Utilities Have Crucial Role in Economic Development

The flood of federal dollars authorized by the passage of the Infrastructure Investment and Jobs Act is expected to accelerate clean energy projects, enable utilities to build out infrastructure and sharpen state competition for economic development. 

The enormous possibilities have not been lost on the Missouri Energy Initiative, a 12-year-old think tank with a mission to accelerate development in the Show Me State.

MEI’s annual two-day economic development meeting, conducted virtually Dec. 8-9, examined the role utilities played in two economic development projects in the service areas of two Missouri utilities, Ameren Illinois and Evergy. 

During the session, MEI unveiled a new report on the extent of electric vehicle charging infrastructure in Missouri, launching an in-depth panel discussion about the pitfalls and expenses of a mass EV charging buildout and what that will mean for the state. 

MEI also invited the head of supply chain at Swift Prepared Foods to discuss the company’s expansion and the role played by utilities in site selection that kept the expansion in-state.  

Swift Foods, owned by Colorado-based JBS USA Holdings, has 60 meat processing plants in 28 states. More expansion is expected.

In a separate panel, a development director with Evergy discussed how the state landed an 800,000 square-foot logistics center built by Chewy, a pet food company. The project will ultimately employ more than 1,600. 

The conference also looked at a new cobalt mining operation in the state, built on the remains of a retired lead mine that had been declared a Superfund Site by the U.S. Environmental Protection Agency. Opened in the 1840s, the mine has sat dormant since the 1980s.

Most of the cobalt used in storage batteries is mined in Africa and processed in China. Missouri Cobalt aims to supply North American battery builders, said John Diehl, Jr., the company’s general counsel.  He said the company is planning to open a hydrometallurgical plant in 2022 to produce battery-grade cobalt sulfate.

Virtual attendees also got updates on the state’s efforts to identify a consensus on a new state energy development plan and a few details on the expected rollout of funding that will be made available by the passage of the bipartisan federal infrastructure bill, which President Biden signed into law on Nov. 15. (See Biden Signs $2 Trillion Infrastructure Bill.)

Utilities Play Crucial Role 

JBS USA earlier this year committed to reduce its greenhouse gas emissions 30% by 2030 and 70% by 2040, with the ultimate goal of net-zero emissions.

Joe Machetta (Missouri Energy Initiative) Content.jpgJoe Machetta, Swift Prepared Foods | Missouri Energy Initiative

“It’s really more about building in the energy efficiency, whether it be lighting or [using] clean energy,” said Joe Machetta, head of integrated supply chain for Swift Foods. 

The company wanted to build a new bacon plant and started its search for a site with a list of over 90 locations, Machetta said. But electricity was a key issue.  

“One of the key things for us was obviously the utilities,” he said. The company decided to build the $68 million plant in Moberly, Mo., creating about 200 new jobs. 

“The [economic development incentive] offered by Ameren was clearly critical, and it really pushed Moberly over the edge,” he said, referring to a 40% rate discount the utility was able to offer the company for five years.

“The utility spend this year will be close to a million dollars. Next year it will be north of $2.6 million just in utilities for keeping the lights on and operating the process,” Machetta said. 

Chewy’s new logistics and e-commerce fulfillment center that opened this year in Belton, Mo., is another success story for the state in which another utility, Evergy, played a key role.

Lisa Franklin (Missouri Energy Initiative) Content.jpgLisa Franklin, Evergy | Missouri Energy Initiative

Lisa Franklin, lead economic development manager at Evergy, said the community reached out to the utility because it had not had much luck attracting new development. 

“Our energy economic development team — along with the city — conducted a competitive analysis to determine what they needed to position themselves to be competitive globally. 

“I think this may be where we’re a little bit different in energy. It’s like putting your house on the market. You know you have some major issues that need to be resolved before you can successfully sell it,” she said.

“We went through an actively competitive assessment. We performed a site identification study. That was us going out and helping them locate a site where an industry would actually want to locate. This happened to be on a major interstate. After that was done, we went through a site due diligence analysis, and that was a research project that allowed us to look at all of the infrastructure needs, whether it was electric, gas, water, sewer,” Franklin said.

Chewy chose Belton over cities in other states and opened the fulfillment center last summer, which is expected to develop a workforce of up to 1,600 employees.  

Franklin said the development team is now working on two other projects, each expected to draw 250 MW of demand. 

“These are very, very large projects. Ten years ago, we would never see anything that large, but today it’s like everything that’s coming to the door happens to be a very large project. That’s becoming a big issue for us because we’re having to build up infrastructure to meet those demands.” 

Job Training Is Key

Job training has become another critical ingredient in economic development as technology has transformed manufacturing. And since the pandemic began, an unexpected new phenomenon has only added to the problem: the “Great Resignation.”

Rosa Schmidt (Missouri Energy Initiative) Content.jpgRosa Schmidt, Center for Energy Workforce Development | Missouri Energy Initiative

“I still remember the time when we were in the single digits, and people would start with our companies and leave from our companies,” said webinar participant Rosa Schmidt, an analyst with the Center for Energy Workforce Development, a nonprofit consortium of nearly 120 utilities. The center’s mission is to take the pulse of the industry’s workforce and issue comprehensive biennial reports  

The latest analysis reveals that “64% of folks leave within the first five years. Think about the impact on the industry when you have almost 65% of the population that you hire, spend time and energy to educate and train, and within the first five years they’re walking out the door. This is a major issue for our employers.”

More disturbing, she said is that 19% of people with more than 10 years of service are also leaving their jobs. Almost half of those are … over the age of 53, and 43% are between the ages of 38 and 52. It’s the Great Resignation.” 

Added to that problem is that technologies are changing, making it difficult for utilities as well as technical schools and unions to prepare for the future, especially one that will be decarbonized. 

Ben Berhorst (Missouri Energy Initiative) Content.jpgBen Berhorst, Missouri Technical College | Missouri Energy Initiative

The center has been working with several consulting firms in an effort to figure out what job skills utility workers will need in 2035, Schmidt said.

“A lot of our [corporate] members are really struggling with technology because of the way that things are changing. The center is working to develop a ‘competency model’ for future workers. 

“We don’t know what that’s going to look like, what knowledge and skills they will need. And so we are going to be working on developing some tools and resources and an assessment for workers of the future,” she said.

Ben Berhorst, dean of the Division of Technology at the State Technical College of Missouri, said the staff there is also trying to develop an energy technology program to account for power plant technology moving from fossil generation to renewable technologies. 

Nicole Fondren (Missouri Energy Initiative) Content.jpgNicole Fondren, Spire | Missouri Energy Initiative 

Nicole Fondren, manager of talent acquisition and workforce development at gas utility Spire, pointed out that people today already deal with technologies in everyday life as well as on the job. 

“We have a lot of technology that the field [employee] has to use, whether it’s drones or whether it’s utilizing a computer system in the [work] truck. … It’s a learning curve. It’s a change that management has had to face, with individuals who never had to use technology before but are now having to use it,” she said.

Missouri along with the rest of the nation is on the cusp of one of the most significant changes in decades: the electrification of everything from industry to residential to transportation. That also is expected to increase demand for new and comprehensive job training to build out the necessary infrastructure.  

EV Charging Stations the Catalyst 

EV charging stations are more common in Missouri’s metropolitan areas, but given the predictions of EV growth, that will have to change.

Travis Wood (Missouri Energy Initiative) Content.jpgTravis Wood, Missouri Energy Initiative | Missouri Energy Initiative

“EV market share is around 2% now,” said Travis Wood, MEI’s program manager and author of the survey and analysis of EV growth in the state. That share is expected to rise to 10% by 2030 and 58% by the 2040s.

“We can expect relatively explosive growth of the industry compared to what we’ve seen up to this point. Coupled with that growth is the need for charging infrastructure and specifically public charging infrastructure.

“While it is the case that 80% of charging occurs in the home, at least currently, public charging infrastructure is needed to facilitate these longer trips, to top off during shorter trips, to reduce that range anxiety and increase the visibility of EVs and help the industry grow,” Wood said.

“If we look nationally, the U.S. has around 44,000 charging stations, but an estimated 1.25 million are going to be needed by 2030,” he said. “So there’s a lot of growth that is coming for this industry in a relatively short amount of time.”

Missouri has about 9,000 registered light-duty EVs and over 2,000 public charging stations, he said, but only 215 fast chargers — able to refill an EV’s batteries to at least 80% capacity in approximately 20 to 30 minutes. The rest of the public chargers are Level 2 chargers, running on 240 V, and require more time to charge an EV. Many residential Level 1 chargers run on 120 V and are typically used overnight. 

“It can be argued that Missouri has sufficient charging ports in place now to meet current EV adoption levels,” Wood said. “But you know, looking out to 2030, it’s estimated there’s going to be over 200,000 EVs on the road in Missouri. So, there’s going to be the need for 8,000-plus public charging ports, at least according to DOE, to support that growing market.”

The buildout of EV charging infrastructure will test not only the utilities but also private electrical contractors who will be asked to bid for private construction of charging stations.

Using the rise of EVs as a starting point, a separate panel looked at the potential impacts on the ability of the state’s utilities to meet new demand while maintaining a stable delivery system and avoiding steep price increases. 

Linda Little (Missouri Energy Initiative) Content.jpgLinda Little, St. Louis Electrical Training Center | Missouri Energy Initiative

“I think that Missouri could try to lead in a couple of things. One is coming up with an energy storage solution. So then as we have more and more of these charging stations — even the quick charging stations that are going to need this energy — that we have the energy storage capability to back those up,” said Linda Little, assistant director of the IBEW/NECA Electrical Industrial Center in St. Louis. 

Patrick Justis, manager of efficient electrification development for Ameren Missouri, said building home charging stations will be “a big, big issue” in multifamily homes, whether high end condominiums or multicomplex apartment buildings.

“When you’re talking about a 150-car parking garage or parking lot, you’re talking about quite a bit of power,” he said. 

“One of the principles we have with utilities is a meter for each domicile. And now you’ve got these vehicles taking up quite a bit of energy and you can’t pull them through your existing meter. Finding technical solutions to this will be really important.”

Panel moderator Maurice Muia, principal of a consulting company and climate adviser to the Natural Resources Defense Council and the city of St. Louis, summed up the future this way:

“I think innovation and workforce development are going to play a key role. We have very good institutions of higher learning. We have a ton of electrical contractors across the state. 

“We have what we need to be great in this clean energy economy of the future. We have all the necessary parts and puzzles. It’s a matter of, as everyone has said, how do we prioritize and come up with a vision and mission that meets the needs of the residents and those that visit Missouri as well.”

California PUC Proposes New Net Metering Plan

The California Public Utilities Commission issued a much-anticipated revision to its net metering rules for residential rooftop solar generation Monday, inflaming a controversy that has been growing for months over how much homeowners should be compensated for returning excess electricity to the grid.

The battle has pitted an unusual coalition of large utilities, ratepayer advocates, unions and environmentalists against the rooftop solar industry, trade groups and homeowners who receive generous billing credits for rooftop solar.

Those who want to significantly change the current net metering framework argue it unjustly benefits richer households at the cost of common ratepayers. Those who want to keep it contend changing net metering will decimate household solar adoption in California, where incentives that started in the mid-1990s led to more than a million household solar arrays.

The CPUC has been examining net energy metering (NEM) since August 2020 with extensive input from stakeholders and homeowners. Its 204-page proposed decision published Monday would make some compromises but generally favors those seeking wholesale change by cutting compensation rates, incentivizing home battery storage and promoting solar adoption across a broader socioeconomic spectrum.

“Our review of the current net energy metering tariff, referred to as NEM 2.0, found that the tariff negatively impacts nonparticipating customers; is not cost-effective; and disproportionately harms low-income ratepayers,” CPUC Administrative Law Judge Kelly Hymes wrote. “This decision determines that, to address the requirements of the guiding principles and the findings related to the NEM 2.0 tariff, the successor tariff should promote equity, inclusion, electrification and paired storage, and provide a glide path so that the industry can sustainably transition from the current tariff to the successor.”

The proposed decision is scheduled to be heard at the CPUC’s Jan. 27 voting meeting. The lead commissioner in the effort, Martha Guzman Aceves, will leave before then to become administrator of EPA’s Region 9, while CPUC President Marybel Batjer is retiring. Her replacement, Gov. Gavin Newsom’s energy adviser Alice Reynolds, is scheduled to take office at the end of this month.

Proposed Changes

The CPUC’s proposed changes would revise the structure of net metering, which credits rooftop solar owners for excess electricity they export to the grid. For years, homeowners have received the full retail value of the surplus electricity plus bonuses for producing more energy than they use in a 12-month period.

A new avoided-cost rate would consider the value of behind-the-meter generation to resource adequacy and grid reliability, potentially slashing the reimbursement rate by less than half. It would also impose an interconnection fee that does not currently exist, averaging about $40/month.

“The successor tariff ensures all customers pay for their usage of the grid,” the proposed decision says. It would apply a grid charge of $8/kW of installed solar “to capture residential adopters’ fair share of costs to maintain the grid and fund public purpose programs,” the CPUC said in a news release.

The decision proposes applying time-of-use rates to encourage solar owners to charge batteries during the day and discharge them after sunset, the net-peak hours when California has run short of electricity during heat waves the past two summers.

“More accurate price signals…will promote greater adoption of customer-sited storage, which will help California decrease its dependency on fossil fuels during the early evening hours, when the sun is down and energy demand is high,” the CPUC said.

The proposal would create an equity fund with up to $600 million to “improve low-income customer access to distributed clean energy programs with strong consumer protections,” the commission said. A stakeholder process would determine how the funds are spent, for instance on community solar projects.

One compromise in the proposed decision seeks to address concerns that slashing net metering credits would ruin the rooftop solar industry. A proposed four-year “glide path” for the industry would pay a monthly market transition credit of up to $5.25/kW for new residential solar-plus-storage and solar-only systems.

“Customers will lock this amount in for 10 years,” the CPUC said in its news release. “During the four-year glide path, the credit will step down 25% a year for prospective customers, who will also lock in their amount for 10 years.”

To soften the blow to homeowners, the decision proposes a “storage evolution fund” to provide rebates for existing net-metering customers who add storage systems to their homes and switch to the new net-metering structure in the next four years. Otherwise, it would transition current customers to the new compensation structure after 15 years of continuous interconnection.

Opponents React

Reaction from the solar industry was swift and angry.

“Today the California Public Utilities Commission issued a proposal that will create the highest solar tax in the country and tarnish the state’s clean energy legacy,” the Solar Energy Industries Association said in a statement. “The proposal imposes fees on solar and storage customers, making solar and storage more expensive and less accessible to all Californians. The new program will rapidly reduce the bill credit solar customers get for selling electricity back to the grid, adding unpredictability and instability for customers that already have solar.”

SEIA said the proposed decision would deter residents from installing rooftop solar, “leaving the state’s grid vulnerable to blackouts and power outages and harming California’s ability to reach its clean energy goals.”

“Before today’s decision, about 40% of all rooftop solar installations in California were going to low- or middle-income homes in California, but the new costs and fixed fees are going take away the value proposition for virtually all Californians,” it said. “This will slow the massive momentum the state was building toward a grid powered by clean energy.”

Cutting net metering payments is mainly about boosting utility profits, critics argued.

Main proponents included the state’s three large investor-owned utilities, ratepayer advocates such as The Utility Reform Network (TURN) and environmental groups including the Natural Resources Defense Council.

Pacific Gas and Electric, the state’s largest utility, said the proposal “is a step in the right direction to modernize California’s outdated rooftop solar program. Over time, NEM has resulted in deep inequities between customers with rooftop solar and those without, who are often lower-income customers. Sensible reform is necessary to support customer equity and help continue California’s success toward a clean energy future.”

Independent research firm ClearView Energy Partners said the proposed decision seemed to strike a balance.

“We are still reviewing the 204-page document but think [it] may provide a reasonable middle ground between the different proposals offered by stakeholders earlier this year,” the firm said in a note to clients. “While the [proposed decision] would reduce export compensation, it would also include a 10-year transition credit for customers that deploy distributed generation such as rooftop solar within the next four years.

“That said, a proposal to impose a comparatively high monthly charge on rooftop solar customers may prove very contentious,” ClearView said.

Fights over net metering have occurred in other states, with utilities set against the solar industry.

In July 2020, FERC rejected a challenge to net metering by a purported ratepayer group called New England Ratepayers Association, which argued that the commission had exclusive jurisdiction over sales of rooftop solar power. (See FERC Rejects Net Metering Challenge.)

Hawaii, Indiana, Maine, Michigan and North Carolina have struggled with net metering policies, which were introduced to promote solar when it was rarer and rates were higher. Solar has since become far more common and inexpensive. (See Net Metering Reform Means Asking New Questions.)

ERCOT Board of Directors Briefs: Dec. 10, 2021

New Leadership Begins to Assert its Influence

TAYLOR, Texas — Meeting publicly for the first time with almost a full complement, ERCOT’s new Board of Directors made a point to reassure any Texans listening to the webcast that a new sheriff is in town following last February’s devastating winter storm.

“This is a work in progress,” Director Carlos Aguilar said. “We’re doing everything we can to stay abreast of the situation and ensure the system remains stable.”

Fellow Director John Swainson, who has more than 40 years of technology experience, said during a quick round of introductory statements that he hopes to leverage his IT background for the grid’s benefit.

“I want to focus on how we can look 10 years into the future and even longer,” he said. “How can we get past the current set of issues, but continue to provide this same abundance of reliable energy for decades to come?”

The storm resulted in the resignation of much of the previous board, most of whom Texas’ political leadership faulted for living out of state. Following new state legislation, they have since been replaced by six independent directors, two short of a full slate, who all live in the Lone Star State. (See 2 More Directors Appointed to ERCOT Board.)

“Look at those pictures,” interim CEO Brad Jones said, pointing to a screen with images of the board’s four newest members. “It’s great to have a nearly full board.”

Brad Jones Clif Lange 2021-12-10 (RTO Insider LLC) Alt FI.jpg

Interim CEO Brad Jones (left) shares a light moment with TAC Chair Clif Lange. | © RTO Insider LLC

“I can’t tell you how happy I am to see you today,” Public Utility Commissioner Will McAdams said. “You have a big job in front of you. Winter is upon us, and this organization has made giant strides to ensure we’re ready. This grid is resilient and hardened and will survive [another winter weather event]. The public remains safe.”

Jones stressed the amount of work ERCOT staff have undertaken since the storm. The legal department has been swamped with litigation issues; a new 12-person department has been created to handle winter readiness inspections as a result of new legislation; and staff are working to improve communications within the industry and not just within ERCOT.

The workload has resulted in above-normal turnover for ERCOT, but fears have lessened that the light at the end of the tunnel is another oncoming train. Jones said staff are already closely monitoring a storm due to hit Texas near the end of December.

“We’ll be ready because we’re working with the PUC,” he said. “Tweaks that will have significant value to the market, we’re making today. We’re in the same room together.”

Response to NERC-FERC Winter Storm Inquiry

Staff told the directors they have begun or completed work on nearly all of the recommendations applicable to ERCOT identified in NERC and FERC’s joint inquiry into the storm. That doesn’t include the numerous recommendations made by staff, stakeholders, regulators and legislators since February.

The federal agencies released their report in November, highlighting the failure of electric and gas utilities to adequately prepare for the storm’s extremely low temperatures. The event caused more than 23 GW of manual firm load shed as generators and their supply lines froze. (See FERC, NERC Release Final Texas Storm Report.)

Compiled by a team of more than 50 subject matter experts, the report listed 28 recommendations that covered the electric and gas industries and went beyond NERC reliability standards revisions to address cold weather, which were approved in August 2021.

Jones reassured board Vice Chair Bill Flores and the webcast’s viewers that the problems were regional and not isolated to ERCOT. Among several recommended improvements to ERCOT’s grid are improving interconnections with other grid operators beyond the current 820 MW worth of DC ties.

The report’s authors “recognized the ability to move power all the way east to Texas would have been very limited,” Jones said. “Our power supplies were cut because we have an agreement with the regions around us that if one of us gets into trouble, we can terminate the power supplies [we’re exporting]. We recognize that was an appropriate action to take.”

Betty Day, ERCOT’s vice president of security and compliance, said the grid operator is finalizing its own report on the storm and will publicly post the document when it’s complete.

“This is standard after any grid event,” she told the board.

ERCOT to Correct Prices

The directors signed off on staff’s request to correct prices for eight operating days in September and October stemming from a modeling error for a generation transmission constraint in the day-ahead market. Resettling the error resulted in more than $816,000 in increased charges and more than $122,000 in reduced charges to market participants. (See “Staff to Seek Price Correction,” ERCOT Technical Advisory Committee Briefs: Nov. 29, 2021.)

Price corrections “are largely event-based and don’t have a consistent cadence,” Dave Maggio, ERCOT’s director of market design and analytics, said when questioned about the frequency of price corrections. “There have been a handful or so of various events that have occurred.”

The grid operator’s staff must seek board approval of price corrections when they are identified outside of a short multiday deadline to make corrections themselves.

TAC’s 2022 Membership Approved

The board unanimously confirmed the 2022 Technical Advisory Committee, which will continue in its present form and with its familiar members as elected by their market sectors. The board has not yet decided whether to make any changes to the committee’s stakeholder membership. (See ERCOT Technical Advisory Committee Briefs: Nov. 29, 2021.)

PUC Chair Peter Lake welcomed the committee’s membership and offered a reminder that “with this new board, this new leadership will continue to leverage the expertise of TAC while also optimizing its effectiveness.”

“We look forward to working with you during this transition as you see fit,” said TAC Chair Clif Lange, of South Texas Electric Cooperative.

Lange will continue in the chairman’s role, and Just Energy’s Eric Blakey will remain as vice chair. The committee is responsible for recommending protocol changes and endorsing other operational issues to the board and is assisted by four sub-committees.

Board Approves $1.28B Tx Project

The directors approved a number of staff and stakeholder recommendations during the meeting, including a $1.28 billion transmission project in the Rio Grande Valley. The project would add 351 miles of transmission lines radiating from a new substation in the Lower Rio Grande Valley, which ERCOT and the PUC have both identified as in urgent need of more transmission capacity. (See “TAC Endorses $1.28B Tx Project,” ERCOT Technical Advisory Committee Briefs: Nov. 29, 2021.)

Director Aguilar asked whether the project would be eligible for funding under the federal infrastructure bill signed into law last month, saying, “Should we identify more of these that are essential and could be implemented sooner than later because of the infrastructure bill?” (See Biden Signs $1.2 Trillion Infrastructure Bill.)

“Our function is to identify the needs in the system and hand that process over the transmission provider who will do that development,” Jones said.

The board passed several other items, including:

Directors Zin Smati and Bob Flexon abstained from the last vote.

The consent agenda, which cleared unanimously, included seven nodal protocol revision requests (NPRRs); a Nodal Operating Guide revision (NOGRR), an other binding document changes (OBDRR), a revision to the Planning Guide (PGRR) and a modification to the resource registration glossary (RRGRRs):

        • NPRR1077: expands NPRR1026’s self-limiting facility concept to include sites with one or more settlement-only generator (SOG) and introduces additional revisions to fully address requirements for generators and energy storage systems (ESSs) connected at distribution voltage. The NPRR requires the SOG’s qualified scheduling entity to provide telemetry of the injection or withdrawal at the point-of-interconnection (POI) for transmission-connected sites or point-of-common coupling for distribution-connected sites.
        • NPRR1091: addresses energy-price suppression and liquidity issues created by ERCOT’s early and greater procurement of ancillary service by extending the treatment of must-take energy from reliability unit commitments in pricing runs to offline non-spinning reserves, when it is manually deployed. The change also increases the amount of responsive reserves and non-spin services that an entity can self-arrange above its obligation.
        • NPRR1094: allows a transmission operator (TOP) and transmission/distribution service providers (TDSPs) to manually shed load connected to under-frequency relays during a Level 3 energy emergency alert (EEA) if the affected TOP can meet its overall under-frequency load shed (UFLS) requirement and its load shed obligation under the Nodal Operating Guide.
        • NPRR1101: modifies load resources’ deployment grouping requirements if they’re not controllable load resources providing non-spin to include generation resources providing offline non-spin.
        • NPRR1103: establishes the processes for assessing and collecting default charges and default charge escrow deposits for the debt-obligation order securitizing about $800 million owed to the market by cooperatives and municipalities.
        • NPRR1104: corrects the definition of real-time liability extrapolated (RTLE) to include market activity for entities that have no load or generation but do have real-time exposure.
        • NPRR1107: adds new fees for ERCOT’s weatherization inspections of the resource entity’s capacity divided by the entity’s aggregate capacity.
        • NOGRR233: allows a TOP and a TDSP to manually shed load connected to under-frequency relays during a Level 3 EEA if the affected TOP can meet its overall UFLS requirement and load-shed obligation.
        • OBDRR035: aligns the non-spinning reserve deployment and recall procedure with NPRR1101’s revisions.
        • PGRR092: allows an interconnecting entity (IE) proposing a SOG to designate it as part of a self-limiting facility during the generator interconnection or modification (GIM) process, consistent with NPRR107.
        • RRGRR029: allows an IE proposing a SOG to designate it as part of a self-limiting facility during the GIM process.

The directors separately approved five non-unanimous revision requests recommended by the TAC:

        • NPRR1106: codifies the grid operator’s current practice of deploying emergency response service when physical responsive capability falls below 3 GW before declaring an EEA.
        • NPRR1109: allows a resource entity to bring a decommissioned generating unit back to service if it notifies ERCOT within three years of its removal from the network operations model.
        • NOGRR236: allows ERCOT to instruct TDSPs to deploy any available distribution voltage-reduction measures before declaring an EEA.
        • NOGRR237: aligns the Nodal Operating Guide with NPRR1106’s protocol changes.
        • OBDRR036: revises the ERS procurement methodology document to mesh with NPRR1106.

Cooper Vetoes NC Bill Prohibiting Bans on Natural Gas Hookups

North Carolina Gov. Roy Cooper on Thursday vetoed a bill that would have prohibited the state’s cities and counties from banning natural gas hookups in residential construction.

To date, similar bills — heavily supported by the natural gas industry — have been passed in 20 states and are pending in four more. These “pre-emptive bills” have all been enacted in the past two years in response to ordinances or building codes now adopted in 50 cities in California to promote home electrification and reduce carbon emissions by banning natural gas hookups in new construction, according to S&P Global.

In a statement released with the veto announcement, Cooper said, “This legislation undermines North Carolina’s transition to a clean energy economy that is already bringing in thousands of good paying jobs. It also wrongly strips local authority and hampers public access to information about critical infrastructure that impacts the health and wellbeing of North Carolinians.”

The governor has been pushing for the state to cut its emissions by 70% over 2005 levels by 2030, a goal codified in a new law, HB 951, which he signed in October. According to a 2019 greenhouse gas inventory produced by the North Carolina Department of Environmental Quality, residential emissions then accounted for 3.5% of the statewide total.

The vetoed bill, HB 220, would stipulate that cities and counties in the state cannot “adopt an ordinance that prohibits, or has the effect of prohibiting, the connection, reconnection, modification or expansion of an energy service based upon the type or source of energy to be delivered to an individual or any other person as the end user of the energy service.”

The specific sources of energy that cannot be prohibited are defined in the bill as “natural gas, renewable gas, hydrogen, liquefied petroleum gas, renewable liquefied petroleum gas or other liquid petroleum products.”

To date, no North Carolina cities or counties have passed or proposed such bans, which led some Democratic lawmakers to question the need for the bill when it was introduced earlier this year. Defending the pre-emptive action, Rep. Dean Arp (R), a bill sponsor, said, “Energy policy is a state issue,” and a bill protecting consumer choice “absolutely clarifies that before it becomes a problem.” (See Gas Industry Brings Fight Against Building Electrification to NC.)

In a statement released following Cooper’s veto, Arp said the bill was intended to leave “household decisions like whether or not to have a gas stove in their home to consumers themselves. The heavy hand of government has no place in the personal decisions North Carolinians make for their households.”

House Speaker Tim Moore (R) also criticized the veto, characterizing it as an act of “partisanship over common sense.”

To override a veto, a three-fifths majority is needed in each chamber of the General Assembly: 30 votes in the Senate and 72 in the House of Representatives. There are 28 Republicans in the Senate and 69 in the House.

‘It’s not About Today’

Maggie Shober, research director at the Southern Alliance for Clean Energy, praised Cooper for “standing up for local control of how to make our buildings safer and cleaner. These ban-the-gas-ban bills have been pushed by special interests across the country, with little thought to the customers that will be forced to pay for expanding fossil fuel infrastructure in their neighborhoods while the science has been clear: To avert the worst of climate change, we need to reduce, not expand, our use of fossil fuels.”

According to the U.S. Energy Information Administration, about one in four North Carolina homes are heated with natural gas. EIA also ranks the state as one of 10 in the U.S. with the lowest per capita use of natural gas, although natural gas consumption there has quadrupled in the past decade, mostly from its use in electricity generation.

But the debate here and in other states has centered on the economics and emissions of natural gas versus electricity.

The American Gas Association does not take positions on state policies, such as pre-emptive laws prohibiting bans on natural gas hookups, but spokesperson Jake Rubin argued that natural gas is both a cheaper, cleaner and more reliable fuel for home heating and cooking.

“A natural gas home has fewer CO2 emissions than a home that uses electricity for its various applications … because of the efficiency of the delivery infrastructure,” Rubin said. “It takes a lot more energy to get electricity to a home than it does to get natural gas to a home.”

And because “most of electricity is made using either coal or natural gas,” he said, a home using natural gas for space and water heating and cooking will have lower emissions than an all-electric home.

But Ram Narayanamurthy, program manager for buildings at the Electric Power Research Institute, said that calculations of an electrified home’s emissions will depend on the generation mix of the utility providing the electricity. And, he noted, many utilities are now committing to decarbonizing their power supplies.

“We find that in places like California, the generation mix they have today, all-electric homes [produce] about 40% less emissions than a mixed-fuel home,” he said. “In a place like Texas, it’s closer to neutral.

“The fact is that as you set the goals for going zero carbon, as the electricity gets cleaner, the grid gets cleaner and cleaner,” he said. “The trend is that your all-electric home is going to have far less emissions. It’s not about today, but if you look at 2030, the generation that’s in 2030, that all-electric home that you build today is going to be a lot cleaner.”

Which Will be Cheaper, Cleaner?

In New Jersey, the latest state to consider a pre-emptive prohibition on bans on natural gas hookups, gas advocates are also pointing to the future potential for low-carbon fuels as a reason to maintain gas pipelines.

At a recent hearing in the New Jersey Senate, Robert Pohlman, managing director of innovation and strategic initiatives at New Jersey Natural Gas, said that ratepayers had invested $17 billion to create the infrastructure through which natural gas is supplied to their homes. That infrastructure could be used to bring alternative fuels, such as hydrogen or renewable natural gas, to consumers, but it would be discarded if buildings transitioned to electricity. (See NJ Legislators Back Alternatives to Electric Heat.)

“The state must not close itself off from the future benefits of investment, innovation and competition happening around low-carbon fuels today,” Pohlman said.

But whether natural gas or electricity is cleaner and cheaper for North Carolina consumers will depend, again, on the local generation mix and rates. EIA ranks North Carolina in the top 10 for overall electricity consumption and the top five for residential electricity sales.

Duke Energy, the state’s largest utility, has committed to cutting its carbon emissions by 50% by 2030 and achieving net-zero emissions by 2050. However, the utility’s integrated resource plan, still pending before the North Carolina Utilities Commission, anticipates adding thousands of megawatts of natural gas generation through 2035.

The utility’s rates will also likely increase in coming years. Under HB 951, Duke will be able to file multiyear rate plans, under which it will only have to file a full rate case once every three years, rather than yearly as it does now. It will be able to raise rates up to 4% per year in between without the approval of the NCUC.

Con Ed Submits Proposal for New Jersey Offshore Transmission

A subsidiary of New York-based utility Consolidated Edison (NYSE:ED) has submitted a proposal for a 2.4-GW transmission “backbone” to the New Jersey Board of Public Utilities (BPU) to bring offshore wind-generated electricity to the PJM grid.

The proposal submitted by Con Edison Transmission would create Clean Link New Jersey, a high-voltage network of multiple undersea transmission cables.

“The offshore mesh-style network is flexible and modular to allow various offshore wind projects to plug in as they become ready to generate,” the company said in a Dec. 6 statement outlining the project. A description of the proposal posted on the PJM website states that an undersea “power corridor” through which cables will run “provides the opportunity to better manage costs and improve grid stability, while significantly reducing permitting and environmental impacts.”

Con Ed submitted the proposal under the competitive solicitation by the BPU and PJM for new transmission and grid upgrades to handle the 7,500 MW of offshore wind energy that the state expects to bring online by 2035. (See New Jersey Seeks OSW Transmission Ideas.)

The organizations issued the solicitation under FERC Order 1000’s state agreement approach, under which the BPU requested that PJM integrate the state’s offshore wind goals into the RTO’s Regional Transmission Expansion Plan process. About 80 documents are posted on the PJM webpage that lists proposals submitted under the solicitation. (See PJM, NJ Staff Brief Stakeholders on State Agreement Approach.)

Proposals were accepted until September, and PJM officials are now reviewing them. The BPU expects to begin evaluating them early next year and will decide which ones fit their needs in the third or fourth quarter.

First NJ Venture

New Jersey has so far approved three offshore wind projects in two phases totaling 3,758 MW, about half the state’s target. Danish developer Ørsted’s Ocean Wind, an 1,100-MW project, won the first solicitation in 2019, and in June the state awarded the developer a second project, its 1,148-MW Ocean Wind II, in the second solicitation. The BPU also backed Atlantic Shores, a 1,510-MW project developed by a joint venture between EDF Renewables North America and Shell New Energies US.

Con Edison Transmission’s project is the subsidiary’s first venture into New Jersey, although another subsidiary of Con Ed, Orange and Rockland Utilities, serves customers in Northern New Jersey, company spokeswoman Anne Marie Corbalis said. The release said Con Edison Transmission is “developing a portfolio of transmission projects delivering renewable energy to customers.”

The Clean Link New Jersey proposal includes plans for a 27-mile fiber optic undersea cable and 23 miles of onshore cable, and the project will be capable of handling energy from multiple projects, according to the proposal. The project consists of eight transmission components, including substations onshore and offshore, transmission lines and a 500-foot-wide right of way, which will together cost $2.75 billion, according to the proposal.

Public Service Enterprise Group (NYSE:PEG) announced in October that it has submitted several projects to the BPU/PJM solicitation in partnership with Ørsted, collectively known as Coastal Wind Link. The company declined to provide details of its submissions. Proposals listed on the PJM website under PSEG’s name only include one to conduct a series of upgrades to the Central Jersey grid system.

The list of projects on the site submitted under Coastal Wind Link includes a 92-mile offshore transmission line that will come ashore at the Raritan River and then run 6 miles onshore, mainly on public rights of way, to a converter station in Sewaren, in Middlesex County, at a cost of $848 million. Another proposal would create a converter platform in the South Hudson offshore area planned for the two Ørsted developments that will receive AC power from the wind farms, convert it to HVDC and move it to the shore, with a cost of the various components of $1 billion.

Coastal Wind Link’s proposals would “provide a reliable, resilient and cost-effective infrastructure to the state,” the company said in a statement. The proposals “encompass individual and networked solutions and would ensure that New Jersey has a clear path to connect to the offshore wind energy coming online during the next decade while minimizing environmental impacts along New Jersey’s coastline,” the statement said.

Biden Appoints California PUC Commissioner to Head EPA Region 9

EPA said Thursday that President Biden intends to name California Public Utilities Commissioner Martha Guzman Aceves to run the region of the agency that includes California, Arizona, Nevada and Hawaii, implementing the administration’s environmental agenda in the far West.

Guzman Aceves has served for five years on the CPUC. She worked previously as former Gov. Jerry Brown’s deputy legislative affairs secretary and for the California Rural Legal Assistance Foundation and the United Farm Workers. Much of her focus at the commission has been on providing clean energy to underserved communities and preventing disconnections of basic utilities.

Martha Guzman Aceves (CPUC) FI.jpgCPUC Commissioner Martha Guzman Aceves | CPUC

“Given Martha’s extensive background in successfully delivering access to underserved communities, I am confident she is an excellent choice to lead our Region 9 team,” EPA Administrator Michael Regan said in a statement. “Martha is an experienced leader that values economic justice and will represent the best interests of the residents in the region.”

Guzman Aceves said she was “honored to be appointed by President Biden to serve as administrator of EPA Region 9 under the leadership of Administrator Regan. And I am grateful for the opportunity to work with the resilient staff at Region 9 as we tackle the chronic and emerging environmental issues in our communities.”

The move continues a series of transitions at the CPUC, an agency tasked with ensuring resource adequacy, preventing utilities from igniting wildfires and shepherding the state through its transition to 100% clean energy by 2045.

CPUC President Marybel Batjer announced in September that that she planned to step down at the end of the year with five years left in her seven-year term. Gov. Gavin Newsom in late November named his senior energy adviser, Alice Reynolds, as the commission’s next president. (See California PUC President to Step Down and Calif. Governor Names Next CPUC President.)

In December 2020, Newsom named then-CPUC Commissioner Liane Randolph as chair of the California Air Resources Board, which oversees vehicle emissions and other types of air pollution. Randolph replaced retiring Chair Mary Nichols, whom Biden reportedly was considering to head EPA at the time. Instead, he appointed Regan, then head of North Carolina’s Department of Environmental Quality. (See EPA Nominee Regan Receives Bipartisan Support.)

EPA on Thursday also announced the appointments of Earthea Nance and Meg McCollister as administrators of its regions 6 and 7, respectively. Nance is an environmental engineer and an associate professor of urban planning and environmental policy at Texas Southern University; Region 6 covers Arkansas, Louisiana, New Mexico, Oklahoma and Texas. McCollister is an independent consultant based in Kansas City, Mo., where she serves “as an adviser and strategic thinker in areas including environmental, health and social improvement initiatives, as well as communication strategies,” according to EPA. Region 7 covers Iowa, Kansas, Missouri and Nebraska.

FERC Rejects SEEM Opponents’ Rehearing Requests

Another door has been closed to opponents of the Southeast Energy Exchange Market (SEEM), after FERC on Friday ruled that their request for a rehearing on the market was submitted too late to be heard (ER21-1111, et al.).

The opponents — an ad hoc alliance of environmental and clean energy organizations calling themselves the Public Interest Organizations (PIOs), and a separate group referred to as the Clean Energy Coalition (CEC) — filed their rehearing requests Nov. 12. (See SEEM Opponents File Rehearing Requests.) In its Friday order, FERC declined to engage with these criticisms on the grounds that the opponents should have submitted their requests by Nov. 10.

Both groups also submitted alternative requests in the event FERC denied rehearing. The PIOs asked for their objections to SEEM to be the subject of a “paper hearing with a technical conference before briefing,” while the CEC asked the commission to provide “clarification and confirmation on the role and function of the SEEM proposal and the platform that will enable transactions.”

However, FERC rejected these requests as well. Because the PIOs’ rehearing request was untimely, the commission said the issues raised therein could not be set for a paper hearing. Regarding the CEC’s request, FERC said that “in the absence of an order” relating to SEEM, “there is nothing to be clarified.”

Because the commission was split 2-2, SEEM was automatically approved “by operation of law” Oct. 12. Hence, there was no actual order from the commission. (See SEEM to Move Ahead, Minus FERC Approval.)

According to the Federal Power Act, any parties “aggrieved” by a FERC order may apply for rehearing within 30 days of its issuance. But because FERC did not issue a formal order in the proceeding, the PIOs and CEC recognized Oct. 13 — when FERC announced that the agreement had taken effect — as the date of FERC’s “order.” Under this logic, the deadline for submitting the rehearing request was Nov. 12, making their filings timely.

By contrast, SEEM’s supporters, in a Nov. 30 filing, argued that the “date of issuance” is not when the commission announces a decision, but when it issues an order — or, in this case, fails to do so. (See SEEM Members Seek to Quash Rehearing Requests.) Because Oct. 11 was the deadline for FERC to issue an order, members said that rehearing requests must be filed 30 days after this date, meaning that any requests filed after Nov. 10 were out of time.

FERC did not cite either filing in Friday’s order, but the commission acknowledged that it “has not previously explained … the proper calculation of the deadline for rehearing requests following the failure of the commission to act.” Its subsequent clarification echoes the opinion of SEEM members, with FERC stating that the date of its “order” in this case was Oct. 11 and that the 30-day clock for rehearing requests “starts running on the day after the last day that the commission could have taken action,” meaning the deadline was Nov. 10.

When FERC deadlocked on the original SEEM proposal, Chair Richard Glick and Commissioner Allison Clements — both Democrats — opposed the agreement, while Republican Commissioners James Danly and Mark Christie approved of it. The commission’s filing on Friday did not mention the views of specific commissioners, though it did say that Commissioner Willie Phillips, the newest member who was confirmed by the Senate on Nov. 16, did not participate. (See Senate Confirms FERC Nominee Willie Phillips.)

SEEM Moving Toward 2022 Launch

Because the SEEM agreement took effect in October, FERC has approved revisions to four of the participating utilities’ tariffs implementing the special transmission service used to deliver the market’s energy transactions. (See FERC Accepts Key Tariff Revisions to SEEM.) Members have also submitted further changes to the commission that would implement a series of “transparency enhancements” to the market. The changes were proposed in June in response to FERC’s first deficiency letter, but the commission was not able to mandate their inclusion in the SEEM agreement because it did not issue an order. (See SEEM Members Offer Rule Changes.)

SEEM members also announced on Friday that they had chosen technology solutions company Hartigen to build and deploy the market’s technology platform. The selection of Hartigen follows a request for proposals issued in March. In a press release, members said they plan to have the new market online by the third quarter of 2022.

Implementation Underway for NWPP’s Western RA Market

The Northwest Power Pool (NWPP) last week took its first steps in implementing its Western Resource Adequacy Program (WRAP), opening the door for participants to submit resource data for a “nonbinding” phase of the capacity market, which the organization says will serve as a “beta test” for a final program design.

The data from the 26 “Stage 1” participants are needed to model “forward showings” of resource adequacy and availability for the WRAP’s winter 2022 season commencing next November. In the future, participants will be required to provide their forward showings seven months in advance of the summer (June-September) and winter (November-March) compliance periods.

NWPP developed the WRAP to help Western balancing authorities cope with potential generation shortages during critical hours as the region confronts the retirement of increasing numbers of thermal generators and its growing reliance on variable renewable resources such as wind and solar.

The WRAP is intended to increase visibility into existing RA conditions in the West, addressing concerns among industry stakeholders and state regulators that load-serving entities are unknowingly relying on the same capacity resources without realizing it, threatening system reliability during periods of scarcity. The program is designed to provide participants a framework in which to access capacity resources when a participant is experiencing an extreme event.

“An extreme event could be when a participant’s load is in excess of their [forward showing] forecast or resources (generation and transmission) are experiencing unexpected outages; this portion of the program unlocks the footprint’s load and resource diversity,” NWPP explained in a “detailed design” document released last July. “The program seeks to achieve a balance between planning in a reasonably conservative manner but also to provide flexibility in order to protect customers from unreasonable costs.” 

In developing the WRAP, NWPP distinguished among various forms of RA — such as flexibility, energy and capacity — and decided to initially focus on a capacity-based program “with a demonstration of [resource] deliverability.”

The WRAP will kick off next winter with a nonbinding, no-penalty phase, denoted as Stage 1 in the NWPP timeline. The absence of enforcement and penalties shields the program from FERC oversight, giving members additional time to iron out wrinkles and finalize its design.

The binding Stage 2 program will introduce a requirement that participants demonstrate to the RA program administrator that they have sufficient resources to meet required metrics for a compliance season seven months ahead of the operational timeline or face a penalty based on the cost of new gas peaking plant.

The 26 Stage 1 participants represent more than 65,000 MW of winter peak load and nearly 67,000 MW of summer peak load within the Western Interconnection.

“This group is diving into the remaining program design questions, including a task force dedicated to a second transmission hub that would allow participants in the southwest region to more readily access program diversity; one considering specific contract terms that would be necessary to ensure an enhanced WSPP Schedule C agreement would count as qualified capacity; and others considering other outstanding issues,” NWPP said in a statement last week.

“We are very excited about the interest and commitment to the WRAP we’ve seen from former NWPP members and new participants alike. The level of excitement for the program’s forward program speaks to the determination and dedication of the participants,” NWPP CEO Frank Afranji said.

NWPP also noted last week that the move to implement the WRAP officially kicks off its working relationship with SPP, which has been retained to administer the program. (See SPP to Operation NWPP’s Resource Adequacy Program.)

“SPP has begun providing program operation services, including facilitating the collection of participants’ data to perform modeling for the upcoming seasons,” NWPP said.

“As we reach this significant milestone in the WRAP’s implementation, SPP is grateful for the relationships we’ve built and the opportunity to work with such a collaborative and diverse group of entities,” SPP CEO Barbara Sugg said. “This resource adequacy program will play an important part in the reliability of the Western grid, and it’s exciting to see new participants joining the effort.”

WRAP Stage 1 participants include Arizona Public Service, Avangrid, Avista, Black Hills Energy, Basin Electric Power Cooperative, Bonneville Power Administration, Calpine, Chelan PUD, Clatskanie PUD, Douglas PUD, Eugene Water and Electric Board, Grant PUD, Idaho Power, NorthWestern Energy, NV Energy, PacifiCorp, Portland General Electric, Powerex, Puget Sound Energy, Seattle City Light, Snohomish PUD, Shell Energy, Salt River Project, Tacoma Power, Turlock Irrigation District and The Energy Authority, which is representing seven Washington and Oregon publicly owned utilities.

Texas RE Briefs: Dec. 8, 2021

The Texas Reliability Entity highlighted its involvement in a joint NERCFERC inquiry into the February winter storm that nearly collapsed the ERCOT grid but warned its Board of Directors that next year could be more challenging.

“Still, there’s so much to do to ensure such an event never happens again,” Board Chair Milton Lee said. “We must hold ourselves accountable to develop future strategies, implement them, and ensure we monitor and update them for future improvements.”

NERC and FERC released their joint report in November, highlighting the failure of electric and gas utilities to adequately prepare for Winter Storm Uri’s frigid temperatures. The event caused more than 23 GW of manual firm load shed as generators and their supply lines froze. (See FERC, NERC Release Final Texas Storm Report.)

Texas RE staff were among the nearly 50 subject matter experts who helped prepare the report. Their final report included 28 recommendations that covered both industries and went beyond NERC reliability standards revisions to address cold weather, which were approved in August 2021.

“This report recognizes that folks at the RTO and ISO level coordinated very well and made the best of the situation by bringing in [power] supplies from their neighbors,” said Mark Henry, Texas RE’s director of reliability services and registration.

Henry said the RE staff’s next task is a deeper dive into the unavailability of ERCOT’s black start units during Winter Storm Uri.

The board approved the Nominating Committee’s recommendation that Lee again serve as its chair in 2022 and that Crystal Ashby serve as vice-chair.

The directors also approved Joseph Younger’s selection as Texas RE’s COO.

The Member Representatives Committee met before the board meeting and approved a work plan for NERC Project SAR-012: Revisions to the Standards Development Process. The work plan lays out the steps for revising a Regional Standard in accordance with Texas RE’s standards development process document.

Annual Membership Meeting

Texas RE CEO Jim Albright said staff is “leaning in” to a NERC audit next year, the result of a FERC order that applies to all six regional entities.

“We’re ready to show our work and be involved,” he said during the organization’s short annual membership meeting.

Albright said staff’s full return to the workplace is still “in flux,” given the coronavirus’ stubborn presence and the mutating variants. A target date has been set for Jan. 10, but staff will be limited to two days a week.

“We’ll be very cautious about bringing employees back to the office,” he said.

Resuming onsite stakeholder engagement will be a “challenge,” Albright said. He said the organization will focus on “comprehensively engaging” with stakeholders on all extreme events, not just those related to the winter.

Staff said Texas RE’s membership re-elected Lee to serve another three-year term as independent director. Lee’s term will expire Dec. 31, 2024.

The membership also elected three new MRC members: Acciona Energy USA Global’s George Brown and Vistra’s Kristopher Butler as the generation sector’s representatives, and Denton Municipal Electric’s Cameron Molsbee as the municipal alternate.

Lee honored Oncor Electric’s Liz Jones for her service as the MRC’s vice chair. Jones remains on the committee, which will elect its 2022 chair and vice-chair in January.

Texas RE added six new members in 2021, pushing its membership roll to 116. Five of those new members were in the generation sector, thanks to the continued growth of the state’s renewable energy.

MISO Board of Directors Briefs: Dec. 9, 2021

MISO Pulls off 1st Face-to-face Meetings Since Start of Pandemic

ORLANDO, Fla. — MISO Board Week meeting marked MISO’s first plunge into in-person gatherings in nearly two years.

“Isn’t it great to be back in person?” CEO John Bear said in opening the Board of Directors’ meeting Thursday, held at Loews’ Sapphire Falls Resort, near Universal Orlando. “I was excited to put my tie on this morning.”

Organization of MISO States President Julie Fedorchak thanked MISO for “forging ahead” with an in-person meeting. She said the RTO showed it can be done in a “safe and pragmatic way.”

“There’s nothing quite like face-to-face communication,” Fedorchak said.

Board Week drew about 90 stakeholder attendees. MISO also offered a virtual attendance option.

MISO Board Week 2021-12-08 (RTO Insider LLC) Alt FI.jpgSocially distanced attendees at MISO Board Week | © RTO Insider LLC

MISO is charting a return to in-person meetings at its offices in Carmel, Ind.; Eagan, Minn.; and Little Rock, Ark., in late January.

The grid operator plans to reduce meetings of its major stakeholder committees from monthly to eight times per year and rotate which meet in-person, to limit virus exposure. Some stakeholders have misgivings that MISO can accomplish all its market and reliability aims and related FERC filings with just eight meetings per year, four of them in a virtual format. (See MISO Modifies Stakeholder Meeting Schedule.)

Robert Kuzman, MISO’s head of stakeholder relations, called the plan “a good start to get back in person as safely as we can.”

“This is a partnership. We intend to be as efficient as we can while still working through out goals,” Kuzman told the Advisory Committee on Wednesday.

Members asked if MISO would enact vaccination requirements for stakeholders wanting to enter a conference room.

Chief Customer Officer Todd Hillman said MISO is still navigating which requirements in-person meeting attendees must follow.

“Given the 15-state footprint, we’re trying to do right by all,” Hillman said.

Hillman said this week’s event will serve as the “litmus test” for MISO’s on-site meetings. So far, he said, MISO envisions socially distanced attendees, with tables spread apart.

MISO: New Market Platform Running by 2025

MISO said it remains on track for a late 2024 completion for its market platform replacement.

The RTO this year launched its new, one-stop system modeling tool and new market user interface, the nonpublic site market participants use to submit energy bids and offers. It believes it can complete the conversion by late 2024.

MISO is using Siemens smart grid technology to support its new model manager. It plans to cut over to a new method of member data submittal by March and retire its old method of data collection thereafter.

Chief Digital Officer Todd Ramey said MISO will retire both its legacy modeling system and old market user interface in 2022.

Next year, the RTO will work to debut an energy storage participation model on its vintage market platform. It previously said it couldn’t both roll out energy storage offers and focus on the platform replacement. Now it must introduce the storage participation model on both its old and new market platforms. (See MISO: No Choice but to Double Up on 841 Compliance.)

Late next year, MISO anticipates that it will receive its new day-ahead market clearing engine from General Electric.

This year marked the fourth full year of the ongoing swap of the grid operator’s old and rigid platform for a new modular one that can host more complex market offerings.

Board Approves Budget Shaped in part by COVID-19

MISO’s Board of Directors has greenlit a $376.1 million total budget for 2022.

The budget includes a $282.3 million base operating expenses, $37 million in project investments and $56.8 million in other operating expenses.

The 2022 budget is 1% lower than last year’s. MISO executives said pandemic impacts continue to influence budgeting. The RTO originally estimated that it would be largely free of pandemic irregularities in summer 2021.

Like other companies, MISO is contending with cybersecurity issues, supply chain issues, inflation and a tight labor market. CFO Melissa Brown said in fall that MISO was waiting on about $4 million in physical goods, including laptops, tables and new wallboards for the control room, that had yet to be delivered.

Brown also expects that MISO’s higher-than-expected employee vacancy rate will persist into 2022.

She said compared to pre-pandemic levels, MISO is earning a much lower interest rate on its cash, money it usually uses to offset some expenses.

Increasingly severe weather events are also upping spending. Executives said they spent about $2 million over 2021 to answer state- and federal-level questions about MISO’s decision-making and operations during extreme weather events.

Year to date, MISO is $5 million underbudget from its $226 million base operating allotment.

MISO Director Barbara Krumsiek thanked the RTO’s financial team for balancing a budget despite an “extraordinary number of variables.”