Search
`
July 3, 2024

ACP: Clean Energy Construction Increases in 1st Quarter

Nearly 5.6 GW of new solar, wind and storage capacity was added in the U.S. in the first quarter of 2024, the American Clean Power Association reported. 

The clean energy trade group said May 7 that capacity additions in the first quarter of 2024 were 28% higher than in the same period in 2023, putting utility-scale solar power installations over the 100-GW mark for the first time. It took 18 years to reach 50 GW of installed utility-scale solar but only four years to jump from 50 to 100, noted John Hensley, ACP’s vice president of markets and policy analysis. 

“Given current trends and expectations, [we expect] that the next doubling will come in a relatively short time,” he said at a news conference. 

At the close of the first quarter, installed clean power capacity stood at 269.88 GW nationwide, ACP said. The pipeline of projects under construction or in advanced development nationwide reached 174 GW, up 2% from the fourth quarter of 2023 and 23% from the first quarter of 2023. 

Offtake mechanisms for clean energy projects under development | ACP

“So 2023 was already a great year, but we’re already off to an even better year here in 2024,” Hensley said. “Just to give you some sense, those 5.6 GW of projects that came online this year are about enough to power a million American homes.” 

The projects ACP considers “in the pipeline” are either under construction or far along in the preconstruction process, he said. There are supply chain challenges, trade and tariff issues, and crowded interconnection queues, but “I will say that for the first time in quite a while, as we’ve looked at project delays, we’re starting to see that number slow pretty significantly,” Hensley said. “I mean, we were generally adding 10 [GW to] 15 GW of delays a quarter. We had 7 GW of delays in Q1 2024.” 

As of the first quarter, ACP counts 151 GW of onshore wind, 101 GW of solar and 18 GW of storage operational nationwide. 

In response to a reporter’s question, Hensley said the political situation in the U.S. introduces some uncertainty, but the industry is in a sound position: Customer demand for clean energy is increasing, technology costs are easing, and the economic benefits are spread across red and blue states. 

“It may be kind of strange to concede that 80-plus percent of our projects are actually taking place in more conservative parts of the country,” Hensley added. 

So much of what is being built is solar, which has a lower capacity factor than wind or fossil fuel-burning generation and needs more of a backstop. Wind was first to market, about a decade ahead of large-scale solar, Hensley noted, and there has been some balancing of wind-dominant generation portfolios. ACP expects to see developer interest in wind start to rebound in 2025 and beyond. 

First-quarter additions and cumulative growth of U.S. clean energy capacity | ACP

“And again, let’s not forget about storage, we built close to 8 GW last year, another 8 to 10 this year,” Hensley added. “It’s starting to proliferate, and in more markets than just California and Texas. … We’re not quite there yet on that balanced mix, but I think that’s the direction that we see things go.” 

By the Numbers

Datapoints from the report include: 

    • 4,557 MW of utility-scale solar came online in the first quarter of 2024; onshore wind and storage totaled about 450 MW each. 
    • 132 MW came online from South Fork Wind, the first major infusion of offshore wind in the nation. 
    • NextEra Energy was the leading clean-power developer in the first quarter; its 1,829 MW of solar, 449 MW of onshore wind and 50 MW of battery storage made up 41% of the national total. 
    • The nationwide development pipeline reached 94,462 MW of utility-scale solar in the first quarter, up from 81,509 a year earlier; 25,321 MW of onshore wind, up from 20,176; and 31,627 MW of batteries, up from 19,621. 
    • 66,959 MW of clean power capacity is now operational in Texas, the most of any state; California is second, at 35,002 MW, and Iowa is third, at 13,486. 
    • 1,964 MW of clean power came online in the first quarter in Texas, the most of any state; Florida was second, at 1,789 MW, and California was third, at 293 MW. 
    • Texas led the U.S. in capacity under active construction in the first quarter, with 18,950 MW; New York led in capacity in advanced development stages, at 13,850 MW, though 4,000 MW of offshore wind fell out of its pipeline early in the second quarter. 
    • Developers reported a cumulative 62 GW of clean power projects as “delayed” in the first quarter and expect a little less than half of that — 29.8 GW — to become operational by the end of this year. 
    • 7,773 MW of power purchase agreements were announced in the first quarter, 52% more than in the same quarter of 2023. Utilities were responsible for most of the increase, but corporate PPAs increased as well: Microsoft alone announced 1.4 GW of new PPAs, and Meta, Amazon and UnitedHealth Group also reached sizable PPAs. 

Ameren: MISO Missouri Capacity Shortfall Likely Inconsequential

Ameren executives have reassured shareholders that Missouri’s capacity shortfall beginning this summer is no cause for panic.  

Speaking May 3 on a first-quarter earnings call, CFO Michael Moehn said he doesn’t expect Missouri ratepayers to see “material” bill impacts from MISO’s capacity auction. The utility also doesn’t expect to encounter “any issues with providing reliable electric service throughout the year for our customers,” he said.  

MISO’s recent capacity auction returned insufficient capacity for the upcoming fall and spring 2025 in Missouri’s Zone 5, where capacity prices hit the $719.81/MW-day limit on par with building new generation.   

Otherwise, all local resource zones cleared at $30/MW-day for the summer, $15/MW-day for the fall, $0.75/MW-day for the winter and $34.10/MW-day for the spring. Zone 5 contains local balancing authorities Ameren Missouri and the Columbia, Mo., Water and Light Department. (See Missouri Zone Comes up Short in MISO’s 2nd Seasonal Capacity Auction, Prices Surpass $700/MW-day.)  

Moehn said the cost of new entry prices in MISO Zone 5 are a function of “higher load requirements, changes to the accredited capacity of generation available and reduced import capability.”  

He said auction results indicate that Ameren Missouri needs to redouble efforts to “execute the generation plans” laid out in its integrated resource planning. The pairing of new, large loads with new renewable generation means that significant transmission expansion is more necessary than ever to maintain reliability, he said.  

“We stand ready to work with stakeholders in our region to address the capacity needs,” Moehn said. He added that the Ameren Illinois and Ameren Missouri service territories are on track to experience mounting load growth, with new projects proposed from the automotive, aerospace manufacturing, data center and agricultural industries.  

Ameren’s retiring Rush Island Energy Center — which played a role in the Zone 5 capacity shortfall — also factored into the utility’s earnings picture for the first quarter.  

Ameren announced first-quarter earnings of $261 million ($0.98/share) compared to $264 million ($1/share) a year ago. CEO Marty Lyons said unseasonably warm conditions in February and March reduced profits, as did expenses related to mitigation relief stemming from Rush Island’s unresolved air pollution case.   

“Despite the year-to-date weather headwinds and the Rush Island charge, our team is taking steps to contain spending, and we remain on track to deliver within our 2024 earnings guidance range of $4.52 per share to $4.72 per share,” Lyons said. 

For the rest of 2024, Ameren will implement hiring restrictions, reduce its contractor and consultant workforce and cut back on discretionary spending, Moehn said. 

Coal Woes

The company recently filed a plan with the U.S. District Court of Eastern Missouri to remediate 14 years of unlawful air pollution from Rush Island. The $20 million plan involves a surrender of the plant’s sulfur dioxide allowances under EPA’s cap-and-trade program, distributing air filters to disadvantaged households downwind of the pollution and an offer to purchase 20 electric school buses and 40 charging stations for the St. Louis area. 

The U.S. Department of Justice, on the other hand, insists Ameren spend $120 million on a plan including more intensive bus electrification and residential filtration programs. (See Court: Ameren Still Without Remedy for Years of Rush Island Air Pollution.)  

Ameren expects evidentiary hearings on the matter this summer and the court’s decision by the end of the year.  

“When you look at the components of the two programs, they are very similar in terms of electric school buses, air filtration program, charging infrastructure. … It really is seemingly not a matter of the program mix, but sort of the extent of them and the cost of them. So, we can’t predict what mitigation the court would ultimately order,” Lyons said.  

He added that any penalty will be “nonrecurring and onetime and won’t be something that affects ongoing operations or earnings.” 

The district court last year ordered Rush Island to shut down no later than Oct. 15. Ameren opted to close the plant rather than spend several million dollars to install a flue gas desulfurization system to scrub excess emissions. The Justice Department and Ameren have been at an impasse for two years over how to remediate Rush Island’s longstanding environmental harms beyond the plant’s early retirement.  

Lyons said Ameren is progressing on its request with the Missouri Public Service Commission to securitize the remaining balance of Rush Island, noting that PSC staff in March recommended the company be allowed to securitize $497 million instead of an original request for $519 million. The PSC is expected to issue a ruling in late June.  

Lyons cautioned that another Ameren Missouri coal plant, the Labadie Energy Center, faces an uncertain future. While units at the plant aren’t slated to retire until 2036 and 2042, they are vulnerable to EPA’s new rule stipulating that coal plants either close by 2039 or use carbon capture or other technologies to capture 90% of their emissions by 2032. (See EPA Power Plant Rules Squeeze Coal Plants; Existing Gas Plants Exempt.)  

Lyons said EPA “expects generators to rely heavily on carbon capture and storage technologies, which are not ready for full-scale economy-wide deployment.” He added that the rule’s application to new gas-fired units with greater than 40% capacity factors will likely complicate Ameren’s plan to add a gas-fired combined cycle plant sometime in the early 2030s to maintain reliability.  Litigation by stakeholders is likely, Lyons said.  

“While we are still assessing the impact of the rules on our integrated resource plan, these new rules are making it more challenging and costly to maintain existing dispatchable generation or build new dispatchable generation. These challenges come at a time when supply and demand is tight, and the industry has seen significant potential load growth. … These rules, if not modified, would require significant investments beyond what’s in our current 10-year pipeline to meet compliance obligations and maintain a reliable system,” Lyons said.  

Transmission Awards

Finally, Lyons called attention to MISO selecting Ameren to build three competitively bid projects from its first, $10 billion long-range transmission portfolio. (See MISO Chooses Ameren for 3rd Long-range Tx Project.) He said the awards provide evidence of the company’s “record of being able to deliver cost-effective, high-value projects to our communities.”  

“Ultimately, Ameren was assigned or awarded approximately 25% of total Tranche 1 portfolio projects addressing the MISO Midwest region and 100% of the projects in our service territory,” Lyons said.  

Lyons said he expects construction on the projects to “substantially begin in 2026.” He noted also that Ameren representatives have been collaborating with MISO planners in “ultimately approving the most appropriate path forward” on the approximately $20 billion in long-range transmission projects proposed in the RTO’s second portfolio 

Report: Small Nuclear Reactors not the Answer

In a recent report, a nuclear power expert from George Washington University strongly criticized proponents of nuclear power for presenting what she considered an overly rosy picture of the technology’s potential to meet the world’s energy needs while ignoring its many reliability and security challenges. 

The author of “New Nuclear Energy: Assessing the National Security Risks,” Sharon Squassoni, is a research professor of international affairs at GWU whose work focuses on reducing risks from nuclear energy and weapons. In a webinar last month, Squassoni said her goal in writing the report was to explore “what risks might arise given the goals of tripling nuclear energy and deploying small modular reactors to do many things in many places.” 

With increasing awareness of the climate effects of burning fossil fuels, some energy experts have touted nuclear energy as a proven technology for meeting baseload energy needs without emitting carbon dioxide and other pollutants. SMRs have emerged as the centerpiece of “an effort to make nuclear energy more affordable, safe and flexible, and thus more attractive to a broader range of uses and users,” the report said. 

However, the document pointed out that despite much effort from the nuclear industry and governments “to make nuclear energy relevant again after decades of stagnation,” the actual presence of SMRs on grids “is largely fictional.” 

While nuclear boosters have held out visions of cheaply built, moveable reactors powering individual towns and military installations while providing numerous other services, Squassoni said there are currently only two operating facilities that actually merit the SMR label. These reactors — China’s HTR-PM plant, in operation since December 2023, and Russia’s “floating nuclear power plant” Akademik Lomonosov, launched in 2010 — solve few of traditional nuclear plants’ problems and may create new ones, according to the report. 

The HTR-PM uses two reactors with a capacity of 100 MWe each, using a “pebble-bed” design incorporating spherical balls of uranium enriched to 8.5% U-235 (compared to the 3 to 5% enrichment typically used in commercial U.S. reactors). It was launched in 2001, based on an existing test reactor, with on-site construction beginning in 2012. 

The report noted that the higher enrichment of the reactor’s fuel could make it more attractive for use in a nuclear weapon, while the fuel fabrication, storage of spent fuel and reprocessing “will be more challenging to monitor” than in current reactors. In addition, safeguarding the reactor could be more challenging because it uses on-line refueling, a more complicated process than shutting down the reactor first, and because the spent fuel is stored on site. 

Akademik Lomonosov comprises two reactors with a capacity of 35 MWe each and was intended to replace a retired nuclear plant and coal plant in the Chukotka region of eastern Russia. The report noted that placing nuclear plants on a barge does solve the issues of “scarce land for nuclear power plants that require large emergency planning zones,” but the design is far from flawless. Planners must consider the risks of shipping collisions and tsunamis, along with the potential environmental damage of fuel and waste leaks. 

Floating plants are also “open to attack either from the surface of the sea or beneath it,” the report said. Pirates and terrorist groups could infiltrate the facilities to steal radioactive material or threaten to damage the plants for financial or political gain. 

Additionally, the report warned that “SMRs are unlikely to be built in quantities that will revolutionize nuclear energy” because focusing on large amounts of small reactors means giving up the economies of scale that come with building a single large, centralized plant. The report cited analysis from Princeton University suggesting “700 [small] plants would need to be produced” to outweigh the benefits of large plants, noting that “this is roughly the total number of commercial nuclear … reactors ever built.” 

Side Benefits Slow to Emerge

SMR supporters have also proposed that small reactors could provide additional benefits besides electricity, such as residential and industrial heating, desalination, and hydrogen production. The report said that these uses are “neither new nor unique to nuclear energy,” and Squassoni suggested that they would likely not be mentioned if alternatives to nuclear generation for electricity had not recently become available. 

“In the past, maybe 10 to 15 years ago, the nuclear power narrative was that nuclear was the only low-carbon baseload generation,” Squassoni said during the webinar. “But what’s happened in the interim is that [renewable energy sources] have captured such a huge part of the market for electricity generation that nuclear now has to tout its ability to multitask.” 

This multitasking ability has been touted by the U.S. Department of Energy, and the Electric Power Research Institute floated its NuIDEA plan last year that would see multiple microreactors operate at airports, college campuses, hospitals and other facilities to provide a range of services. But the GWU report said efforts to realize these ambitions will “likely be an uphill climb,” noting that in the U.S., only the Diablo Canyon reactor in California has provided desalination, and none has ever provided district heating. 

“Although there are more than 660 district energy systems operating in the United States, few present the right economics for large nuclear cogeneration plants,” the report said. “Smaller plants sprinkled among population centers might overcome the costs of heat transportation, but technical issues like the availability of large dual-purpose turbines to produce electricity and extract steam at suitable temperatures and pressures may continue to persist.” 

Military Risks Growing

Finally, the report warned about the possibility for SMRs to become military targets. 

Russian forces have occupied both the Chernobyl and Zaporizhzhia power plants at different times since they invaded in 2022 and remain in control of Zaporizhzhia as of early May. The head of the International Atomic Energy Agency (IAEA) recently said that Russia’s “reckless attacks” have brought the danger of nuclear mishaps “dangerously close.” Such an event would have devastating consequences not only for grid reliability but also for the local environment. 

“Cooperation among key states essential to minimize the safety, security and proliferation risks of nuclear energy is at an all-time low,” the report said. “The call to triple nuclear energy coincides with the disintegration of cooperation, the unraveling of norms and the loss of credibility of international institutions that are crucial to the safe and secure operation of nuclear power.” 

The report called for the U.S., Russia and China to resume their cooperation in nuclear nonproliferation rather than allowing the current environment to spiral into “great power competition.” 

“The United States still wields considerable influence in international fora associated with nuclear energy, nonproliferation and nuclear security, and it should use this influence to ensure that any expansion of nuclear energy does not exacerbate national security risks,” the report said. “But first, it will need to get its own policy house in order.” 

Pushback from Nuclear Community

Several nuclear experts who spoke to RTO Insider criticized the report, saying it overstated the risks of SMRs without considering the efforts of the international community to address them. 

Madeline Lockhart, a doctoral fellow in nuclear engineering at North Carolina State University, acknowledged that growing the nuclear fleet “will naturally lead to an increase in the associated nuclear security risks.” But she argued that the report’s characterization of these dangers is “not well defined,” and that policies should address the risks connected to “specific capabilities, facilities, designs, locations and countries” rather than taking an overly broad view. 

“Government organizations, National Laboratories and stakeholders are actively engaged with reactor vendors and buyers to address and minimize national security risks before any reactor will be connected to the grid. Often, robust and complex regulations and guidelines contribute to the extended timelines for reactor deployment — but the goal is always the deployment of safe and reliable energy production,” Lockhart said. “While the national security risks must be addressed, the risk associated with the failure to meet a growing global demand for electricity will be devastating.” 

Mehdi Sarram, who served as safeguards director of the Atomic Energy Organization of Iran from 1974 to 1979 and later served in DOE and the IAEA, called the report “biased toward a negative view of nuclear energy.” He disputed Squassoni’s claim about the vulnerability of Chernobyl and Zaporizhzhia, saying that the IAEA “has worked with Russia to avoid a possible attack on Ukrainian nuclear plants.” 

The report also discounts the boost that technological advances bring to nonproliferation work, according to Angela Di Fulvio, associate professor of nuclear, plasma and radiological engineering at the University of Illinois Urbana-Champaign. Di Fulvio noted that advances in radiation detection systems and other technologies helped the IAEA track the development of China’s nuclear weapons capabilities. 

With regard to SMRs, Di Fulvio admitted that deploying such resources may require “a paradigm shift in material accountancy” and close collaboration between designers and the IAEA to develop proper safeguards against diversion of nuclear material, particularly in regions of political instability. But she insisted that these risks “can be mitigated effectively” and should not prevent the deployment of needed energy resources. 

Paul Dickman, chair of the American Nuclear Society’s External Affairs Committee and formerly with DOE’s National Nuclear Security Administration, focused on the challenge of building large fleets of SMRs, noting that the U.S. lacks manufacturing capacity to produce reactor components on a large scale. He said that rather than looking to SMRs to replace large plants as baseload energy suppliers, they should be used to “fill in gaps where grids are small or to replace smaller coal and oil-based generating stations.” 

NJ Senator: Failing State Grid Can Stymie Clean Energy Efforts

The biggest obstacle to New Jersey’s adoption of clean energy is the state’s inadequate grid and a reluctance to make the kind of investments needed for the grid to handle a surge in solar and wind power, a state senator said at a clean energy conference. 

Sen. Bob Smith (D), chairman of the Senate Environment and Energy Committee, which initiates much of the state’s clean energy legislation, said that despite New Jersey’s aggressive agenda, the state is far short of creating a grid that can accept numerous clean energy connections. 

Smith spoke at the Clean and Sustainable Energy Summit 2024 on May 2 at Montclair University. Transmission issues were prominent, but some speakers differed with Smith’s analysis, praising initiatives such as the state’s aggressive solicitation of projects to develop onshore and offshore transmission links to connect offshore wind (OSW) projects with the grid.  

Smith said his committee got some “relatively modest” climate change initiatives passed but has struggled with major initiatives to prepare the grid for the task of handling the state’s shift to an energy system focused almost entirely on electricity. 

“We’re in trouble, and we’re not moving fast enough to solve the problem,” said Smith, the conference’s morning keynote speaker. He called for a “wartime mobilization for global climate change.”  

“We have this 19th-century view that you should not spend an extra one-tenth of a cent in trying to upgrade your grid,” he said. The attitude is “build what you basically need and maybe only for the short term. We don’t have long-term thinking, either at the federal level, FERC, or the regional entity PJM or in New Jersey. So we now have a grid that is held together by duct tape, and not very good duct tape.” 

Smith noted that Gov. Phil Murphy (D) marked Earth Week by citing his administration’s clean energy initiatives, including the allocation in his 2024/25 budget of $40 million for grid upgrades, to use a federal match. But Smith called it “literal spit in the bucket of what we need to do to make our grid work.” 

Commissioner Marian Abdou | © RTO Insider LLC

In an interview with NetZero Insider after his speech, Smith said he’s uncertain whether a bill he co-sponsored, S258, which would allocate $300 million to grid upgrades to use $200 million more in federal funds, will advance in the near future. Introduced in January, the bill in March passed out of the Senate Environment and Energy Committee but has yet to move in the Senate Budget and Appropriations Committee or the Assembly. 

Smith said educating legislators is not too dissimilar from educating the citizenry, in the sense they often get motivated only by a hurricane, flood or other crisis.  

“People have to understand how serious this is,” he said. “We have got to get their attention.” 

Marian Abdou, a commissioner of the New Jersey Board of Public Utilities (BPU), was more measured in her assessment of the state’s position. She said that “with an increase in demand for electricity and expanding our renewable energy resources, we need to ensure the grid can handle this influx.”  

Standing in for BPU President Christine Guhl-Sadovy, who was unable to attend, Abdou noted the board on April 30 approved a package of grid modernization rules that could help streamline the interconnection process. 

“Stable infrastructure is a critical piece of building a clean energy future, and for New Jersey, it centers on modernizing our electric grid,” she said. 

Balancing New and Declining Energy Sources

Matthew Bernstein, senior policy advisory, governmental services at PJM, addressing a panel on energy security, said the RTO faces a series of the challenges but already has recognized, and responded to, the need for “proactive transmission planning,” and an improved connection process. 

The RTO is working with stakeholders on a long-term framework that would allow it to get ahead of anticipated generator deactivations and load growth and focus beyond a “five-year regional transmission expansion planning process,” he said. 

Mathew Bernstein, PJM | © RTO Insider LLC

The RTO is addressing the ongoing backlog of new projects awaiting connection through reforms that would allow the company to “expeditiously move these projects through the interconnection queue,” Bernstein said. 

“We implemented stronger guardrails around speculative projects to show that the projects that are entering the queue really do have the potential to be built,” he said. “We’re already seeing a lot of projects make their way through the queue in a much more timely manner.” 

By the middle of 2025, PJM expects to have studied and processed projects with a combined capacity of about 72,000 MW, he said. And over the next three years, all 230,000 MWs of proposed projects will be studied by PJM and the response delivered to their developers, he added. Still, about 40,000 MW of generation that was passed out of the PJM connection process has not been developed due to obstacles such as supply chain issues, inflation and financial pressures, he said. 

PJM electricity demand growth | PJM

The RTO also is working to balance the retirement and closure of fossil fuel generators with the arrival of clean energy generators, to create a steady power flow that matches demand, Bernstein said. Load growth has increased dramatically, driven by “significant electrification of the transportation sector, heating equipment and other dwelling units, as well as the proliferation of data centers throughout the region.” 

In its annual forecast, PJM predicted from 2014 to 2024 that load growth would decline slightly, Bernstein said. But the RTO this year predicted summer peak load will grow by about 1.7%. That dynamic has raised questions about whether the RTO has “sufficient generation available to meet our demand today, and in the future, not just the actual demand, but also have sufficient reserves in place for contingencies,” Bernstein said. 

“If the load continues to grow at the rate that we are expecting, and we are seeing resources retire, this will become a problem,” he said “It’s not a problem that we’re seeing this moment today. But over the coming decade, this will become a problem if these (new) resources aren’t coming into the system in a timely manner.” 

Linking OSW to the Grid

Damian Bednarz, managing director for Attentive Energy Two, which is developing a 1,342-MW OSW project off the Jersey Shore, agreed with Smith that long-term planning will be “critical” to the sector. The state has shown foresight in its “prebuild” solicitation seeking proposals for transmission infrastructure that will link OSW projects with the grid on land, Bednarz said.  

If completed, Attentive Energy Two and a second project, Leading Light Wind, together would bring about 3,742 MW of capacity through Sea Girt, in Monmouth County. The projects would connect to the grid at the Larrabee Collector Station, an entry gateway the BPU instigated in a solicitation held under the FERC State Agreement Approach. 

Damian Bednarz, Attentive Energy | © RTO Insider LLC

Bednarz, referring to Smith’s comment that the state needs a “wartime mobilization,” said he believes “offshore wind is that counterattack.” He added that “if we’re going to have a counterattack in this effort to combat climate change, it takes a deep level of investment into not just the generation, but all aspects, to make this reality.” 

Attentive Energy was the developer of one of three projects canceled by the New York State Energy Research and Development Authority (NYSERDA) after they had been approved in the state’s third solicitation, on Nov. 17. NYSERDA said the designated developers could not finalize their agreements due to changes in several factors, in particular a decision by GE Vernova to halt development of an 18-MW variant of its Haliade-X turbine and to remain making smaller, less efficient turbines.

Bednarz called the cancellations “incredibly frustrating” for many stakeholders, but he said the sudden, dramatic project meltdowns may be dissipating. Attentive Energy’s New York project suffered from the change in technology due to GE Vernova’s decision, rather than routine supply chain price hikes, he said. 

“You also have a lot of states looking at the solicitations differently, I think, through some hard trial and error,” he said. “In key aspects of the solicitations, you have an inflation adjuster additive that could potentially push back on some of the supply chain risks, and then increased costs that can vary being factored in.“ 

“And I believe New Jersey, going forward, as well is going to have a lot of those things built into solicitations that prevent some of that increase in costs,” he said. 

FERC Approves NYISO Request to Lower NYC Capacity Requirement

FERC on May 6 granted NYISO’s waiver request to update its installed capacity requirement for New York City in the 2024/25 capability year, which began May 1 (ER24-1800). 

The amount of capacity the market is set to procure for Zone J (i.e., the city) was off because NYISO originally used the wrong historical data to calculate the transmission security limit (TSL) floor for the zone, from 2017-2021 instead of 2018-2022. The TSL floor is an input for the locational capacity requirement (LCR) and essentially acts as the minimum LCR. 

The correct inputs lead to a TSL floor value (and LCR) of 80.4% instead of 81.7%. NYISO told FERC in its request that the waiver would save load-serving entities in the city about $15 million to $20 million per month in capacity costs. 

NYISO discovered the issue late and only filed its request on April 18, but it immediately reported the issue to FERC’s Office of Enforcement and the ISO’s Market Monitoring Unit, Potomac Economics, on April 10, as required by its tariff. The grid operator said it acted swiftly to analyze the error and determine its impact and potential remedial impacts. It is also trying to understand how it happened and avoid it going forward, it said. 

The waiver is the narrowest feasible solution to the problem created by the error, NYISO said. Only Zone J needs to be fixed, and the correction would not cause any reliability issues or changes to the reserve margin set for the New York Control Area. 

The waiver also addresses a concrete problem by avoiding overcharging consumers in New York City, and it would not have undesirable consequences, such as harming third parties, the ISO said. 

“NYISO argues that although the correction may result in lower capacity prices in Load Zone J, which may be contrary to the economic interests of some market participants, no stakeholder has a legitimate interest in preventing an error from being corrected for that reason,” FERC said. “NYISO asserts that all market participants will benefit from capacity auction prices that accurately reflect NYISO’s methodology for computing transmission security limit floor values for LCRs.” 

The LCR is also the basis for several downstream processes related to the capacity market, such as the determination of capacity accreditation factors and the availability of capacity import rights, but NYISO said it did not need to fix those issues yet because the financial impacts of doing so would be limited. However, the ISO said it would continue to work with stakeholders to assess the feasibility, implications, timelines and required actions to pursue any corrective actions going forward. 

The Independent Power Producers of New York and New York City both said NYISO should work expeditiously to complete the assessment of how other downstream parts of the capacity market might be impacted.  

FERC found that the waiver request met its requirements, including solving the concrete problem of avoiding overcharging for capacity. 

While some parties argued for additional requirements that NYISO fully address the downstream impacts of its error, FERC said such arguments were beyond the scope of the proceeding. The commission encouraged NYISO to expeditiously complete its assessment of the error’s impact and continue working with stakeholders on a solution. 

Wisconsin PSC: Missing Info in We Energies’ Oak Creek Coal-to-gas Plans

The Public Service Commission of Wisconsin said it’s missing several details from We Energies regarding its multiyear plan to substitute gas for coal at its Oak Creek Power Plant south of Milwaukee.  

In a May 3 letter, the commission said it and the Wisconsin Department of Natural Resources reviewed We Energies’ application for a certificate of public convenience and necessity to build the gas plant and deemed it incomplete. The PSC told the utility it could not make a decision and to re-file an application including the overlooked specifics (6630-CE-317). 

We Energies intends to retire two of its 60-year-old Oak Creek coal units this month and the remaining two units by December 2025. It has requested to replace the capacity on-site with $1.4 billion in five gas-fired combustion turbines that would generate up to 1.1 GW. The utility applied for the certificate at the beginning of April and expected to have commission approval this month.  

The Wisconsin PSC compiled a three-and-a-half-page list of missing or incomplete elements in the application. The agency asked for modeling data supporting the case for the plant, drawings of proposed and alternate layouts, an estimated maintenance schedule, a description of all major construction activities and a breakdown of capital costs. The commission asked We Energies to detail how hydrogen “may be used for any potential future fueling of the proposed combustion turbines.”  

The agency also zeroed in on how the plant could be affected if the utility’s proposed, 33-mile Rochester Lateral gas pipeline is rejected, and asked how the pipeline stands to affect the plant’s construction schedule. We Energies filed for permission to build the pipeline — which would supply firm natural gas service to Oak Creek — on the same day it requested commission approval to the build the plant.  

The PSC asked We Energies to calculate the amount of firm natural gas supply needed to run all five turbines continuously at maximum output and asked if its proposed upgrades to its natural gas infrastructure — alongside ANR Pipeline Co.’s planned capacity expansion in the area by late 2027 — would be enough to support those kinds of operations. It also asked how much a proposed, on-site liquified natural gas storage tank would hold and how long the tank could support the new turbines running at full speed.   

The commission said it wanted to know if We Energies anticipates or has factored in additional costs to convert the Oak Creek substation since the new gas plant must connect to the MISO system at different voltages than the existing coal plant. Transmission owner American Transmission Co. is phasing out its 230-kV system in the area and will use only 138-kV and 345-kV voltages, affecting Oak Creek’s point of interconnection.  

In February, FERC granted We Energies a departure from MISO’s interconnection rules so the replacement gas plant can connect to the system at a different voltage without the utility having to submit a fresh interconnection request with MISO. (See We Energies Secures FERC Permission to Switch Coal Interconnection with Gas Plant.)  

The PSC asked whether We Energies has contacted MISO to perform retirement studies to figure out if the system can operate reliably as the coal units cease production and after Oak Creek’s interconnection point is calibrated to different voltages. It said it wanted to know if powering down the four coal units can “proceed as planned without reliability concerns.” It also asked whether Oak Creek’s generator replacement studies consider only the two immediate coal unit retirements or all four of them.   

Finally, the PSC said We Energies submitted an incomplete construction-noise study with its application.  

In its application to build the plant, We Energies called Oak Creek’s shift to natural gas a “key component” in providing reliability amid its fleet transition, conforming to MISO’s stricter resource adequacy rules, meeting growing load and complying with proposed EPA requirements.  

EPA Finalizes Methane Reporting Rule for Oil and Gas Industry

EPA issued a final rule May 6 meant to strengthen, expand and update methane emissions reporting requirements for oil and natural gas systems, as required by the Inflation Reduction Act. 

Oil and natural gas facilities are the largest industrial source of methane, which is a stronger greenhouse gas than carbon dioxide — though shorter lived — and estimated to be responsible for about a third of the increase in global average temperatures. 

The IRA’s Methane Emissions Reduction Program is meant to help states, industry and communities implement recently finalized standards under the Clean Air Act and slash emissions from the oil and gas sector. The Biden administration also is mobilizing $1 billion to accelerate the transition to no- and low-emitting oil and gas technologies as part of a broader effort to cut methane emissions. 

“EPA is applying the latest tools, cutting-edge technology and expertise to track and measure methane emissions from the oil and gas industry,” EPA Administrator Michael Regan said in a statement. “Together, a combination of strong standards, good monitoring and reporting, and historic investments to cut methane pollution will ensure the U.S. leads in the global transition to a clean energy economy.” 

EPA said studies have shown that actual emissions from the oil and gas industry are much greater than what they have reported to the agency. The new rule is meant to address that gap by making it easier to use satellite data to identify superemitters and quantify large emission events, and by requiring direct monitoring of key emission sources. 

EPA also is finalizing new methods allowing empirical data for quantifying emissions to be used. The changes are meant to improve transparency and give owners and operators more options to submit empirical data to show their efforts to cut methane emissions. 

The rule covers about 8,000 facilities around the U.S., which have to report their emissions data annually; EPA publishes the results every October. Owners and operators of oil and natural gas systems that emit 25,000 metric tons or more of equivalent carbon dioxide emissions annually are required to report their emissions. 

Aaron Padilla, vice president of corporate policy for the American Petroleum Institute, said in a statement that the final rule raises serious concerns, including the use of “flawed methodologies” that could lead to inaccurate reporting of higher GHG emissions. 

“We are reviewing the final rule and will work with Congress and the administration as we continue to reduce GHG emissions while producing the energy the world needs,” he said. 

The Environmental Defense Fund, which launched its own satellite earlier this year to track methane emissions, welcomed the new rules. 

“By directing EPA to update and strengthen methane emissions reporting, Congress recognized the vital importance of measurement-based, accurate and scientifically robust data to establish the true volume of pollution created by the oil and gas industry,” EDF Senior Scientist Daniel Zavala-Araiza said in a statement. “Updated methane reporting, along with continued integration of new measurement data, will allow us to better understand emission sources and mitigation opportunities and track changes in emissions over time.” 

Members Vote Against Granting PJM Filing Rights over Planning

BALTIMORE, Md. — The PJM Members Committee on May 6 rejected endorsement of revisions to the RTO’s Operating Agreement and tariff shifting filing rights over the Regional Transmission Expansion Plan (RTEP) from the committee to the Board of Managers. 

The language received 25% sector-weighted support during PJM’s Annual Meeting, held this year at the Baltimore Marriott Waterfront hotel. 

The proposal was brought to the MC by the PJM Board of Managers in response to similar revisions to the Consolidated Transmission Owners Agreement (CTOA) brought to the Transmission Owners Agreement-Administrative Committee (TOA-AC). The TOA-AC also is set to consider revising the CTOA on May 14. Should the CTOA be modified, modifications to the PJM OA and Tariff would be necessary to avoid inconsistency.

The vote does not necessarily prohibit the board from unilaterally filing a proposal with FERC. PJM Director of Stakeholder Affairs Dave Anders said the board sought the input of stakeholders on the changes prior to considering whether to agree to any CTOA amendments that the TOA-AC may request.

During the April 25 Markets and Reliability Committee meeting, PJM General Counsel Chris O’Hara said the board has not ruled out making a Federal Power Act Section 206 filing asking FERC to grant it filing rights over the RTEP protocol if TOA-AC approves the CTOA revisions and the MC does not endorse the companion OA and Tariff revisions.

. At the Annual Meeting, board Chair Mark Takahashi stressed that no decisions had been made and that the board values the stakeholder process. There may be some cases, however, where the membership reaches a stalemate and the process cannot yield a solution to an issue that needs resolving, he said. 

Several stakeholders argued they had only weeks to consider the changes, leaving insufficient time to vet the language for unintended consequences or to provide thoughtful comments. 

Paul Sotkiewicz, president of E-cubed Policy Associates, said transferring the planning to the Tariff from the OA, in the context of the planning reforms in the table, would lead back to integrated resource plans. 

Susan Bruce, of the PJM Industrial Customers Coalition, said the key difference with the RTO holding filing rights is that overriding an MC vote currently requires a filing under FPA Section 206, which must demonstrate that the existing governing document language is unjust and unreasonable. 

“We strongly believe in the stakeholder process. The PJM stakeholder process has been important in balancing parties’ rights in this industry that has gone through a lot of transitions,” she said, adding that stakeholders have not had adequate time to think through the proposal. 

LS Power’s Sharon Segner argued that any MC votes to amend the OA must immediately result in a FERC filing, but the drafted CTOA language includes a mediation process for any instances where a TO objects to an MC vote that it feels is contrary to the agreement. She said the interactions between that provision and the proposed OA and tariff language are not understood. 

The status quo governing document language strikes a balance between granting TOs filing authority over local planning decisions, while PJM membership holds filing authority over regional planning. 

Exelon’s Alex Stern said the PJM Members Committee is not a FERC jurisdictional public utility.  It is a body created for consultation and does not have regional planning authority — that burden lies with PJM, which should hold final say over planning decisions. Stern asserted that “the Planning Protocol was directed to be placed in the OA by FERC nearly two decades ago to afford PJM independence. Unfortunately, as things have evolved, that intention has been thwarted to the point that people now actually incorrectly believe the Members Committee and not PJM has the regional planning authority.”

He said TOs, as PJM members, also are giving up stakeholder process veto rights over the planning protocols, but supporters of the CTOA revisions believe changes are needed to ensure reliability through the clean energy transition and to meet rising load, noting the growing reliability challenges facing PJM, highlighted by last week’s announcement that the summer outlook PJM presented to the Operating Committee on May 2 stated there’s a smaller generation pool available this summer than past years while forecast peak loads are increasing. (See related story, “PJM Confident on Summer Reserves; Stakeholders Concerned About Long Term,” PJM Operating Committee Briefs: May 2, 2024.) 

PJM PC/TEAC Briefs: April 30, 2024

Planning Committee

Stakeholders Discuss Change to CIR Transfer Issue Charge

The East Kentucky Power Cooperative presented potential revisions to the process for transferring capacity interconnection rights (CIRs) from a retiring generator to a replacement resource. 

The changes would allow for solutions to include CIR transfers to planned resources interconnecting at the same substation as the deactivating unit, but on a different breaker. Both sets of language would preclude proposals contemplating shifting CIRs to a resource connecting to an entirely different substation. 

During the April 2 PC meeting, EKPC Vice President of Federal and RTO Regulatory Affairs Denise Foster Cronin said package formation at the Interconnection Process Subcommittee revealed the issue charge would prevent solutions sought by some stakeholders to allow CIRs to be transferred to a new resource interconnecting on a different breaker, but which otherwise are electrically equivalent. (See “Stakeholders Discuss Expanding CIR Transfer Issue Charge,” PJM PC/TEAC Briefs: April 2, 2024.) 

Exelon Director of RTO Relations Alex Stern suggested modifying the proposed revisions to require that solutions allow only CIR transfers to generators interconnecting at the same or lower voltage as the original resource. Stern argued that increasing the voltage would be more likely to impose additional costs as well as implications to service to others that would compromise the clean CIR transfer the issue charge intended to explore. The suggestion was not accepted to provide more time for the package sponsors, EKPC and Elevate Renewables, to consider the changes. 

First Read on CIFP Manual Revisions

PJM presented a set of manual revisions to codify changes to capacity accreditation, reliability risk modeling and procurement targets FERC approved in January following PJM’s Critical Issue Fast Path (CIFP) process last year. (See FERC Approves 1st PJM Proposal out of CIFP.) 

Manuals 20, 21 and 21A would be replaced with new Manuals 20A and 21B — which respectively detail resource adequacy analysis and the determination of generating capability. Manual 14B, which pertains to the regional transmission planning process, would see changes to its load deliverability analysis and the capacity emergency transfer objective (CETO) and capacity emergency transfer limit (CETL) analyses. 

PJM plans to ask the PC to vote on endorsing the manual revisions during its June 4 meeting. The Market Implementation Committee endorsed related revisions to Manual 18, which relates to the capacity market, on May 1. If endorsed, the manual revisions would be effective for the 2025/26 delivery year. 

Transmission Expansion Advisory Committee

PJM Updates RTEP Timeline

PJM intends to open two competitive Regional Transmission Expansion Plan (RTEP) windows in July to solicit proposals to resolve transmission violations and interconnect 3.5 GW of wind generation planned off the New Jersey shoreline. (See “PJM Preparing 2 Competitive Transmission Windows in July,” PJM PC/TEAC Briefs: April 2, 2024.) 

PJM’s Sami Abdulsalam presented the Transmission Expansion Advisory Committee with a plan to use an eight-year horizon when identifying grid upgrades necessary under New Jersey’s second State Agreement Approach (SAA), under which the state agreed to cover the cost of transmission necessary to meet its policy goal of developing 3.5 GW of offshore wind. 

The longer window allows the RTEP analysis to capture how load growth, generation deactivations and the first round of SAA transmission — which aims to facilitate the interconnection of 7.5 GW of offshore wind in New Jersey — may interact with transmission needs identified, Abdulsalam said. 

The eight-year window also will identify any reliability needs and could lead to multi-driver projects that share reliability and facilitate offshore wind interconnection in New Jersey.  

PJM also aims to open the first standard reliability-focused five-year window of the 2024 RTEP in July. Abdulsalam said the window likely will be open for 60 days. Vice President of Planning Paul McGlynn told RTO Insider that more detail about needs identified in the window likely will be presented in June or July. 

Scope Change to 2022 Window 3 RTEP Adds $19.5 Million

PJM has expanded the scope of a component of the 2022 RTEP Window 3 to upgrade an existing 230-kV line to 500-kV for an estimated $19.5 million. 

The original project scope was to add a 500-kV line parallel to the existing Otter Creek-Conastone 230-kV line. Abdulsalam said dialogue between PJM and PPL suggested there could be substantial benefits to upgrading the existing line as part of the project. 

Upgrading the line as part of the 2022 RTEP could limit construction along the corridor and add scalability to a vital corridor for moving power between northern and southern PJM regions. 

The project is one component of a larger $5 billion transmission expansion the PJM Board of Managers approved in December 2023 to address concentrated load growth in northern Virginia and about 11 GW of deactivating generation, most notably the Brandon Shores plant and the Wagner Generating Station outside Baltimore. 

Supplemental Projects

FirstEnergy proposed a $35 million project to upgrade its South Reading 230-kV substation in the Med-Ed transmission zone to mitigate the risk of multiple breakers or a bus fault causing the entire facility to go offline. The proposal would reconfigure the substation to a double-breaker, double-bus configuration; replace the bus conductor; install new circuit breakers; and build a new control house. The work would increase the ratings of the 230-kV lines between South Reading and the Boonetown, Lauschtown and Berks substations. 

The project is in the engineering phase, with a project in-service date of Dec. 31, 2026. 

The utility also proposed rebuilding its gas-insulated 230-kV Smithburg substation in the JCPL transmission zone due to the need for specialized parts, poor performance and its age at over 40 years old. The $30.2 million project would reconfigure the substation to be open-air, along with upgrading terminal equipment, retiring the Smithburg-Larrabee and revising relays at the Larrabee, East Windsor, New Prospect Road and Manalapan facilities. 

The project is in the conceptual phase, with a possible in-service date in June 2027. 

FirstEnergy also presented several proposed projects to replace transformers across its facilities. A $56.4 million project would replace three 500/138-kV transformers at its Belmont substation in the APS transmission zone. The utility said the units are approaching their end of life and are experiencing degradation challenged by obsolete replacement parts. The replacements would be staggered to go in service between June 2027 and December 2029. 

Two separate projects also would replace 230/69-kV transformers at the South Reading substation, due to increased gas levels and their age. The projects, which are in the engineering phase, would total $17.6 million, with completion targeted in June and December 2025. 

In the Penelec zone, FirstEnergy proposed replacing a 230/115-kV transformer at its Shawville substation due to age, maintenance issues and nitrogen leaks. The utility also discussed replacing a 345/230-kV transformer at the Homer City substation as it approaches its end of life and parts have become obsolete. The projects are estimated to cost $17.6 million. 

Exelon presented a $35 million project to install seven new 345-kV circuit breakers at its Libertyville substation in the ComEd zone, as well as replace two deteriorating oil circuit breakers with SF6 based units. 

Dominion presented a problem statement for possible reliability violations along the transmission corridor between the Possum Point and Fredericksburg substations. More than a dozen substations are planned in the region to serve growing data center load, which could strain existing transmission even with four ongoing projects to upgrade the corridor to hold two 230-kV lines, the utility said. 

Projections of the load interconnecting on the 13 new substations suggest consumption could increase by more than 1,700 MW by 2029 and by more than 3,000 by 2032. Dominion said load is increasing at a similar pace along the corridor to the south of Fredericksburg, with 14 new substations along that segment estimated to have 2,000 MW of new load by 2029 and an additional GW by 2032. 

Ensuring adequate transmission in place would require either new “diverse transmission sources” or additional reconfiguring of the two 230-kV lines to allow additional lines to be installed, which Dominion said may result in increased outage times, higher costs and delays to consumer in-service dates. 

Dominion proposed rebuilding its 10.6-mile Harrisonburg-Grottoes 230-kV line as it approaches the upper end of its expected lifespan. Most of the line was built in 1970 with wood structures, which would be replaced with steel at an estimated cost of $28 million. The project is in the conceptual phase, with a possible in-service date in December 2027. 

PJM MIC Briefs: May 1, 2024

Stakeholders Endorse Manual Revisions to Implement CIFP Changes to Capacity Market

The Market Implementation Committee endorsed by acclamation a rewrite of Manual 18 to implement market redesigns drafted through the Critical Issue Fast Path (CIFP) process last year and approved by FERC in January. (See FERC Approves 1st PJM Proposal out of CIFP.)  

If endorsed by the Markets and Reliability Committee, the revisions would expand the use of effective load carrying capability (ELCC) analysis for accrediting all generation types, require that planned resources notify PJM of their intent to participate in a Base Residual Auction (BRA) at least 90 days in advance and change how generation unforced capacity (UCAP) values are calculated. 

The Planning Committee endorsed related revisions to Manuals 20, 21 and 21A on April 30 to reflect the risk modeling and accreditation changes the commission approved. 

The revisions to Manual 18 would shift the calculation of the maximum annual nonperformance penalties generators face to be based on the net cost of new entry (CONE) — effectively decreasing the penalty over the current use of auction clearing prices. 

First Read on Proposed Demand Response Energy Market Parameters

PJM’s Pete Langbein presented a proposal to add two energy market parameters for demand response resources that would allow them to specify a maximum run time and a minimum “cooldown” period after being dispatched before the resource can be committed again. 

Langbein said PJM plans to ask the committee to endorse the revisions June 5 with the aim of filing the proposal at FERC in October. He said the filing likely would request a nine-month implementation period due to the complexity of changing the market clearing engine and to allow testing of the changes. 

Langbein said there are differences between a resource saying it’s not economical to operate under certain conditions and being able to respond to a capacity call. 

“They’re not saying they can’t respond; they’re saying they don’t want to respond because it’s not economical,” he said. 

Update Re-evaluation of CONE Inputs

PJM plans a June 5 presentation to discuss analysis by the Brattle Group on whether the CONE values produced by the most recent quadrennial review remain accurate or should be updated to reflect rising interest and construction costs. (See “PJM Re-evaluating CONE Inputs,” PJM MRC Briefs: April 25, 2024.) 

Skyler Marzewski, PJM | © RTO Insider LLC

FERC approved the quadrennial review in February 2023, accepting a shift to a forward-looking energy and ancillary (EAS) offset and a combined cycle reference resource, rather than the previous combustion turbine. (See FERC Approves PJM Quadrennial Review.) 

PJM’s Skyler Marzewski said a quick-fix proposal revising the inputs to the CONE calculation may be included in the June presentation, with the aim of submitting a FERC filing in August or September. Any changes to CONE values would be effective for the 2027/28 BRA. The quick-fix process allows for an issue charge and proposal to be voted on concurrently. 

PJM’s Pat Bruno said Brattle’s analysis includes whether there should be more regular revision of the CONE inputs, possibly through escalation factors. 

Stakeholders Regroup on Energy Efficiency Rules After MRC Rejection of Proposals

Proposals rewriting how the capacity contributions of energy efficiency resources are measured and verified were brought back to the drawing board after the MRC rejected four packages in March. (See “Stakeholders Reject Changes to EE Measurement, Verification,” PJM MRC/MC Briefs: March 20, 2024.) 

PJM questioned the value EE provides, with Langbein stating he has yet to see a case made that capacity market revenues are incentivizing the purchase of devices more efficient than what consumers otherwise would have bought. 

“They shouldn’t be able to claim things that are naturally going to occur … if I’m making a decision to purchase a high-efficiency air conditioner, an EE provider shouldn’t be able to claim that unless they can prove” that they incentivized the purchasing of that unit over a less efficient product, Langbein said. 

Luke Fishback, of Affirmed Energy, said the purpose of EE is to find the most economically efficient way of pricing a guaranteed reduction in consumption over PJM’s load forecast. 

Several items were added to the solution matrix, including requirements for when EE providers may need contracts with each of the end-use customers participating in EE programs. PJM also modified an option previously part of its package, which would require end-use customer data be provided to PJM, to only require that data be provided to the RTO upon request. 

The stakeholder process is focused on developing package components, which could be used to develop new proposals for the committee to consider later.