Search
`
November 20, 2024

Maine Supreme Court Hears Entangling Arguments in NECEC Appeals

The Maine Supreme Court heard oral arguments Tuesday in two uniquely entwined appeals related to the New England Clean Energy Connect (NECEC) transmission project.

A court determination on the retroactive application of a Maine voter referendum on transmission development passed in November could affect the outcome of an appeal of a lower court decision to vacate a 1-mile lease of public land for the project. The validity of that lease could, in turn, determine the outcome of the constitutionality of applying the law established by the referendum to the NECEC project.

Maine law prohibits public land — including state parks or land set aside for conservation — from being “reduced” or its uses “substantially altered” unless the Legislature approves the changes with a two-thirds majority vote. A group of state legislators, the Natural Resources Council of Maine and a group of residents challenged the Maine Bureau of Parks and Lands’ (BPL) grant of a public land lease to NECEC’s developer, Avangrid (NYSE:AGR) subsidiary Central Maine Power (CMP), because it did not seek the Legislature’s approval.

The Superior Court agreed, vacating the lease. The court also found that the agency did not provide notice to the Legislature or the public of the lease contracts.

Meanwhile, voters in November approved a referendum that would categorize any transmission construction after September 2014 as a substantial alteration under the law, thus requiring the Legislature’s approval.

CMP and its development partner, NECEC Transmission — as well as BPL — appealed the Superior Court’s decision. Arguing on behalf of BPL Director Andy Cutko on Tuesday, Maine Assistant Attorney General Lauren Parker said that the statute on park lands does not apply to BPL’s leasing authority over lands it manages for “specified beneficial purposes, including electric power transmission.”

At the time BPL executed the lease with CMP, she said, Cutko had the authority to issue 25-year leases for transmission, contrary to the lower court’s ruling.

CMP attorney Nolan Reichl, a partner in Pierce Atwood’s Litigation Practice Group, argued separately that the statute on park lands calls a BPL determination on land use into question.

“If there is no substantially altered use of the land, there is no two-thirds vote requirement,” he said. The BPL, he added, has no obligation to make any case-by-case determinations on usage.

The legislature, he said, has “never required BPL to run any particular administration process in that respect,” with thousands of executed leases all “consistently reported” to the legislature.

It’s not clear that BPL made a use determination, Chief Justice Valerie Stanfill said, adding that the court could, therefore, remand the case to BPL to do so.

Referendum Appeal

The developers had also challenged the constitutionality of the voter referendum because of its retroactivity and that it deprived them of their “vested right” to build the project. The Superior Court disagreed, upholding the change to the law.

James Kilbreth, an attorney at Drummond Woodsum representing the group that challenged the lease, on Tuesday argued before the Supreme Court that the referendum invalidates the lease and therefore makes all questions in the appeal of its vacatur irrelevant. The appeal of the referendum, which relies on the validity of the lease, would therefore also be irrelevant, he said.

The referendum “moots all the questions” in the lease appeal, he said. State law, he added, also clearly establishes that when laws change during an appeal, as is the case with the referendum, the court must apply the new law in that case.

Kilbreth argued that the lease appeal must be decided before the referendum appeal. To bring the referendum appeal, he said, the developers need a valid lease because they claim that the lease is the basis for their vested right.

John Aromando, a partner at Pierce Atwood and attorney for NECEC Transmission and Avangrid, said that the existence of the lease appeal does not invalidate the lease in and of itself. A valid lease, he argued, ensures that the referendum cannot take away their vested right.

With the validity of the lease under appeal, the outcomes of both cases are uniquely connected.

In defending the referendum, the state argued that the concept of a vested right is not straightforward.

The vested right “as Avangrid conceives it, does not allow for any consideration of the governmental interests at stake in legislation,” Maine Assistant Attorney General Jonathan Bolton said.

In the developers’ view, Bolton said, government and public interests are “irrelevant” if construction of a project has started. “The modern view is that due process by its very nature requires consideration of both private rights and public or government interest,” he said.

NECEC agreed last fall to discontinue construction activity for the project pending outcome of the appeals.

“Delaying the construction of the project by 12 months will make it impossible for the company to complete the project by the contracted deadline in mid-2024,” Thorn Dickenson, president and CEO of NECEC Transmission, said in a September affidavit to the Supreme Court. The delay, he added, could cost as much as $83 million.

In closing the hearing, Chief Justice Stanfill said there is a “great deal” of interest in the referendum appeal and, by extension, the lease appeal.

“I don’t think this courtroom has been this full since I’ve been here,” she said, adding that the court will try to issue a written decision as soon as possible.

North Carolina OSW Auction Nets $315 Million

Duke Energy (NYSE:DUK) and France’s TotalEnergies (NYSE:TTE) agreed Wednesday to pay a combined $315 million to lease 110,000 acres off North Carolina that could produce 1.3 GW in offshore wind.

After 18 rounds of bidding, TotalEnergies Renewables USA agreed to pay $160 million for Lease OCS-A 0545 and Duke Energy Renewables Wind will pay $155 million for Lease OCS-A 054, the Bureau of Ocean Energy Management (BOEM) reported.

The winning bids in the Carolina Long Bay auction averaged almost $2,900 per acre, more than double the prices paid in BOEM’s 2018 auction for three sites off the Massachusetts coast, but a fraction of the record $8,837/acre paid for sites in the New York Bight in February. (See Fierce Bidding Pushes NY Bight Auction to $4.37 Billion.)

Lower prices were expected, because unlike many other East Coast states, North Carolina has no statutory offshore wind goal, although Gov. Roy Cooper issued an executive order in 2021 calling for 2.8 GW of offshore wind capacity by 2030 and 8 GW by 2040.

North Carolina House Bill 951, enacted in October, requires the state Utilities Commission to cut the state’s electric sector carbon emissions to 70% below 2005 levels by 2030, with carbon neutrality by 2050.

Duke Energy, the state’s largest utility, has proposed 2,650 MW of OSW by 2035 in two scenarios in its 2020 integrated resource plan.

ClearView Energy Partners said H.B. 951 was “a primary motivator” for bidders in the auction. “The law did not create offshore wind-specific targets, but it does require each electric public utility to submit a ‘Carbon Plan’ describing how it intends to achieve the targets” to the NCUC by May 16, ClearView said. “The law also compels electric utilities to propose a program for the competitive procurement of energy and capacity from renewable energy facilities, inclusive of offshore wind.

“We regard state-led offshore wind solicitations as the most important policy driving offshore wind in the U.S. today. However, today’s winning bids exceed that of all other offshore wind lease auctions held prior to the New York Bight sale,” ClearView added. “This could suggest that an emerging domestic offshore wind supply chain and demonstrable under development and in-service projects over the last few years may sufficiently validate the viability of some offshore wind in waters that do not directly serve active state solicitations.”

Bidding

BOEM removed hundreds of thousands of acres from consideration since its 2012 North Carolina call for information and nominations to avoid conflict with the habitat of the North Atlantic Right Whale. It also eliminated areas within 20 statute miles of the shoreline and areas that would have overlapped with a navigational fairway proposed by the U.S. Coast Guard.

Following the removals, BOEM said it divided the remaining lease area into two nearly equal lease areas with similar acreage, distance to shore and wind resource potential.

Bidding for the two 55,000-acre leases increased in virtual lockstep for the first 11 rounds, beginning at the minimum bid threshold of $2.75 million with a total of nine bidders. By round 11, prices had risen to $100 million each while the number of bidders dropped to three. Sixteen companies had qualified to bid.

Heather Zichal, CEO of the American Clean Power Association, said the lease sale should “be a sign to Congress to repeal the 10-year moratorium on offshore wind leasing off the coasts of North Carolina, South Carolina, Georgia, and Florida. Creating a stable policy platform for offshore wind development and facilitating the first wave of significant projects will provide certainty for the industry, strengthen the workforce, and bolster domestic supply chains up and down the coasts and across the country.”

Stipulations

BOEM included stipulations to encourage “construction efficiency” and development of a domestic supply chain. Lessees will be required to make reasonable efforts to enter a project labor agreement covering construction. (See Ørsted Inks Labor Agreement for US OSW Construction.)

“For the first time, the federal government used an auction system designed to spark investment directly into U.S. manufacturers, small businesses, shipbuilders and new workforce training, accelerating development of the already-emerging domestic supply chain,” said Liz Burdock, CEO of the Business Network for Offshore Wind.

Draft Plan Seeks Calif. Carbon Neutrality by 2045

The California Air Resources Board has released a draft plan for the state to reach carbon neutrality by 2045, tentatively rejecting alternatives that would achieve the net-zero goal 10 years sooner.

CARB released the draft climate change scoping plan on Tuesday and has scheduled a public hearing on the plan on June 23. Written comments are due by June 24.

The agency expects to adopt a final scoping plan by the end of the year.

The scoping plan is a roadmap for the state to meet greenhouse gas reduction goals. State law requires a scoping plan update every five years; the last update was in 2017.

In its process for developing the scoping plan, CARB analyzed four different scenarios. Alternatives 1 and 2 would bring the state to carbon neutrality by 2035, while Alternatives 3 and 4 would reach the target in 2045.

The alternatives differ in other key areas, including the rate of consumer adoption of clean technologies; reliance on carbon capture and sequestration (CCS) and CO2 removal; and the remaining demand for fossil energy after carbon neutrality is reached.

Choosing an Alternative

The draft scoping plan proposes moving forward with Alternative 3.

“It is the proposed alternative because it best achieves the balance of cost-effectiveness, health benefits and technological feasibility,” the draft plan states.

With its extra 10 years to achieve carbon neutrality compared to Alternatives 1 and 2, the proposed alternative provides more time for technologies to scale up and be deployed at lower costs, according to CARB.

The proposed alternative would reduce petroleum usage by about 90% by 2045 and achieve a state target of reducing GHG emissions 80% by 2050.

In comparison to Alternative 4, the other scenario with carbon neutrality in 2045, the proposed alternative includes a faster adoption rate of clean technologies and less reliance on CO2 removal.

The most aggressive of the scenarios is Alternative 1, which would nearly eliminate fossil fuel combustion by 2035. The alternative would require early retirement of millions of gasoline- and diesel-powered vehicles as well as natural gas appliances.

Alternative 1 has a limited reliance on CCS. It would include direct regulation of dairies to reduce methane emissions.

The scenario has the highest direct costs of the four options and would cause the most slowing of economic growth, according to CARB’s analysis.

Alternative 3 would have the least impact on employment and economic growth among the four options, the draft plan said.

CARB’s board has the option to choose another scenario. The board could also keep the proposed alternative but incorporate elements from other scenarios.

Sector Specific Strategies

CARB said the most significant part of the draft plan is the aggressive reduction in the state’s fossil fuel reliance. That would be accomplished by building on existing strategies, including regulations, incentives and carbon pricing.

And the 2022 scoping plan differs from previous plans in its focus on “the accelerated rate of deployment of clean technology and energy within every sector,” the agency said.

The draft scoping plan details carbon reduction strategies in several key sectors.

In the transportation sector, the plan includes a transition to zero-emission vehicles while ensuring there’s enough zero-carbon alternative fuel for the vehicles. To achieve the latter, the plan proposes incentivizing private investment in new zero-carbon fuel production in the state and looking at options to increase the stringency of the low-carbon fuel standard.

The draft scoping plan also envisions a 22% reduction in vehicle miles traveled by 2045 compared with 2019 levels.

In the electricity sector, decarbonization strategies include addressing challenges to resource buildout, such as permitting, interconnection and transmission network upgrades.

The draft plan proposes exploring rate designs to increase affordability and continuing to look at the benefits of regional markets.

Another strategy proposed for the electricity sector is use of incentives and other programs to improve disadvantaged communities’ access to renewable energy projects, such as rooftop and community solar, battery storage and microgrids.

In addition, the plan proposes to evaluate the cap-and-trade program, with changes to strengthen the program if needed.

Adoption of the 2022 scoping plan is just “the beginning of the next phase of climate action,” according to CARB.

Approval of the plan will lead to the development of new regulations or strengthening of existing programs and regulations, the agency said. The changes will take place at CARB and at other state agencies.

“The unprecedented rate of transition will also require identification and removal of market and implementation barriers to the production and deployment of clean technology and energy,” the draft plan said.

SEEM Members Launch Engagement Series for Participants

Southeast Energy Exchange Market (SEEM) members began an informational series Wednesday to educate existing and prospective participants on how the market will function and what to expect before it goes live.

With a planned launch in the fourth quarter, SEEM’s founding utility members worked this spring to design the optimization platform that will drive the market, according to Chris McGeeney, manager of transmission services at Associated Electric Cooperative, a SEEM member.

“In late May, we’re going to start kicking the tires on the system and onboarding participants, and training will continue through the end of June,” McGeeney said during the first of three introductory webinars.

Participants will begin submitting their company information into the SEEM platform prior to the start of market trials scheduled for late summer, he said.

The region-wide, automated intra-hour platform will function as SEEM’s optimization engine based on inputs from market participants, such as bids and transmission capacity, to create bilateral matches between participants, according to McGeeney. An algorithm will process market participants’ inputs every 15 minutes for bids and offers, consider participants’ constraints, such as trading restrictions, and identify matches between the bids and offers.

Automated transactions, he said, will go to relevant transmission service providers, balancing authorities and generators for approval, and the SEEM platform will create transaction records between participants. At that point, energy flows will occur in the same way they do in the bilateral market.

“There’s no single clearing price or concept of financial congestion,” McGeeney said. “What’s going to turn the crank is this optimization engine looking for the optimal set of trades that benefits the entire region.”

Participation

Entities that want to voluntarily buy and sell within SEEM and are not formal market members must have control of a valid energy source or sink within the market’s footprint, according to Molly Suda, associate general counsel at Duke Energy (NYSE:DUK).

If that basic criterion is met, participants can sign up by executing the SEEM participation agreement, which is on file with FERC for review, she said.

Prospective participants also must have transmission service arrangements in place for the new non-firm energy exchange transmission service (NFEETS) product that all the transmission-owning members of SEEM will be offering.

Duke, Southern Company (NYSE:SO), LG&E and KU Energy, and Dominion Energy South Carolina (NYSE:D) have all filed with FERC and have, as part of their open access transmission tariffs, a form transmission service agreement for the NFEETS product that participants can execute, Suda said.

In addition, participants must have at least three enabling agreements with other non-affiliated participants. The enabling agreements function as an underlying bilateral contract that will allow participants to settle trades matched by the SEEM platform.

“That three-counterparty rule was put in place and contained in the market rules to establish a mechanism to prevent opportunities for parties to collude to gain preferential access to this new transmission service,” Suda said.

Operations

Matt O’Neal, project manager for energy policy at Southern, outlined some functional capabilities of the SEEM system during the webinar that attendees can discuss with their IT teams in advance of onboarding.

The SEEM platform will have several different authentication options for participant login, he said. And participants need to be thinking ahead to how they will access the platform. They can use the SEEM platform via a web user interface or APIs that connect to a company’s back-end systems.

“Many of our existing participants are building up internal systems that will formulate bids and offers, submit bids and offers or pull results back down to store in their energy trading risk management systems,” O’Neal said. “Many of the large vendors out there are offering SEEM add-ons or features to their products to interact with the SEEM.”

The onboarding process will also require participants to provide important details to help with the SEEM functionality, according to O’Neal. Those details include source and sink locations, tagging requirements and geographic constraints.

Consideration early in the onboarding process should go to how participants will formulate their bids and the volume of bids, O’Neal said, adding that with a fast-moving, 15-minute market, system automation could be “worthwhile.”

“If you do the math and think about a 15-minute market, that means you have … close to 35,000 trading intervals within a single year,” he said. “There is a lot of potential for deals; maybe more deals than you traditionally have today.”

Upcoming webinars in the series will take place May 20 and June 20 to give participants an overview of the SEEM network infrastructure and a closer look at tagging process and settlement.

Colorado Law Requires Cities to Adopt Green Building Codes

In an effort to decarbonize the state’s building sector, Colorado lawmakers passed a bill Wednesday that will require local governments to update their building codes to maximize energy efficiency in new construction.

The Building Greenhouse Gas Emissions Bill (HB22-1362) aims to reduce carbon emissions from new commercial buildings and homes through changes to municipal codes. By July 1, 2023, local governments will have to adopt building energy codes that meet or exceed the energy performance of the 2021 International Energy Conservation Code. It will also require that updated codes include language for solar-ready, energy-efficient and low-carbon buildings.

The legislation will establish a new Energy Code Advisory Board that will model the language required in updated energy codes, acting as a resource for municipalities. The co-chairs for the 21-member board will be representatives from the Colorado Energy Office and Department of Local Affairs, according to a press release from the Southwest Energy Efficiency Project.

“HB22-1362 will facilitate adoption of rooftop solar systems, high efficiency heat pumps, and electric vehicles in homes and commercial buildings that do not include these features from the start,” Meera Fickling, senior climate policy analyst with Western Resource Advocates, said in a statement. “This will extend the climate benefits of the bill beyond those provided by the energy efficiency improvements in new construction.”

In addition to the new code requirements, the bill funds grants for nonprofits and government buildings to upgrade to high-efficiency electric heating equipment and appliances. The bill also establishes the Clean Air Building Investments Fund, which will transfer $21 million from the general fund to finance the grant programs.

“The energy code requirements as well as the grants programs will expand the market for high efficiency heating and cooling equipment, insulation/air sealing, building control systems and other energy efficiency measures,” Patricia Rothwell, executive director of the Energy Efficiency Business Coalition of Colorado, said in a press release.

HB22-1362 is currently awaiting Gov. Jared Polis’ signature, with the legislature confident that he’ll sign the bill into law.

PJM MOPR Challenge May Set Legal Precedent on FERC Deadlocks

Challenges to PJM’s narrowed minimum offer price rule (MOPR) in the 3rd U.S. Circuit Court of Appeals do not just concern the RTO and its capacity market; they may set the precedent for all future legal reviews of tariff changes that go into effect because of a commissioner deadlock at FERC.

In briefs filed with the 3rd Circuit on Monday, the PJM Power Providers Group (P3), Electric Power Supply Association (EPSA) and two state utility commissions not only argued that the new MOPR threatened the competitiveness of the PJM capacity market, but that FERC did not provide adequate reasoning for allowing the rules to go into effect (21-3068).

The narrowed MOPR — which applies only to resources connected to the exercise of buyer-side market power or those receiving state subsidies conditioned on clearing the RTO’s capacity auction — automatically took effect Sept. 29, 2021, because FERC’s four members at the time were evenly divided. (See FERC Deadlock Allows Revised PJM MOPR.)

Such deadlocks are rare, but they had occurred before, including a tie vote over ISO-NE’s Forward Capacity Auction 8 in September 2014, the results of which were automatically accepted. The D.C. Circuit Court of Appeals refused to review the auction in 2016 because there was no order by the commission. (See FERC: FPA Change may not Solve Catch-22 on Vote Deadlocks.)

The America’s Water Infrastructure Act, signed into law by President Donald Trump in October 2018, added a provision to Section 205g of the Federal Power Act to allow for judicial review if FERC fails to act on the merits of a rehearing request within 30 days because the commissioners are divided 2-2. The challenge to the PJM MOPR marks the first time a court has been asked to address the standard of review in the new provision.

In its petition, P3 called the new MOPR a “radical reversal in policy” that “eviscerated more than a decade” of precedents by the commission regarding the rule.

The notice issued by the commission announcing a deadlock was not an order and contained “no findings of fact or conclusions of law authorizing PJM to implement market rule changes that reverse longstanding FERC precedent” and to “defy minimum requirements for controlling state-sponsored market power,” the organization argued.

“This policy reversal was not made through a FERC order, but rather announced by FERC’s secretary on the basis of a tie vote,” P3 said. “To the extent this court chooses to address the commissioners’ conflicting views on the merits of PJM’s proposal, it should find the MOPR revisions unjust, unreasonable and unduly discriminatory.”

P3 cited comments from Chairman Richard Glick, who dissented from a previous order under Chair Neil Chatterjee that expanded the MOPR, arguing that it would increase capacity prices and impede the development of renewable resources in the RTO. However, P3 cited, when PJM held its only capacity auction under the expanded MOPR in May 2021, capacity prices fell “dramatically” and “large amounts of new renewable resources displaced thermal resources.”

“Nevertheless, Chairman Glick repeatedly threatened PJM and other regional transmission organizations to propose their own modifications or FERC would ‘do it for them,’” P3 said.

The group also argued that independent power producers “cannot compete effectively against resources that employ state subsidies to submit uneconomic offers below their actual costs” and that the new rules “allow certain states to shift the cost of subsidized resources to consumers in other states through a market-wide clearing price.”

“PJM’s narrow MOPR discriminates against all unsubsidized power suppliers and cannot produce just and reasonable wholesale rates as required under the FPA,” P3 said. “It is beyond legitimate argument that subsidies disrupt competition, distort market prices and harm nonsubsidized resources.”

In its own petition, EPSA argued that FERC’s default acceptance of PJM’s MOPR proposal “does not represent reasoned decision-making by the agency” and should be set aside under the Administrative Procedure Act (APA).

EPSA said the APA’s arbitrary and capricious standard requires an agency to “articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’”

“The agency itself — as opposed to individual commissioners — has provided no explanation for its deemed action, and it is only FPA Section 205(g) that transforms FERC’s non-action into reviewable agency action in the first place,” EPSA said. “FERC has — through its inaction — allowed a rate structure to take effect that shares the exact feature that, in FERC’s own estimation, made the pre-2018 tariff unlawful: a MOPR that does not address state-subsidized resources. That abject failure to abide by the most basic requirements of reasonable administrative decision-making requires reversal.”

The group also argued that FERC’s action violated the FPA’s prohibition on “unduly discriminatory” rates and that the commission is not permitted to “approve a rate structure that would allow a single state to impose its own policy choice on neighboring states.”

“The focused MOPR improperly allows one state to project its policy choices regarding the generation mix beyond its borders, dictating the generation mix that applies to other states,” EPSA said.

State Challenges

In a joint petition, the Pennsylvania Public Utility Commission and Public Utilities Commission of Ohio argued that the commission’s inaction on the MOPR allowed PJM “to overturn a FERC-defined rate without any supportive reasoning or public decision-making whatsoever.”

The commissions said the narrowed MOPR will allow buyer-side market power to “infiltrate its capacity market with a low likelihood of screening.”

“FERC and the courts have emphasized that market power must be reviewed,” they said. “For its part, FERC has repeatedly approved buyer-side screens that review this sort of behavior without looking to intent. That review is not merely an option; it’s a critical feature of functioning competitive markets.”

They also argued that the changes “unjustly and unreasonably allow states to both subsidize resources and set a price contrary to the PJM capacity market auction price approved by FERC.”

“Regardless of when these policies were put in place, they have the effect of uncompetitively reducing prices through the market for the benefit of the buyer, and they therefore are an exercise of buyer-side market power,” the commissions said. “PJM and its supporters provide no coherent reason why old policies that exercise market power should be treated differently from new policies that do the same.”

ISO-NE Plans Working Group Reshuffle

ISO-NE is proposing a merger of two of its stakeholder working groups to align with rapidly changing energy technology.

The grid operator has put forward a plan to merge the Demand Resources Working Group (DRWG) and Variable Resource Working Group (VRWG), created to help inform the formal NEPOOL stakeholder process, into the Emerging Technologies Working Group.

According to ISO-NE spokesperson Matt Kakley, the goal is to provide a “single working group forum for any emerging technology,” including inverter-based resources, distributed energy resources or other new technologies that might enter the picture.

“Rather than starting and stopping different working groups for specific resources, having one standing group maintains a consistent structure for nascent resources as their needs arise and naturally phases out focus on resources that are more established in the marketplace,” Kakley wrote in an email to RTO Insider.

He pointed in particular to storage as a “rapidly proliferating resource” that needs a forum to discuss grid integration and market participation issues.

ISO-NE has been introducing the idea in recent NEPOOL meetings and put forward a draft charter for the new ETWG at this week’s Markets Committee meeting.

The group would report to each of the Markets, Reliability and Transmission committees and would have a chair appointed by ISO-NE and a vice chair selected by NEPOOL participants.

The charter would define emerging technologies as “any technology that may require distinct technical discussions to help facilitate their grid integration and market participation, such as inverter-based resources or distributed energy resources that are not materially immersed or integrated into the wholesale power markets or operating in the bulk power system.”

Talen Energy Subsidiary Files for Bankruptcy

Talen Energy on Monday filed for Chapter 11 bankruptcy protection for its Talen Energy Supply (TES) subsidiary, citing rising natural gas prices, greater hedging collateral requirements and lawsuits stemming from the unit’s Texas operations during Winter Storm Uri in 2021 (22-90054).

The company announced Tuesday that TES has secured $1.76 billion of debtor-in-possession financing from Citigroup, Goldman Sachs and RBC Capital Markets in a restructuring agreement consisting of a $1 billion term loan, a $300 million revolving credit facility and a $458 million letter of credit facility.

TES also executed a restructuring deal with a group of bondholders who will participate in an equity rights offering of up to $1.65 billion and an agreement to turn more than $1.4 billion of the unsecured notes into equity.

The secured creditors, who are owed nearly $2.9 billion, are expected to be fully paid under the proposed agreement, according to court documents.

“TES expects to continue its day-to-day business in the normal course and intends to move as quickly as possible through the process,” Ryan Leland Omohundro, managing director for Alvarez & Marsal, Talen’s restructuring advisor, said in a filing Tuesday. “TES has filed customary ‘first day’ motions with the court to ensure no interruption to employee wages, healthcare, and other benefits as well as the ability to conduct routine business with vendors and other business partners, including the resumption of hedging activities. TES’ plants will continue to generate needed electricity for the markets they serve.”

TES’s generation portfolio consists of 18 facilities located in PJM, ERCOT and ISO-NE, producing around 13,000 MW of power. Its largest operations include the 2,254-MW Susquehanna nuclear plant, the 1,711-MW Martins Creek natural gas plant and the 1,518-MW Montour and 1,422-MW Brunner Island coal plants, all in Pennsylvania.

The parent company, Talen Energy Corp., and its crypto mining operation are not part of the bankruptcy filing.

Talen, which is based in The Woodlands, Texas, listed assets and debts of more than $10 billion in the Chapter 11 filing at the U.S. Bankruptcy Court for the Southern District of Texas in Houston.

The filing said TES started the Chapter 11 proceeding because of “immediate and significant liquidity concerns that can be traced back to the sudden and sustained rise of natural gas prices in late 2021.” The company said the natural gas prices “sharply increased” collateral requirements for hedging activities and resulted in an “unexpected squeeze on available cash.”

TES remains subject to several lawsuits, court filings said, including litigation over allegations that Talen Texas facilities were unprepared to handle the extreme weather during Uri and were subject to “other operational failure.”

BPA Customers Support Effort to Weigh CAISO, SPP Market Options

SPP’s plan to develop an electricity market to compete with CAISO’s Western Energy Imbalance Market is getting another boost from the region’s industry players, this time from a key group of utilities and energy customers in the Pacific Northwest.

The support came in the form of an open letter issued May 5 by the Public Power Council (PPC), which represents 85 “preference” customers of the Bonneville Power Administration that account for 70% of the federal power marketing agency’s $3.9 billion in revenues. The group’s members include Seattle City Light, Tacoma Power, Eugene Water & Electric Board, Port of Seattle and Grant County (Wash.) PUD, among many others.

In the letter, PPC announced its members were throwing their weight behind an initiative by Western utilities that said last month that they will help develop SPP’s Markets+ platform as a way to evaluate the effort against CAISO’s proposed extended day-ahead market (EDAM) for the WEIM. (See Western Utilities to Support SPP Market Development.)

“The deployment of an integrated real-time and day-ahead market is a very significant undertaking,” the PPC said. “Any market alternative must be carefully considered to ensure all design objectives are properly met without undue adverse effects. The ability to evaluate two fully-formed day-ahead market options, where both the market design and market governance have been developed, will ensure that entities are able to make an informed decision on the option that provides the best step forward for their customers.”

The 15 original utilities, a handful of which are PPC members, said they would be “dedicating key staff” to participate in the Markets+ initiative over the next year and “working collaboratively with SPP and other stakeholders towards the design of a governance framework and conceptual market design proposal,” expected to be completed by the end of the year. 

PPC said it has already committed “significant staff resources” to CAISO’s EDAM effort and would continue to do so, while also contributing to the SPP effort. 

“PPC members are committing to having productive discussions with other stakeholders to develop the best possible market opportunities.  Sharing this commitment along with PPC members’ collective objectives is an initial step in that discussion,” Lauren Tenney Denison, PPC director of market policy and grid strategy, told RTO Insider in an email.

Among those objectives is a long-term solution that “maximizes” the group’s three priorities, according to the letter:

  • a reduction in future costs for preference customers “by reducing net power supply costs and providing just compensation for all relevant attributes of the federal system;”
  • a market that maximizes “efficient operation” of the federal transmission system and enables its expansion; and
  • ease of integration of carbon-free resources.

“At the same time, an acceptable market must operate within several parameters,” the PPC said. “First, it must maintain or enhance grid reliability. Second, it must preserve our statutory rights to cost-based federal service. And finally, it must have a strong and effective independent governance structure that does not unduly discriminate in favor of or against specific market participants.”

Asked to clarify how an organized market could aid in expanding the federal transmission network in the Northwest, Tenney Denison said: “The potential that a market could send additional price signals on where BPA could most effectively invest in transmission could be helpful to encourage that responsible expansion.  If larger conversations develop on a potential Regional Transmission Organization, this will create additional opportunity and potentially additional risk for the preference customers, given the comparatively low cost of BPA transmission today.”

Critical Role for BPA

The PPC’s letter also shed light on other specific issues compelling its members to explore market development, not least of which is the looming termination of their 20-year cost-based power contracts with BPA in 2028, which will soon be subject to renegotiation. Under federal law, the Northwest’s publicly owned utilities are entitled to electricity generated by the Federal Columbia River Power System (FCRPS), but they are not guaranteed specific rates for that electricity, which can vary based on how BPA meets its own revenue requirement. Higher sales of surplus power or transmission capacity can translate into lower rates for the agency’s preference customers.

“We remain committed to exploring organized market options that develop in the West to assess whether an option exists that appropriately values the attributes of the FCRPS and provides net benefits to BPA customers,” the group said.

The PPC encouraged other Western stakeholders — and “especially BPA” — to participate in the market exploration effort. Tenney Denison said BPA’s role as operator of the “backbone” of the Northwest grid means “the agency’s ability to facilitate an integrated market across the Northwest will be critical to that market’s success.”

BPA began trading in CAISO’s Western EIM just last week, the culmination of a nearly four-year stakeholder effort to reach a decision on membership and prepare the agency’s customers for market participation. (See BPA, Tucson Electric Power Enter Western EIM.)

Tenney Denison said that with BPA now participating in the EIM, PPC will “continue to work with the agency to understand the impacts that participation is having on the preference customers, including the cost and reliability of the services that they receive from BPA.  PPC worked with BPA to develop metrics which the agency will use to report on its participation in the EIM and we plan to continue to engage with agency staff in the coming months to better understand the agency’s performance in the EIM, as well as any lessons learned which may be applicable for a day-ahead market.”

PUC Selects Firm to Aid in ERCOT’s Market Redesign

The Texas Public Utility Commission said in a filing Tuesday that it has selected California firm Energy and Environmental Economics (E3) as its independent consultant to aid it in reviewing and analyzing new designs for ERCOT’s wholesale market.

According to the filing, E3 is expected to recommend implementation strategies and support the commission in developing business requirements for the strategies. It will work with the PUC’s Phase II market designs and structure changes that the commission says are “intended to ensure sufficient dispatchable generation resources … to meet the reliability needs of the ERCOT power region during a range of extreme weather conditions and net load variability scenarios” (53237).

The commission chose E3 over Potomac Economics, which also serves at ERCOT’s Independent Market Monitor. They were the only two firms to respond to the PUC’s request for proposals.

However, E3 is also behind one of the market structures under the commission’s consideration. Under a contract from NRG Energy and Exelon — both ERCOT market participants — the consulting firm laid out in a white paper a load-serving entity reliability obligation (LSERO) structure it said would directly address resource adequacy concerns by introducing a formal reliability standard and a mechanism to ensure sufficient resources meet this standard. (See Study Suggests Texas LSEs Can Provide Reliability.)

The contract includes a section on conflicts of interest that require E3 to certify to the PUC “that no existing or contemplated relationship exists between [the] contractor and another person or organization” that will constitute a conflict. The PUC defines that as a “situation in which the concerns or aims of the contractor are incompatible with the concerns or aims of the PUC acting in the public interest.”

Commission spokesman Rich Parsons pointed out the contract “clearly stipulates” E3 working conditions “under the strict oversight of PUC staff … to ensure it is conducted solely in the best interest of the [PUC] and the people of Texas.”

“E3 was selected through a competitive RFP bid process open to any qualified respondents and in full compliance with the state’s procurement laws and procedures,” he said in an email. “Through this competitive process, it was determined E3 presents the best value to Texans for this project.”

The firm is expected to follow mitigation strategies laid out by the commission and to make a “good-faith effort” to identify any ERCOT market participants and list them as potential conflicts, the contract says.

Even so, stakeholders are expressing concerns with the optics of hiring a consultant that has proposed one potential market structure to review it and others.

“It’s absurd on its face,” said Stoic Energy President Doug Lewin, who advocates for energy efficiency and demand response. “The proposal the consultant and [PUC Chair Peter Lake] favor is a non-transparent capacity market [that] … would cost customers billions of dollars, reduce competition and give an advantage to incumbent generators. I’m not sure why the [PUC] couldn’t find a truly independent evaluator of the proposals.”

Indeed, Lake has seemed to favor the LSERO in several commission meetings and workshops, with the other three commissions offering some pushback. However, the E3 proposal has been included among up to five specific proposals under the PUC’s market design “blueprint” that the commissioners agreed to in December. (See PUC Forges Ahead with ERCOT Market Redesign.)

“The proposals to be considered should place a requirement on LSEs to either purchase an energy credit, a type and quantity of energy resources, or prove its ability to meet the demand of the customers that it has contracted to serve,” the contract says.

E3 will analyze the proposals’ cost to the ERCOT market and the financial effect on consumers. The firm must review the various proposals; analyze and advise PUC staff on appropriate reliability standards and metrics to reach a certain level of dispatchable generation; provide estimated implementation and consumer-cost analysis associated with the blueprint’s market changes; provide potential dispatchable generation investment outcomes associated with the changes; and provide reliability impact analysis.

The contract is not to exceed $364,000. Hourly rates for the E3 team will vary from $725 (managing partner) to $250 (associate).

The PUC’s goal is to have a turnkey solution for its approval that can be fully operational and functioning in the ERCOT footprint within a year of regulatory adoption.

The commission references in the contract state legislation passed last year that requires it to establish a reliability standard that meets ERCOT’s needs; annually assess the quantity and characteristics of the reliability services needed to perform under extreme weather conditions; procure sufficient ancillary or reliability services during low non-dispatchable power production periods; develop qualifications and performance requirements for providing those services, including appropriate penalties for failure to provide the services; and sizes the services procured to prevent prolonged rotating outages from net load variability in high-demand and low-supply scenarios.