ralph LaRossa said in the utility’s second-quarter earnings call July 30.

“We have the capacity,” he said. “But we’re upgrading that last mile. So that’s really playing out exactly the way we expected it to.”

Because of the unique “condensed nature of our housing and our commutes” in New Jersey, he said, EVs “have not had the same challenges and pressure that maybe the rest of the country has seen as far as the expansion that was expected.”

New Jersey last year put an additional 62,426 new EVs on the road, a 68% increase over 2022, which has prompted some advocates to suggest the state is in reach of its goal of having 330,000 EVs in the state by 2025. The rise occurred as some analysts say EV uptake elsewhere around the nation is slowing.

The New Jersey Coalition of Automotive Retailers says the state’s affluent population is less bothered than drivers in some states by the higher price of an EV, but the organization is skeptical the target can be reached. (See NJ EV Incentives Target Low-income Buyers.)

LaRossa said the rise in EV charging, along with growing interest from developers in putting data centers in the state, “is expected to drive load growth and system investment in these in the future.” Responding to a question from an analyst, he said he sees little risk in investing for continued EV growth, even if former President Donald Trump is re-elected.

“The only question, and we’ve talked about this before, is will you have 100% EVs by 2035, or will we get a 50% on that test?” he said. “And a 50 on that test is still going to be quite a bit of market penetration for the electric vehicle industry here.”

Data Centers

LaRossa said the utility is heavily focused on positioning itself to take advantage of interest from data centers in locating in the state, and especially those interested in co-locating next to the three nuclear plants owned and operated by PSEG in South Jersey.

He said the utility has “experienced an increase in new business requests and feasibility studies from potential data center customers across our service area compared with 2023 activity, which, combined with increased electric vehicle charging, is expected to drive load growth and system investment in these in the future.”

PSEG takes proposals seriously once the developer has moved beyond the engineering phase, he said. He added that “we’re seeing several hundred megawatts of data centers that are moving into that scenario here in New Jersey,” and two or three times as many projects that are in earlier stages.

LaRossa noted that Gov. Phil Murphy (D) on July 25 signed a law (S3432/A4558) creating a $500 million program to offer tax credits to encourage artificial intelligence companies to locate in the state.

He said a co-located data center has two benefits for the state’s economic development ambitions.

“It’s not necessarily just that it’s co-located,” he said. “It’s the fact that it’s a hyperscale data center. It’s going to provide a clear signal to AI companies that are looking to locate here in New Jersey and in the region, that the infrastructure is here up and running and ready to go for their businesses to thrive,” he said.

Talen Controversy

LaRossa said his attitude has not changed in response to the recent controversy over Talen Energy’s deal to divert capacity from its Susquehanna Nuclear Plant to serve a data center on the same site.

The project, which Talen developed next to its northeastern Pennsylvania plant and sold to Amazon Web Services, has drawn protests at FERC from parties who argue that it could siphon power meant for other clients, shifting costs and threatening reliability. (See Talen Energy Deal with Data Center Leads to Cost Shifting Debate at FERC.)

“That’s not shifting us in any way, shape or form,” LaRossa said, adding the utility will be guided by its commitment to supporting Murphy’s economic development plans.

“I will say this to you. I’m a little bit concerned about co-located load as it impacts other industries,” he said. “If you really think about co-located load, that doesn’t just apply to data centers. That’s for combined-heat-and-power plants; it’s for cogeneration units.

“So, depending upon where this goes, while I’m concerned about data centers, I’m just as concerned about everything from rooftop solar behind the meter to cogeneration that might be taking place.”

Still, he added in response to a question from an analyst, whatever outcome emerges from the Talen case would not affect, or even delay, any proposal that might emerge for co-locating a facility next to PSEG’s three nuclear plants.

“Every deal is going to be very specific. I think the way our nuclear facilities are configured will be different than a nuclear facility down the street.” he said. “So, each one of those will be looked at differently, whether it’s by PJM, in its current rules that coexist for co-located load, or FERC when they come out with some sort of a process, if they do under the current challenge that’s there.”

PSEG’s second-quarter results this year fell short of those in 2023. The company reported net income of $434 million ($0.87/share), compared with $591 million ($1.18/share). It brought in about $2.4 billion in total revenue during the quarter, a slight increase over last year.

PJM Capacity Prices Spike 10-fold in 2025/26 Auction

PJM capacity prices increased nearly tenfold in the 2025/26 Base Residual Auction (BRA) as a trifecta of load growth, generation deactivations and changes to risk modeling shrank reserve margins. 

The clearing price for most of the RTO jumped to $269.92/MW-day, far above the $28.92/MW-day for the 2024/25 auction. Two regions surged to their price caps, reaching $466.35/MW-day in the Baltimore Gas and Electric (BGE) zone and $444.26/MW-day in the Dominion zone. (See PJM Capacity Prices Jump in 5 Regions.) 

“The significantly higher prices in this auction confirm our concerns that the supply/demand balance is tightening across the RTO. The market is sending a price signal that should incent investment in resources,” PJM CEO Manu Asthana said in a July 30 announcement of the BRA results. 

PJM forecasts a peak load of 153,883 MW for the 2025/26 delivery year, up 3,243 MW from the previous year. The auction procured 135,684 MW of capacity at a record $14.7 billion to serve that load, with an additional 10,886 MW supplied through fixed resource requirement (FRR) plans. 

The total installed capacity was around 182 GW, resulting in an 18.5% reserve margin, just over the 17.8% installed reserve margin (IRM) target. The Dominion and BGE zones landed just under their reserve requirement and are transmission-constrained, causing prices to jump to the zonal cap. 

PJM Executive Vice President of Market Services and Strategy Stu Bresler said the auction procured adequate supply and sent a signal that investments in capacity are needed for future delivery years. He cautioned that capacity costs remain just one component of consumers’ bills and the results should not be read as causing a multifold increase in retail rates. 

“Auction prices were significantly higher in this auction and those steep increases, we believe, do signal the need for investments,” he said during a press conference July 30. 

The auction followed a yearslong trend of declining supply, with around 6.6 GW retiring or being approved for a must-offer exemption, which signals their intent to deactivate. Bresler said the tension between supply and demand demonstrates the reliability concerns the RTO highlighted in a February 2023 Energy Transition in PJM white paper. (See “PJM White Paper Expounds Reliability Concerns,” PJM Board Initiates Fast-track Process to Address Reliability.) 

Bresler said PJM is searching for solutions to speed the generation interconnection process to facilitate new resource development; however, 38 GW of resources have cleared the generation interconnection process but have yet to enter commercial operation. 

“Interconnection process reform is proceeding, but hurdles remain for many projects outside of our process,” Bresler said in the announcement accompanying the auction results. “We are considering ways to accelerate those who can successfully overcome those challenges and build.”  

In addition to tighter supply and demand, Bresler said the cost increase was driven by a shift in how PJM models reliability risks and matches them with resources accreditation (ER24-99). (See FERC Approves 1st PJM Proposal out of CIFP.) 

The changes use PJM’s marginal effective load-carrying capability (ELCC) framework to accredit all resources, except energy efficiency, and rely on its hourly probabilistic modeling to calculate capacity needs through the reserve requirement study. The new approach concentrated reliability risk into the winter and led to several resource classes seeing reduced accreditation. (See “Revised Reserve Requirement Study Values Endorsed,” PJM MRC/MC Briefs: March 20, 2024.) 

Auction Conducted After Several Delays

The timing of the auction has been repeatedly delayed from the original May 2022 schedule to implement several market changes, including reversing an order establishing a forward-looking energy and ancillary services (EAS) offset, followed by the Critical Issue Fast Path changes. (See FERC Approves PJM Capacity Auction Date Changes.) 

An additional delay approved in February pushed the opening of the auction from June 12 to July 17 to grant market participants more time to understand how the RTO will calculate effective load-carrying capability (ELCC) ratings to accredit the capacity resources can provide. (See FERC Approves PJM Capacity Auction Delay.) 

EPSA Says Increased Prices Reflect Increased Risks, Manufacturers Skeptical

Electric Power Supply Association (EPSA) CEO Todd Snitchler said the increased capacity prices are an encouraging first step in meeting the mounting reliability risks PJM has identified. 

“While there is still work to be done, these price signals recognize the situation PJM faces and should begin to incentivize the investment needed to deliver a reliable system in PJM and in other U.S. markets,” Snitchler said in a statement. “Reliability watchdogs, regulators, policymakers and PJM itself have been sounding the alarm that the misalignment of power resource retirements and additions poses a serious reliability risk to the grid — especially in the face of rising demand spurred by data center and manufacturing growth among other factors like electrification, extreme weather and policy choices.” 

Ryan Augsburger, president of the Ohio Manufacturers’ Association, said in a statement that auction delays will translate to higher capacity costs for consumers. 

“Markets work — but after years of delay of PJM’s critical capacity auction, prices are rising to attract generation in a hurry. PJM’s capacity auction will yield billions more for generators that locate in its territory to serve healthy customer electric load, but customers will bear the brunt of PJM’s costly auction delays,” he said. 

WEIM Yields $365M in Q2 Benefits with Hot Start to Summer

CAISO’s Western Energy Imbalance Market (WEIM) provided its 22 participants with $365.04 million in economic benefits from April to June this year, down 4% from the same period a year ago. 

Cumulative benefits since the 2014 launch of the real-time market have hit $5.85 billion, according to CAISO’s second-quarter WEIM benefits report, released July 30. 

June saw an extremely hot start to summer for most of the West. During that month, the solar-heavy CAISO area was the WEIM’s leading net exporter, sending more than 1.1 million MWh of energy to other market participants, up 7% from June 2023. In the WEIM, a net export represents the difference between total exports and total imports for a balancing authority area during a particular real-time interval. 

“The transfers helped balance supply and demand when some of the WEIM entities were experiencing higher electricity usage due to a heat wave that saw temperatures climb 7 to 16 degrees above normal for several days across the West,” CAISO said in a press release accompanying the report. 

The ISO also was the biggest net exporter over the full quarter at 2.86 million MWh, followed by PacifiCorp’s East and West BAAs’ combined exports of 584,555 MWh, NV Energy at 464,133 MWh and Salt River Project at 395,542 MWh. 

The largest net importers were Powerex (965,287 MWh), the Balancing Authority of Northern California (BANC) (534,382 MWh) and SRP (473,319 MWh). 

CAISO also was the location of the largest volume of wheel-through transfers during the quarter at 736,433 MWh, followed by Arizona Public Service (508,707 MWh), the Western Area Power Administration’s Desert Southwest Region (DSW) (430,880 MWh) and PacifiCorp-West (419,025 MWh). WEIM participants currently receive no financial benefits from facilitating wheel-throughs through the market, with only the source and sink of the transfers benefiting, although stakeholders have discussed the possibility of changing that in the future. 

“More recently, subsequent to the June 30 closing of the second quarter, the real-time market also provided an important platform for energy trading during the record-setting heat wave in July that caused triple-digit temperatures across much of California and the West,” the ISO said. “Market participants provided similar assistance with robust energy transfers throughout the region.” 

DSW, which joined the WEIM in 2023, reaped the greatest economic benefit during the second quarter, at $50.57 million. DSW this year withdrew from participating in the second phase of developing SPP’s Markets+ — a potential competitor to the WEIM — after finding it would see few benefits from participating in either Markets+ or CAISO’s Extended Day-Ahead Market. (See WAPA DSW Cites Lack of Benefits in Markets+ Withdrawal.) 

BANC realized the second-largest share of benefits ($49.9 million), followed by CAISO ($36.02 million), NV Energy ($33.65 million) and the Los Angeles Department of Water and Power ($30.52 million). 

CAISO’s report said WEIM operations in the third quarter also helped market participants avoid 55,921 metric tons of greenhouse gas emissions through reduced curtailments of emissions-free resources. The market has prevented over 1 million MT of emissions since 2015, the ISO estimates. 

MISO in June: Unchanged Pricing, Lower Peak than Expected

June brought MISO a peak 2 GW lower than anticipated and unchanged real-time and fuel prices from last year, the RTO said in its monthly operations report.

MISO encountered a 113-GW peak on June 24 as a sustained heat wave sent temperatures into the high 90s across the Central and South portions of the footprint. However, the month’s peak was lower than MISO’s 115-GW probable demand forecast for June that it published in the days leading up to the season.

The peak demand for June this year was higher than last year’s 111-GW apex but well below 2022’s 121 GW. Load averaged 82 GW, slightly higher than last June’s 81-GW average.

The RTO’s average natural gas and coal prices did not budge from last June, staying about $2/MMBtu. Similarly, real-time LMPs reflected no change year over year, hovering at $28/MWh.

MISO matched a 6.2-GW all-time solar peak it set in May on June 14, when the collective panels of the footprint managed about 12% of load for a brief period.

The RTO’s approximately 56 TWh of production for the month were supplied 39% by natural gas generation, 28% by coal generation, and about 14% apiece by wind and nuclear generation. Hydro and solar power each contributed almost 3%.

Daily generation outages stood at an average of 35 GW, lower than 2022 and 2021’s 40 GW and 2023’s 38 GW.

MISO ultimately issued conservative operations instructions for its North region on June 25 and for its North and Central regions on June 28 because of above-normal temperatures.

However, MISO has yet to issue emergency instructions this summer. Although MISO issued a capacity advisory for its North and Central regions and conservative operations for the entire footprint on July 15, the combination of forced generation outages, hot weather and transfer capability issues did not rise to an emergency level.

MISO is navigating a capacity advisory for its Central and North regions and conservative operations for the entire footprint through July 31 because of heat, forced generation outages and higher-than-forecasted load.

On July 30, MISO relied heavily on its coal (41 GW) and gas (44 GW) resources to meet a 115-GW peak. Prices ranged from $39 to $49/MWh.

DC Circuit Vacates Pipeline Approval FERC Issued over NJ’s Objections

The D.C. Circuit Court of Appeals on July 30 vacated and remanded an order by FERC approving a natural gas pipeline in New Jersey that state regulators said was unneeded (23-1064).

FERC last year approved Transcontinental Gas Pipe Line Co.’s Regional Energy Access Expansion Project to boost gas delivery by 829,400 dekatherms/day to bring gas from Pennsylvania into New Jersey over the objections of New Jersey regulators and others (CP21-94). (See FERC Approves Pipeline Expansion Despite New Jersey’s Worries.)

Before the gas project came to FERC for approval, the New Jersey Board of Public Utilities opened a proceeding on the future of natural gas in the state, which determined it did not need more pipeline capacity through at least 2030. That proceeding was opened in February 2019; Transco applied to FERC in March 2021; the BPU issued a final order in the proceeding in June 2022; and FERC approved the pipeline expansion in January 2023.

About 73.5% of the project’s gas was destined for customers who signed contracts in New Jersey, but the rest was for Delaware, Maryland and Pennsylvania.

The New Jersey Conservation Foundation, New Jersey Division of Rate Counsel, New Jersey Attorney General’s Office and others challenged FERC’s approval after the commission upheld it on rehearing.

The court found that FERC failed to make a significance determination when it came to the project’s greenhouse gas emissions and failed to discuss mitigation measures.

FERC quantified the emissions associated with the project, finding construction could add 43,548 metric tons of CO2 equivalent, while operation would add 562,044 metric tons per year. Using the fuel downstream from the pipeline would add just over 16 million metric tons. The higher estimates are the project would use 39% of the total annual emissions budgets of New Jersey and Maryland.

The commission said counting the emissions was enough and it did not have to weigh their significance for the project as it had an open proceeding looking into such issues generically.

FERC “did not explain, however, how the pendency of that generic proceeding affects its ability in the meantime to make a case-specific determination here, when it was able to do so in Northern Natural,” the court said, referencing the first time the commission assessed the greenhouse gas emissions of a proposed natural gas infrastructure project and its impact on global climate change. (See FERC Assesses Climate Impact of Gas Project for 1st Time.)

“The anticipated emissions from this project are more than a hundredfold higher than the 100,000 metric tons per year of CO2e that the commission’s interim guidance suggests as a significance threshold,” the court said. Even if FERC was not obliged to make a determination, choosing not to do so on the basis of an arbitrary explanation is a violation of the Administrative Procedure Act, it said.

The court also found FERC acted arbitrarily in granting the certificate under the Natural Gas Act because it failed to explain why it discredited New Jersey’s study finding no need of new pipelines for the rest of the decade. It also failed to give weight to the state’s climate law that requires sizeable and continuous cuts in natural gas use by utilities.

FERC criticized the New Jersey study for relying on the continued availability of 619 million dekatherms/day of off-system peaking resources that are not under long-term, firm contracts.

“The commission did not, however, identify any past event in which such resources — despite being subject to short-term contracts — were unavailable when needed,” the court said. “In fact, the commission recognized that ‘downstream capacity has been available to New Jersey shippers in the past through short-term peaking contracts and may be available in the future on the same short-term basis.’”

The project had contracts for the new capacity. Normally such precedent agreements are used to show a market need, but the court faulted FERC for failing to respond to challenges to its reliance on those. While New Jersey local distribution companies signed up for capacity, it is not guaranteed they will use it to serve their customers.

“If ratepayers assume the cost even when they do not need the capacity, LDCs can afford to contract for additional unneeded capacity, which they can then resell at a profit, even in a soft capacity market,” the court said. “Because the commission failed to respond to that challenge to its reliance on precedent agreements with LDCs who subscribed to a majority of the pipeline’s capacity, the commission acted arbitrarily.”

NREL Examines Gulf of Mexico OSW Transmission Needs

A National Renewable Energy Laboratory report offers insight on transmission infrastructure needs for future offshore wind development in the Gulf of Mexico. 

NREL said the needs are significant but have not been researched previously.  

Offshore wind development in the Gulf presents challenges beyond those facing present-day efforts along the northeast U.S. coast. And developers so far have shown little willingness to meet those challenges — the Gulf wind lease auction planned for later this year was canceled for lack of interest. 

But the Gulf is believed to hold 37% of the nation’s potential offshore wind generation capacity, and federal leaders hope to exploit it. 

NREL’s report looks at some of the steps that would need to be taken well in advance of wind turbine construction so their megawatts of power could be brought ashore. 

A key takeaway: The oil and gas industry already has infrastructure and personnel in the Gulf. Shared transmission systems and workforce could support offshore wind. 

Also, about 18,000 miles of abandoned pipelines remain on the seabed and could be used to transmit clean hydrogen — generation of which is a potential use of offshore wind energy. 

But the NREL report also suggests that offshore wind transmission planning in the Gulf is not so different from other regions: Planners will have to limit the impact of their projects on existing communities, industries and ecosystems while navigating local, state, federal and tribal regulations and sensibilities. 

The report’s authors identify some gaps in existing planning and knowledge needed for buildout: 

    • RTOs and utilities have not incorporated Gulf of Mexico offshore wind power in their long-term transmission planning. 
    • Siting considerations for offshore wind transmission routing in the region have not been identified in published literature. 
    • Focused community and workforce engagement on stakeholder priorities has been lacking. 
    • Engagement and research would inform how offshore wind transmission would fit into the region’s energy generation portfolio and how it serves the needs of industries in the Gulf Coast states. 

The NREL report recommends the Department of Energy and Bureau of Ocean Energy Management convene a Gulf Coast version of the Atlantic Offshore Wind Transmission Study workshop series they began hosting in 2022. 

The Biden administration, as part of its push to build a new emissions-free power sector, envisions fixed-bottom wind turbines in shallower parts of the Gulf and floating turbines in deeper areas. 

But slower average wind speeds punctuated by severe winds from hurricanes and tropical storms present a significant engineering challenge for designers of the wind turbines to be placed in the Gulf. (See Hurricane Threat to OSW Turbines Quantified.) 

In 2023, the first of four planned Gulf wind energy area auctions drew only three bids from two bidders on one of the three areas offered. The single sale came at a rock-bottom price. (See Gulf of Mexico Wind Energy Auction Falls Flat.) 

The planned 2024 auction drew early interest from only one potential bidder and was called off. (See BOEM Cancels Gulf of Mexico Wind Lease Auction.) 

As the 2024 auction was heading to cancellation, however, another developer submitted an unsolicited request to BOEM for two other lease areas off the Texas coast. 

And Louisiana has been advancing offshore wind development in state waters closer to shore. The Climate Action Plan developed during the administration of Gov. John Bel Edwards (D) set a goal of 5 GW of offshore wind capacity by 2035, and the state signed agreements with two developers in late 2023, during the closing days of his administration. 

A previous NREL study identified 25 plausible points of interconnection for offshore wind export cables but concluded that, as in other regions, many of them would need significant upgrades to handle gigawatt-scale injections. 

The new NREL report was funded by the DOE’s Wind Energy Technologies Office and Grid Development Office. 

AEP Planning for 15 GW of Data Center Load

American Electric Power executives say they’re embracing large loads and, fortunately for them, they say they have firm commitments for more than 15 GW of load coming from just data centers by 2030.

AEP told financial analysts during its July 30 second quarter earnings call with financial analysts that it’s seeing “unprecedented” load growth, split primarily between Texas and its PJM footprint. Commercial load has increased 12.4% over the second quarter of last year as new data processing facilities came online, the company said.

“We continue to see strong interest in Ohio and Texas, as well as several of our vertically integrated states, from customers looking to develop new data processing facilities,” interim CEO Ben Fowke said during the company’s call. “Affordability remains top of mind, and we’re working to ensure that the investments made in the grid to support this increased demand are allocated fairly and provide benefits to all customers.”

Noting AEP’s system-wide peak at the end of last year was 35 GW, Fowke said the company continues working with data center customers to meet their increased demand, but also ensuring contracts and new initiatives are “fair and beneficial” for all customers. He said AEP would provide details on its generation and transmission capital investment necessary to meet demand later this year.

“I want to emphasize that it’s critically important that costs associated with these large loads are allocated fairly and the right investments are made for the long-term success of our grid,” Fowke said.

AEP subsidiary Public Service Co. of Oklahoma (PSO) in June announced it will seek regulatory approval of an agreement to purchase Green Country, a 795-MW natural gas facility. Peggy Simmons, executive vice president of utilities, said the transaction will help PSO meet SPP’s higher planning reserve margin, which was increased to 15% from 12%.

“This was a very proactive approach that the team took to go out and find some affordable assets that we can bring onto the system,” she said.

AEP reported second-quarter earnings of $340 million ($0.64/share), down from 2023’s second quarter earnings of $521 million ($1.01/share). The company reaffirmed its 2024 operating earnings guidance range of $5.53-$5.73/share and its 6%-7% long-term growth rate.

Incoming CEO Bill Fehrman, who takes over AEP’s top job Aug. 1, did not participate in the call. Fehrman replaced Julie Sloat in June after his predecessor parted ways with AEP in February following just one year as CEO. (See AEP Selects Industry Veteran as Next CEO.)

“With Bill’s expertise and diverse background, you can anticipate a smooth transition and continuity of strategic direction. Expect more focus on execution,” said Fowke, who served as interim CEO and will advise Fehrman during a transition period.

The company’s share price rallied late July 30 to close at $98.14, up $1.07 from its previous close.