July 4, 2024

FERC Allows MISO Plan to Align Generator Replacement and Suspension Processes

With FERC’s blessing, MISO will synchronize its generator replacement process with its generation suspension and retirement process to give interconnection customers more flexibility when they decide to replace, retire or suspend a generating unit.  

MISO received a favorable decision on a tariff change from FERC on March 29 and now will allow owners hoping to replace their generation with the option to simultaneously request to be evaluated for retirement or suspension if their plans for a replacement facility don’t pan out (ER24-1055). 

MISO’s current generator replacement process requires an interconnection customer seeking to replace its generating facility with a new facility to submit a request for replacement at least a year before the existing facility halts commercial operations. MISO completes a replacement impact study on the new generation to figure out whether its addition will adversely impact the system and completes a reliability study to see if the system will suffer violations without the existing generation while the replacement generation is being built. If the project can proceed, MISO drafts a replacement generation interconnection agreement (GIA).  

However, that roughly yearlong process bumps up against MISO’s generation suspension and retirement requirements, which expect generation owners to make a request to retire or suspend more than a year before the generating unit idles.  

MISO said its generation owners often begin the process unsure of whether a replacement, suspension or retirement is the best decision for their generation and have only the results of MISO’s reliability and impact studies for replacement once the notification deadline to retire or suspend the unit has passed. That leaves owners who find that their replacement plan is not viable in a bind, MISO said, and beholden to a process “entirely driven by procedural timing requirements rather than engineering or economic considerations.”  

Now generation owners will be able to request a suspension/retirement equivalency study alongside their option for MISO to perform generation replacement studies. If owners elect the equivalency study at the time of their replacement request, MISO will waive the yearlong lead time for suspensions and retirement requests and require only 30 days’ notice to begin suspension/retirement studies. 

MISO said the rule change will allow generation owners whose replacement plans fall through and have elected the equivalency study to seamlessly transfer units to suspension status, “which will allow the interconnection customer to make the proper plans for the future of its unit.”  

FERC said the change should allow MISO to process suspension, retirement and replacement requests more efficiently and give interconnection customers better data to make informed business decisions.  

“We find that MISO’s proposal will integrate and harmonize its retirement and suspension processes with its generator replacement process by aligning the timeline for an interconnection customer with an existing generating facility to be considered for a suspension and/or retirement request with a replacement generating facility request,” the commission wrote.   

FERC said the revisions will allow owners more freedom to pursue suspension and retirement decisions if their replacement facility requests are denied by MISO and lessen the risk that they miss deadlines to cease operations.  

MISO also said it will apply its new process to partial replacement of generation facilities, where some interconnection rights are left over after a replacement facility is planned. In those cases, interconnection customers can make additional replacement generating facility requests for the remaining capacity of an existing generating facility up until the first GIAs are struck for some of the interconnection rights.  

The Mississippi and Arkansas public service commissions, Entergy and WEC Utilities protested the filing, arguing that MISO’s plan would deprive generator owners of their residual interconnection capability by prohibiting additional interconnection requests of already-paid-for interconnection rights after the first GIA is signed.  

FERC brushed those concerns aside, saying interconnection customers still have the opportunity to replace an existing generating facility up to the same level of interconnection service.  

Retirements and New Faces on PJM Executive Team

PJM Vice President of Planning Ken Seiler completed a nearly 23-year career with the RTO on March 29 before retiring and handing leadership of the Planning Division to Paul McGlynn, previously the executive director of system operations. 

Seiler was joined by colleagues at PJM and across its membership for a going-away celebration following the March 20 Members Committee meeting, where McGlynn said he has benefited from the work Seiler has put into transforming the RTO’s interconnection process to run more smoothly and generally putting the planning division in a strong position. (See PJM Initiates Transitional Interconnection Queue.) 

PJM Executive Vice President of Market Services and Strategy Stu Bresler also praised Seiler’s leadership. 

“You’re leaving this organization better than you found it — you made it a better place,” Bresler said. 

Seiler will continue to be the RTO representative on the ReliabilityFirst Board of Directors through 2024. He also served on the board of PJM Environmental Information Services (EIS) through Jan. 1, when Vice President of Market Design and Economics Adam Keech assumed his position.  

Paul McGlynn, PJM | © RTO Insider LLC

Prior to heading the Planning Division, Seiler worked in the information technology and operations departments at PJM and was integral in the development of its backup control center. 

McGlynn was named Seiler’s successor in November, shifting him over from the Operations Division, where he oversaw real-time dispatch operations, near-term reliability studies, load forecasting, and the coordination of generation and transmission outages. (See PJM Restructuring Executive Team.)

This won’t be McGlynn’s first time in the Planning Division. Before his time heading operations, he was the RTO’s senior director of system planning, a role involving administering the development of the Regional Transmission Expansion Plan (RTEP).

McGlynn earned his bachelor’s degree in electrical engineering from Pennsylvania State University and a master’s in electrical engineering from Drexel University. Prior to his time at PJM, he worked for Exelon in its engineering and operations departments. 

Aftab Khan Fills New VP Position

PJM has filled its newly created position of executive vice president of operations, planning and security with the appointment of Aftab Khan, former senior vice president of engineering at Eversource Energy. He began in March after his hiring in February. 

“I am eager to help PJM take on the many challenges presented by the energy transition. PJM’s creation of this new role shows the company’s commitment to seeking comprehensive solutions that emphasize reliability and security as the system evolves,” Khan said in a February announcement of his appointment. 

Khan’s role was created in November to “have overall responsibility for grid operations, transmission planning, cybersecurity and physical security, and business continuity.”  

Khan holds a bachelor’s degree in electrical engineering from the University of Alaska, an MBA in operations and finance from Carnegie Mellon University and a master’s degree in electric power engineering from Rensselaer Polytechnic Institute, the announcement says. 

He spent 24 years working at ABB, including as president of the Power Systems Division, Saudi Arabia; senior vice president of power transformers, North America; and senior vice president of grid systems, North America. 

“We welcome the experience, expertise and leadership Aftab brings to this important new role, which was created to support grid reliability during this increasingly complex energy transition,” PJM CEO Manu Asthana said in the announcement of Khan’s appointment. 

EPA Issues Final Standards on Heavy-duty Truck Emissions

The final standards for greenhouse gas emissions from heavy-duty trucks, issued by EPA on March 29, attempt to strike a balance between environmental concerns about diesel fumes the trucks spew into the air and the economic and physical logistics of building out a zero-emission fleet and charging network.  

Aimed at cutting 1 billion tons of GHG emissions per year — and saving $3.5 billion for truckers — the rules provide a longer runway for manufacturers to meet emission-reduction targets that are initially less stringent than the proposed standards EPA issued in April 2023. This slower phase-in is offset by tougher goals in 2031 and 2032, in many cases stricter than initially proposed.  

The standards for three of the heaviest heavy-duty vehicles will go into effect on a staggered schedule. For day-cab “tractors” ― that is, semis without a sleeping compartment ― compliance will begin in 2028. The start date for heavy “vocational” vehicles ― a category covering a range of construction, maintenance and other work vehicles ― is in 2029; for tractors with sleeping compartments, it is in 2030. 

“In consideration of the opposing concerns raised by commenters, EPA believes it is critical to balance the public health and welfare need for GHG emissions reductions over the long term with the time needed for product development and manufacturing as well as infrastructure development in the near term,” the rule says. 

These changes notwithstanding, EPA Administrator Michael Regan hailed the final rules as “the strongest greenhouse gas standards for heavy-duty vehicles in history.” 

Speaking at a prerelease press call, Regan framed the standards as tackling heavy-duty trucking’s impacts on both climate change and public health. Transportation accounts for 29% of all U.S. emissions — more than any other sector — and heavy-duty trucks make up about a quarter of that total, according to EPA. 

“An estimated 72 million Americans, often people of color or people with lower incomes, live near freight truck routes,” Regan said. “These communities are disproportionately exposed to the pollution from heavy-duty vehicles, resulting in higher rates of respiratory and cardiovascular illnesses and even premature death.” 

Both Regan and National Climate Adviser Ali Zaidi also promoted the rules as another piece of the Biden administration’s work on decarbonizing transportation and the economy, while boosting investment in the automotive industry and creating jobs. The new rules are part of EPA’s Clean Trucks Plan, which includes rules, released in 2023, limiting nitrogen oxide emissions from heavy-duty trucks, Regan said. 

Zaidi pointed to the tax credits supporting clean trucks in the Inflation Reduction Act: $40,000 for zero-emission trucks and up to $100,000 for charging and refueling stations. He also cited the recent launch of the administration’s National Zero-Emission Freight Corridor Strategy, which first will develop charging hubs and then corridors to accelerate the buildout of a zero-emission freight network nationwide. (See Feds Announce National Strategy for Zero-Emission Freight.) 

EPA is estimating that operational savings for heavy-duty zero-emission vehicle (ZEVs) ― their total cost of ownership ― will offset their higher upfront costs, which are potentially more than twice the cost of a comparable diesel truck with an internal combustion engine (ICE). 

With EPA’s estimated $3.5 billion in savings for operators, payback on heavy-duty electric vehicles could happen within two to five years, depending on the type of truck. By 2032, when the standards are fully phased in, individual owners and drivers could be saving between $3,700 and $10,500 annually on fuel and maintenance, depending on vehicle type. 

EPA has also committed to ongoing consultation with stakeholders as the standards are implemented, “to learn from their experiences and gather relevant information and data,” according to the announcement. Based on stakeholder input, EPA may issue periodic reports or guidelines or consider modifications to the standards to be made through a future rule. 

“What we are excited about is the ability to collect specific data from various entities, whether that be community groups, environmental groups or the industry … to help accentuate and possibly give us new data and information we may not have considered,” Regan said. 

What’s in the Mix?

Decoding the 1,155 pages of the EPA’s final rule is more than a little complicated. While the industry classifies trucks by weight, EPA has broken down heavy-duty trucks into more detailed categories and subcategories ― vocational and tractor; low and high roof; light, medium and heavy heavy-duty. 

The emission standards themselves are expressed in grams per ton-mile, agency jargon that does not easily translate into pounds of tailpipe carbon dioxide emissions. 

Getting a handle on the scope of the challenge ahead requires some digging. Trucking industry sources count about 13 million registered trucks on roads nationwide, 2.9 million of which are semis. As of June 2023, only about 17,500 were ZEVs, and the vast majority ― 14,000 ― were medium-duty cargo vans, the nonprofit CALSTART reported. 

The Department of Energy’s Alternative Fueling Station Locator shows the U.S. with a total of 15 DC fast-charging stations, with a total of 26 charging ports, available for the largest types of HD trucks, and most of those stations are privately owned.  

EPA’s last GHG standards for HD trucks were set in 2016. When fully phased-in, the new rules could slash emissions by 25 to 60% below the 2016 standards depending on vehicle type, according to an EPA fact sheet. 

Despite Republican complaints that EPA is trying to force Americans into EVs, the new standards do not require truck manufacturers to make — or truck drivers to buy — ZEVs. Regan has stressed that the new rules are performance-based and “technology-neutral, allowing each manufacturer to choose what set of emission-control technologies works best for them, whether that’s advanced internal combustion engines, hybrid vehicles, plug-in hybrid electric vehicles, battery electric trucks [or] hydrogen fuel cell vehicles.” 

The rules offer two scenarios of how different mixes of vehicles might be used to meet the standards and how percentages of ZEVs versus diesel trucks might change through 2032. Generally, the heavier the truck, the lower the percentage of ZEVs being predicted. 

In a scenario with only ZEVs and ICEs, light vocationals start with a mix of 17% ZEVs and 83% ICEs in 2027 but reach 60% and 40%, respectively, by 2032. A second scenario replaces ZEVs with a mix of hybrids, plug-in hybrids, and natural gas and hydrogen-powered ICEs. In this case, ICEs go from 33% in 2027 to just 1% in 2032, while hybrids go from 52% in 2027 to 40% in 2032, and hydrogen ICEs from zero to 24%. 

For long-haul trucks, the rule predicts 25% ZEVs versus 75% ICEs in 2032. In the non-ZEV scenario, ICEs account for 64% of the fleet by 2032, with hybrids at 10%, natural gas at 5% and hydrogen ICEs at 17%. 

However, the potential impact of the EPA standards is only one factor in a broader landscape of policy and market forces that could drive accelerated adoption of heavy-duty ZEVs over the next decade and beyond. 

California’s Advanced Clean Trucks (ACT) rule, now adopted by 11 other states, provides a different approach, requiring manufacturers to increase their percentages of ZEVs offered for sale in the state each year through 2035, in some cases to higher levels than those projected by EPA. 

By 2032, ACT calls for 40% ZEVs for lighter medium-duty vehicles, such as cargo and passenger vans weighing between 8,501 pounds and 14,000 pounds, rising to 55% by 2035. The goals for other medium- and heavy-duty vehicles are 60% ZEVs in 2032, ramping up to 75% in 2035, while long-haul ZEVs hit a 40% plateau for 2032 and beyond. 

Similarly, EPA projections for ZEV adoption generally lag behind the sales targets set by major truckmakers in the U.S. Daimler Truck North America has committed to a carbon-neutral fleet by 2039; Navistar has said it will reach 50% ZEV sales by 2030 and 100% by 2040; and Volvo Group North America is also going for 50% ZEV sales by 2030. 

The three companies together represent 70% of all medium- and heavy-duty trucks sold in the U.S., according to a Daimler press release. 

In January, the companies announced the formation of a new coalition called Powering America’s Commercial Transportation (PACT). The group says it will not advocate for specific technologies or policies; it instead intends to focus on educating industry stakeholders about the bottlenecks to expanding charging networks for ZEVs and looking for new solutions. 

Daimler is also a founding member of another industry initiative called Greenlane, which is building out a charging network for commercial trucking along Interstate 15 between Los Angeles and Las Vegas. Daimler is partnering with NextEra Energy Resources and BlackRock on the 280-mile corridor, which will eventually have 100 fast chargers and stations with “modern amenities designed to increase the comfort of drivers [and] resilience for high uptime and ultimately moving freight more efficiently,” according to the announcement. 

Reactions

Reactions to the new standards were mixed. 

Environmental and cleantech groups were mostly positive, though they lamented what they saw as EPA’s compromises with the trucking industry. 

“Our communities have for years been concerned about the health impacts of the thousands upon thousands upon thousands … of trucks that travel our [streets] daily,” said the Rev. Lennox Yearwood Jr., president and CEO of the Hip Hop Caucus, an environmental, economic and racial justice nonprofit. “Although we would have liked to see a more stringent program that leads to zero emissions from freight, this is a meaningful step toward achieving cleaner air for our communities.” 

“These rules could have done more,” agreed Guillermo Ortiz, clean vehicles advocate at the Natural Resources Defense Council. “Our nation needs a vision to eliminate pollution from the freight transportation system. Every wheeze, every gasp for breath in communities impacted by the movement of freight serves as a reminder of the urgency to act.” 

Ryan Gallentine, managing director at Advanced Energy United, said the new rules will provide certainty for a range of industry players — truckmakers and private and public fleet operators — to move ahead with vehicle and fleet electrification and managed charging. 

“Electric trucks and buses provide a whole new business opportunity for fleet operators, who can take advantage of charge-management technology to maximize electricity savings for their vehicles and facilities,” Gallentine said. “That makes the switch to electric vehicles a force multiplier for communities, who will not only benefit from improved air but also a more energy efficient business environment.” 

Ben Prochazka, executive director of the Electrification Coalition, made a national security argument for the rules as an “important step towards ending our nation’s dependence on oil for transportation. … Heavy-duty electrification strengthens national security by reducing our dependence on global oil markets controlled by bad actors who do not share our democratic values and protects public health, particularly in underserved communities.” 

On the industry side, the American Trucking Associations began lobbying against the rules as soon as EPA released its proposed version last April, arguing the agency should not change its existing standards. 

EPA’s “post-2030 targets remain entirely unachievable given the current state of zero-emission technology, the lack of charging infrastructure and restrictions on the power grid,” CEO Chris Spear said. “Any regulation that fails to account for the operational realities of trucking will set the industry and America’s supply chain up for failure.” 

Truckmakers acknowledged EPA’s efforts to address their concerns but also stressed the need for a quick buildout of a charging network and ongoing federal support. 

Volvo said the company “is completely aligned with EPA’s objective of speeding the transition to zero-emission vehicles. It’s important to note that this regulation represents the first time that compliance is beyond our control as a manufacturer. Customers won’t buy ZEVs unless they’re confident they have access to charging, which neither [truckmakers] nor EPA can guarantee.” 

Cynthia Williams, global director of sustainability at Ford Motor Co., said, “The EPA’s new heavy-duty emissions rule is challenging, but Ford is working aggressively to meet the moment. … We also need policymakers to pair emission standards with incentives and public investment so that we can continue to deliver on the next generation of vehicles and for our nation to lead the future of this industry.” 

Appeals Court Upholds FERC on Gas Project Extensions

FERC on March 29 came out on top of litigation over its granting previously approved natural gas projects’ requests for an extension of their deadlines to bring the facilities online (22-1233). 

The Sierra Club challenged two such orders before a three-judge panel of the D.C. Circuit Court of Appeals: National Fuel Gas Supply’s Northern Access Pipeline in Pennsylvania, and New York and Cheniere’s plan to expand its Corpus Christi Liquefaction LNG facility in Texas. Public Citizen joined Sierra in opposing the extension for the LNG facility. 

The New York State Department of Environmental Conservation denied National Fuel’s request for a permit, which set off years of litigation in federal court and caused it to seek two extensions from FERC. The firm won the case and filed its second request with the commission in 2022, which was granted. 

Cheniere’s LNG facility ran into delays because of the economic impacts of the COVID-19 pandemic and filed with FERC to extend its in-service date from later this year to 2027. FERC granted that, agreeing that the firm could not foresee the pandemic’s impacts on the global economy when its initial plans were made. 

FERC has broad discretion to grant the extensions, which is only limited by the “arbitrary and capricious” standard of the Administrative Procedure Act. It does not have to come to the best decision in such cases, with the court’s review limited to whether the commission examined the relevant considerations and articulated a satisfactory explanation for its action that includes a rational connection between the facts and its ruling. 

“In considering the requests for extensions, FERC found that the project sponsors had demonstrated diligence in the continued pursuit of their projects,” the court said. 

The litigation with New York and the pandemic’s impact on supply chains and the economy gave good cause for the extensions, the court said. FERC’s reasoning in both cases was consistent with its earlier decisions granting extensions. 

“FERC has found a wide range of circumstances to support good cause, including legal or litigation-related barriers, as well as impacts from the COVID-19 pandemic,” the court said. 

Sierra Club and Public Citizen argued that FERC’s inquiry was too lax, saying the agency rubber-stamps requests for extensions. 

“Although it is true that FERC has denied very few extension requests, that is not surprising,” the court said. “Project sponsors invest significant time and resources to secure approval of their pipelines and related facilities, and they generally have economic incentives to promptly complete construction.” 

Project sponsors can meet the good-cause standard by demonstrating their diligence and citing factors beyond their control that have slowed their progress, the court said. Developers who would abandon a project likely would never ask for an extension. 

Sierra Club also argued that FERC should have to re-evaluate the findings underlying its original certificate order any time it considers an extension request, but the court disagreed. FERC has broad authority to take whatever actions it finds necessary to amend a certificate. 

While the commission has to account for substantial or significant changes that impact a project’s approval under the National Environmental Policy Act, it is entitled to substantial deference because that call necessarily relies on FERC’s technical expertise, the court said. 

New York passed its Climate Leadership and Community Protection Act while the Northern Access project was being developed; Sierra Club argued that constituted a major change. But FERC found that the law did not impact demand for the pipeline’s gas, which is largely going to serve customers in Canada, where that law has no impact. The court again sided with the commission. 

FERC Accepts, Sets Hearing on ND Co-op’s Tariff Rates

FERC on March 26 accepted SPP’s proposed tariff revisions modifying Central Power Electric Cooperative’s formula rate template but suspended them for a nominal period subject to refund and established hearing and settlement procedures (ER24-254). 

The commission found the proposed revisions raised issues of material fact that are more appropriately addressed in an administrative hearing. FERC encouraged the proceeding’s parties to reach a settlement before the hearing begins. 

The tariff revisions are suspended for a nominal period, effective Jan. 1, subject to refund. 

SPP filed Central Power’s requested formula rate template with FERC last year. The cooperative asked for a base return on equity of 10.29% and a 50-basis-point adder for its SPP membership. It said incorporating the adder for its initial and continuing RTO membership, previously approved by the commission, resulted in a total ROE of 10.79%. 

The commission said the adder continues to be appropriate given Central Power’s continued SPP membership. However, it found that the ROE, inclusive of the adder, must remain within the zone of reasonableness as determined by hearing and settlement judge proceedings. 

FERC rejected protests by the Western Area Power Administration and Missouri River Energy Services that Central Power should revise the template and the formula rate protocols governing the template’s updates and how the resulting rates will be implemented each year. It said the utilities did not demonstrate how the cooperative’s unchanged template and protocols are “integral to the revisions proposed by Central Power.” 

“We also find that nothing in the interaction between Central Power’s proposed revisions” and the template’s and protocols’ elements “discussed by Missouri River and [WAPA] create an unjust and unreasonable result,” the commission wrote. 

Central Power, headquartered in North Dakota, is a wholesale generation and transmission cooperative interconnected with SPP members WAPA, Basin Electric Power Cooperative and several other utilities. 

While Central Power, a borrower from the Rural Utilities Service, is not a “public utility” under the Federal Power Act, FERC cited precedent and a federal appeals court ruling to find it appropriate to apply the act’s just-and-reasonable standard to the cooperative’s proposed formula rate revisions, which are a component of SPP’s jurisdictional rates. 

MISO Sets Sights on 2025 Completion for New Market Platform

MISO reported it’s making steady progress on installing a new market platform by the end of next year and will debut a new day-ahead market clearing engine this spring.  

The RTO said it likely will begin using its new, day-ahead market clearing engine exclusively sometime in May. 

At a March 27 customer readiness symposium meant to prepare members for MISO’s technological advances, MISO’s Arijit Bhowmik said the RTO is nearing the completion of parallel operations of the day-ahead clearing engine. MISO has said once it has its new clearing engine up and running smoothly, it can retire the legacy clearing engine from parallel operations. 

The grid operator was forced to push back the launch of the day-ahead market clearing engine to early 2024 instead of late 2023 due to delays. (See “Market Platform Replacement to Spill over into 2025,” MISO Board Week Briefs: Dec. 6-8, 2022.)  

MISO is slated to finish its market platform replacement completely by the end of 2025. It previously had ambitions to wrap up the project by the end of 2024, though it frequently cautioned the timeline could run longer. The RTO began the process of swapping out its outdated market platform for a new, modular platform in 2017. 

In late 2025, MISO will replace its real-time market clearing engine, which the grid operator uses every five minutes to send dispatch instructions. It also will go live in early 2025 with a new look-ahead commitment tool for generators.  

MISO completed factory acceptance testing and took delivery of its new real-time engine in 2023.  

Bhowmik said he hopes the introduction of the more nimble, modular platform can allow MISO to scale back the support hours it spends with members on the vintage platform.  

MISO has said it expects to spend $152 million on the market platform replacement, including about $14 million this year. It estimated program benefits remain steady at about $430 million. The grid operator began the market platform project with a $130 million budget and a $30 million contingency.  

Last year, MISO Director Theresa Wise said though the project now is “at the edge of” MISO’s budget plus contingencies, MISO expects the new platform to save at least a few hundred million dollars. 

New England States’ OSW Procurement Receives 5,454 MW in Bids

The coordinated offshore wind procurements of Connecticut, Massachusetts and Rhode Island received 5,454 MW in bids from four developers, falling short of the 6,000-MW solicitation cap.  

The window for bids closed March 27 in the first-of-its-kind coordinated procurement. The states are hoping that joint solicitations will reduce costs by enabling larger-scale projects and better utilizing regional supply chains. Projects could be submitted both as single-state and multistate offers to two or three of the states. 

The procurement comes on the heels of a turbulent period for offshore wind in New England. Avangrid Renewables and SouthCoast Wind both backed out of power purchase agreements with Massachusetts in 2023, while Rhode Island Energy canceled the PPA for a joint Eversource- Ørsted project, citing cost concerns. 

The bids included multiple recently canceled projects from Avangrid Renewables and SouthCoast, along with new proposals. Avangrid, Ørsted, SouthCoast and Vineyard Offshore all submitted bids for the procurement. 

Avangrid

The largest proposal came from Avangrid, which offered an approximately 1,870-MW combined bid of two projects, including its canceled Commonwealth Wind project. The projects, dubbed New England Wind 1 and New England Wind 2, would connect to the grid in Barnstable, Mass. 

Avangrid touted the 791-MW New England Wind 1 as a “shovel-ready project” that could reach commercial operations by 2029. It was offered as both a standalone project and a combined proposal with New England Wind 2. 

“With nearly all local, state and federal permits in hand, all interconnection rights secured and a project labor agreement signed with a skilled, local, union workforce, Avangrid is ready to go,” CEO Pedro Azagra Blazquez said. 

The 1,080-MW New England Wind 2 project, essentially a rebranding of the canceled Commonwealth project, was only offered as part of the combined proposal “to capture important economics of scale and support significant grid upgrades,” the company wrote. 

The company also announced memorandums of understanding for power purchases with the city of Boston and the Massachusetts Municipal Wholesale Electric Co. Boston’s MOU will enable it to purchase up to 15 MW of power from New England Wind. 

“This partnership advances our climate goals while bringing thousands of green jobs to our region, creating a pathway for generations to come,” said Mayor Michelle Wu. 

Vineyard

Vineyard — funded by Copenhagen Infrastructure Partners, Avangrid’s partner on the Vineyard Wind 1 project — proposed a 1,200-MW project dubbed Vineyard Wind 2 to all three states. The project would be south of Nantucket, reaching the shore in New London, Conn., and connecting to the grid in Montville.   

“By making effective use of ports, facilities and interconnection points throughout the region, Vineyard Wind 2 offers the most economic project configuration possible while delivering economic benefits for all three states,” said CEO Alicia Barton.  

The company also highlighted a recently signed tribal benefit agreement with the Mashpee Wampanoag Tribe for the proposal. According to the bid, the agreement would create a fund to “support education, environmental and natural resources, cultural resources and historic preservation efforts by the tribe.” 

SouthCoast

Following the cancellation of its PPA in 2023, SouthCoast resubmitted a 1,200-MW proposal to the states for the coordinated solicitation. The company said it could begin construction in 2025 and reach commercial operations by 2030. 

“The punishing inflation of 2020-2023 profoundly impacted infrastructure costs, upending the economics of projects that had fixed revenues but still needed to fix their costs,” the company wrote. “The clear lesson is that a quick turn from award to construction is critical to de-risk a macroeconomic environment that no one can control.” 

The project has “crucial manufacturing slots and supply chain reservations secured and [a] federal permit Record of Decision expected this year,” the bid noted. 

Ørsted

Ørsted submitted standalone and multistate bids in Rhode Island and Connecticut for its 1,184-MW Starboard Wind project. 

Ørsted and Eversource are constructing Revolution Wind, a 704-MW project that will provide power to Rhode Island and Connecticut. Ørsted and Eversource’s bid for Revolution Wind 2, a proposed 884-MW project, was rejected by Rhode Island Energy in 2023. 

“While the project name Starboard Wind is new, our work on the project itself is not,” Ørsted wrote. “We’ve been developing the offshore project site for nearly a decade, giving us extensive site data and a deep understanding of how to construct our proposed offshore wind farm successfully.” 

The three states now have until Aug. 7 to evaluate and make decisions on the bids.  

“The Healey-Driscoll Administration will review bids over the coming months and coordinate with Connecticut and Rhode Island to evaluate multistate projects that would increase benefits for the region,” said Elizabeth Mahony, commissioner of the Massachusetts Department of Energy Resources. “Massachusetts is committed to growing its offshore wind industry, which will spur our clean energy transition and provide renewable, affordable power to our homes and businesses.” 

NEPOOL TC Approves Process for States’ Transmission Needs

The NEPOOL Transmission Committee voted on March 27 to create a planning process for long-term transmission needs identified by states to meet their clean energy goals.

The new process — Extended-term/Longer-term Transmission Planning Phase 2 — was developed by ISO-NE and the New England States Committee on Electricity (NESCOE) in response to concerns from the states about transmission needs that extend beyond the typical planning horizon.

The proposal builds on the first phase of the transmission planning project — which created a process to study long-term transmission needs and was approved by FERC in 2022 — by creating a process for states to act on needs identified in those studies. 

“This effort, Phase 2, establishes the rules that enable the states to achieve their policies through the development of transmission to address anticipated system concerns and the associated cost allocation method,” said Brent Oberlin, ISO-NE director of transmission planning. 

In the new process, states can direct ISO-NE to issue a request for proposals for projects addressing long-term transmission needs. After soliciting bids from transmission developers, the RTO will quantify projected costs and benefits for each bid, with the benefits required to outweigh the costs to be eligible to be selected. ISO-NE will then select a preferred solution, with NESCOE then given the option to proceed or cancel the project. 

By default, the costs associated with these projects will be regionalized, although NESCOE can also submit an alternative cost allocation method for any project.  

The TC approved a supplemental process for when no projects pass the cost-benefit threshold. The costs commensurate with the benefits would be regionalized, while individual states can voluntarily cover any remaining costs in order to proceed with a project. 

The committee also approved an amendment to the proposal introduced by Avangrid that directs ISO-NE to conduct an independent cost assessment of bids submitted by transmission developers. 

Alan Trotta of Avangrid said different bidders may have different methodologies for calculating their project costs and that “a consistent cost estimating methodology by one entity will put bids on a level playing field.” 

Ensuring an independent assessment, either by ISO-NE or a third party commissioned by the RTO, would prevent aggressive cost estimations or differences in project scope from unfairly influencing the results of the project selection process, Trotta said. 

ISO-NE indicated that it will incorporate this amendment into the proposal it brings to a vote at the NEPOOL Participants Committee in April.

FERC Waives Nearly $2M in CAISO Data Reporting Penalties

FERC on March 27 granted complaints by five utilities against CAISO, nullifying nearly $2 million in penalties for incorrect meter data reporting. 

Idaho Power (EL23-94), Tucson Electric Power (TEP) (EL24-15), Direct Energy Business (EL24-11), Tacoma Power (EL23-103) and the city of Corona, Calif. (EL23-99), all submitted complaints last year challenging the application of CAISO tariff section 37, which spells out the ISO’s rules of conduct. 

Under the section, if a scheduling coordinator fails to submit meter data 52 days after the trading date, the submission is considered late. Failure to submit revised meter data 214 days after the trading day for the resettlement statement that CAISO issues is considered an inaccurate submission. Either violation subjects a scheduling coordinator to a $1,000 penalty for each trading day after deadlines are missed. 

Each of the complainants told FERC that CAISO was applying the provision too strictly for “minor, inadvertent” errors and that the errors had practically no effect on the markets, making the penalties unjust and unreasonable. 

The commission agreed “that the penalties assessed are not commensurate with any potential damage caused by the inadvertent errors, which were properly reported upon discovery, promptly fixed and had a de minimis effect” on the markets. 

The ISO also supported all the complaints, saying that until the rule is changed, it “supports relief for parties that receive excessive penalties under the existing tariff rules.” In May 2023, it opened the Rules of Conduct Enhancements stakeholder initiative to address issues including the potential for excessive penalties in certain circumstances. 

Several of the complaints noted that the tariff provision does not allow CAISO discretion in waiving or reducing penalties. 

Idaho Power had appealed $639,000 in penalties for incorrect data associated with the Arrowrock Hydroelectric Project. In July 2022, the utility discovered that transmission line losses were being double counted in the meter data being provided to CAISO, leading to under-reporting of energy produced by Arrowrock. Idaho Power argued that because the quantity did not affect LMPs or market runs in the Western Energy Imbalance Market (WEIM), the penalties should be waived. 

Tacoma’s reporting errors stemmed from setting its transmission system loss factor of 1.87%, which resulted in it under-reporting load by an hourly average of the same amount. It said the error occurred because of a misunderstanding in the treatment of line losses that occurred when it joined the WEIM. Upon noticing the error, it immediately reported it to CAISO and corrected it the next day. 

Both Corona and Direct Energy challenged their respective $342,000 and $825,000 penalties for errors resulting from Southern California Edison changing its billing system, saying it acted in good faith by notifying CAISO of the error upon discovery.  

Like Tacoma, TEP appealed penalties related to an inadvertent miscalculation during its integration into the WEIM. However, the utility did not submit settlement statements with its complaint; rather, it submitted nine CAISO notices of review, issued over the course of 2023, for periods of trading days in 2022.  

FERC agreed to only waive the penalties — $191,000 — described in the last notice, issued Oct. 31, 2023; TEP filed its complaint in November. The other eight “do not provide sufficient information for us to determine whether the instant complaint was filed with the commission within 22 business days from the date of issuance of any of the corresponding settlement statements,” as required by the tariff, the commission said. It set the other penalties for paper hearing, ordering TEP to file evidence that it submitted its complaint in a timely manner.