Report Criticizes Gas Plant Performance During California Heat Wave

California’s gas-fired power plants experienced a surge in curtailments during last summer’s heat wave, according to a new report, which questions whether the facilities are a solution to preventing energy shortfalls.

At the same time, the gas plants’ emissions spiked, worsening air quality in disadvantaged communities, according to the report, released Wednesday by Regenerate California. The group is a coalition led by the California Environmental Justice Alliance (CEJA) and the Sierra Club.

“Gas simply does not do its job when it matters most,” said Ari Eisenstadt, energy equity manager at CEJA. “Gas plants’ mythical reliability value in keeping the lights on is far outweighed by their negative air quality impacts for environmental justice communities.”

Regenerate California partnered with consultant Grid Strategies to analyze power output and emissions from 107 gas plants in California during the record-breaking heatwave from Aug. 31 to Sept. 9, 2022.

Potential generation that was lost due to gas plant outages and derates during the heat wave totaled more than 1.1 million MWh, or nearly 5,000 MW on average, according to the analysis, which used CAISO data.

And during the peak period from 4 to 9 p.m., curtailments were about 200 MW higher on average.

“California gas plant curtailments track fairly closely with CAISO hourly demand during the heat wave, likely reflecting that derates due to high ambient temperatures coincide with periods of high electricity demand,” the report said.

The report didn’t include curtailment data from days outside of the heat wave. But Grid Strategies Vice President Michael Goggin said a standard assumption is that about 5% of the gas fleet will be unavailable during peak periods.

In contrast, a curtailment of 10% or even as much as 15% was seen at peak periods during last year’s heat wave, Goggin said Wednesday during a media briefing on the report.

That was due to gas plants running less efficiently when the weather heats up, along with an increase in equipment failures, Goggin said. Older plants that were fired up during the heat wave were less reliable, he added.

“It’s pretty clear that these gas plants fell well short of what was expected of them,” Goggin said.

When asked to comment on the report, a spokesperson with the Edison Electric Institute, which represents U.S. investor-owned electric companies, said EEI members are working to deploy wind, solar and energy storage resources while demonstrating technologies that aren’t yet available at cost and scale.

“As we continue to deploy those resources, nuclear energy and natural gas generation are essential partners in accelerating the clean energy transition,” EEI media relations director Sarah Durdaller told RTO Insider. “They allow our member companies to integrate more renewables into the energy grid while ensuring resilience and reliability.”

Emissions Spike

The report also examined gas plant emissions using data from EPA’s continuous emissions monitoring program. For the 107 plants for which EPA data were available, emissions of sulfur dioxide, nitrogen oxides and carbon dioxide increased by about 60% during the heat wave compared with a baseline period of Aug. 19-28, 2022.

Not only did overall emissions increase, but emissions per megawatt-hour were also up as older plants came online, Goggin said.

“There were some very dirty power plants that turned on during these really top hours of need,” he said.

The increased emissions came after Gov. Gavin Newsom issued an emergency proclamation at the start of the heat wave, loosening air quality requirements to allow gas-fired power plants to generate more electricity. (See Newsom Declares Emergency as Heat Stresses Calif. Grid.)

Blackouts Avoided

CAISO was able to avoid rolling blackouts during the heat wave, despite demand reaching a new high of more than 52 GW on Sept. 6. Several factors helped prevent a blackout, the ISO said, including an emergency text message sent out to 27 million cell phones on Sept. 6 urging consumers to conserve electricity. Within 20 minutes of the 5:45 p.m. alert, demand plunged by 2,385 MW. (See CAISO Reports on Summer Heat Wave Performance.)

“That’s really what kept the lights on,” Eisenstadt of CEJA said during Wednesday’s media briefing. “If we were paying people to do that — especially if we were paying low-income ratepayers to do that — the effect would be massive.”

Eisenstadt and others called on the state to fund clean energy projects rather than keeping gas plants going.

“We must invest in demand-side solutions and drive local clean energy buildout in environmental justice communities to improve air quality and ensure grid reliability,” said Teresa Cheng, senior campaign representative with the Sierra Club.

And Eisenstadt said the dense snowpack from California’s unusually wet winter — with its expected boost to hydropower this summer — gives the state a window of opportunity to move away from gas power plants to greener forms of energy.

Some older gas plants that were slated for closure now may be kept in service as part of the Strategic Reliability Reserve that the state developed last year as part of Assembly Bill 205.

For example, AES Corp. announced in April that it signed agreements with the California Department of Water Resources to extend operations of once-through cooling units at its Huntington Beach and Alamitos gas plants through 2026. The units had been scheduled to stop operating in December 2023.

Units at Huntington Beach and Alamitos made it onto a list in the Regenerate California report of the top 15 gas plants ranked by megawatt-hours of curtailment during the heat wave.

If the three-year extensions for the 1.4 GW at Huntington Beach and Alamitos are approved, AES will run the units during emergency grid reliability events within the Strategic Reliability Reserve Program, the company said.

“Our Southland legacy units continue to demonstrate that they are ready and able to support the reliability of California’s electric grid,” Andrés Gluski, AES president and CEO, said in a statement at the time.

NERC Finds Grid Generally Reliable and Resilient

NERC on Thursday released its 2023 State of Reliability report, which found that the North American bulk power system generally remains highly reliable and resilient.

Transmission system reliability has improved significantly for the fifth consecutive year, but conventional generation — challenged by more frequent extreme weather — saw its highest level of unavailability overall since NERC started gathering generator availability in 2013.

Generation saw its worst “weighted equivalent forced outage rate” last year, Manager of Performance Analysis Donna Pratt said on a conference call with reporters Thursday.

“When we analyze this by fuel type, we also observed increasing outage rates for coal over the five-year period, which correlates to higher numbers of start-ups and maintenance outages,” Pratt said. “And the unavailability of gas-fired generation recently has been consistently higher during the winter months.”

Those are two of the main reasons why generation is “surpassing transmission in contributing to major load-loss events,” she added. No apparent trends are discernable in other forms of generation, the report said.

“Higher overall outage rates for coal and gas generation, as well as some utility-scale solar generation not operating as necessary for reliability, indicate that there is still significant work to be accomplished to accommodate the rapidly changing weather and generation resource mix in conjunction with electrification of the economy in a reliable manner,” said Pratt.

The most significant reliability event of the year was the winter storm in December, also known as “Elliott,” which impacted the eastern U.S. and prompted a joint inquiry from FERC and NERC into what happened. The inquiry is expected to be completed late this year, so NERC’s report did not go into depth on Elliott. (See FERC, NERC Set Probe on Xmas Storm Blackouts.)

But in response to that and other recent cold weather events, NERC issued a Level 3 “essential action alert” this May to tell the industry to increase its winter preparedness. NERC has issued several new standards on winter readiness this year, and others are under development.

NERC’s report also highlighted a June 4, 2022, event around Odessa, Texas, where a failed surge arrestor caused the loss of 333 MW of synchronous generation, leading to the erroneous loss of another 511 MW and an unexpected loss of 1,700 MW of solar PV generation.

“The total generation lost exceeded the most severe single contingency and nearly exceeded the Texas Interconnection resource loss protection criteria, the design threshold that is used to establish the requirements for frequency recovery in the Texas Interconnection,” the report said.

That event and other similar ones indicate that the dynamic performance of inverter-based resources (IBRs) have to be improved if the grid is to benefit from their rapid expansion, NERC said.

Texas has had similar events with IBRs, as has the Western Interconnection, and NERC has highlighted the issues with IBRs since 2016. NERC is working to upgrade its standards to address the issue, and FERC launched a rulemaking on it last year. (See FERC Addresses IBRs in Multiple Orders.)

Immediate industry actions are needed to implement published guidelines and ensure the reliable operation of the grid as IBRs grow.

“IBR modeling requirements need significant improvement to ensure that high-quality, accurate models are used during reliability studies so performance issues can be identified before they occur during real-time operations,” NERC said.

Physical and cyberattacks on grid assets are increasing, and that reinforces the need for the further development and adaptation of standards and guidelines.

“The growing attack surfaces that result from the increasing penetration of distributed energy resources call for ongoing development and adaptation of cyber and physical security standards and guidelines to keep up with the ever-changing threat landscape,” NERC said. “Furthermore, cyber-informed planning should include designs and be considered when planning and integrating the technologies into the grid to strengthen the cyber robustness.”

Hostile nation states are continually targeting North American critical infrastructure and are constantly evolving methods to compromise the grid’s security, reliability and resilience.  Homegrown extremists have also targeted the grid, NERC added.

South Fork Wind Announces ‘Steel in the Water’

The two offshore wind farms vying for first-in-the-nation status both now have “steel in the water.”

New York announced Thursday that the first monopile foundation has been installed for South Fork Wind, a 132-MW project being developed by Ørsted and Eversource off the eastern tip of Long Island.

Two weeks ago, installation of the first monopiles and transition pieces began at Vineyard Wind 1, an 800-MW project being developed by Avangrid Renewables and Copenhagen Infrastructure Partners south of Martha’s Vineyard in Massachusetts.

Vineyard and South Fork occupy the same patch of the Outer Continental Shelf south of New England that the Bureau of Ocean Energy Management is developing for emissions-free wind power.

Bokalift 2 is the center of activity on South Fork, supported by a fleet of smaller vessels and onshore personnel.

DEME’s slightly smaller Orion is performing a similar role for Vineyard, also supported by a cast of hundreds.

The heavy lift vessel Orion carries components to the Vineyard Wind project off the Massachusetts coast. | Vineyard Wind

Work on both began in 2022, and while Vineyard got a two-week head start on actual tower installation, the crews need to erect 62 turbines there, compared with only a dozen at South Fork.

Developers of the two projects and their fans in state government each say that theirs will be the first utility-scale or commercial-scale offshore wind project in U.S. waters; bragging rights presumably would belong to the one that goes online first.

South Fork expects to start producing electricity this year. Vineyard had previously specified a 2023 startup date in its publicity materials but no longer includes any prediction.

An increasingly interesting question is, which wind farm will be the third in U.S. waters?

Developers of three projects comprising 97% of New York’s contracted offshore wind pipeline and two projects comprising 67% of the pipeline in Massachusetts have all said they cannot proceed under the financial terms they agreed to before interest rates and input costs skyrocketed.

They’re seeking to cancel and renegotiate their deals. Whether or not they are successful, project delays and/or higher costs to ratepayers appear likely.

In that sense, being first worked to the advantage of South Fork and Vineyard — they locked in their contracts before costs increased.

New York Gov. Kathy Hochul said in a news release Thursday that South Fork will not only help protect the climate but also help the state develop economically.

“This progress on building the first utility-scale offshore wind project in the country cements New York as a national hub for the offshore wind industry,” she said.

Massachusetts has economic goals similar to New York’s in the offshore wind sector and has set a significantly higher per capita target for gigawatts of offshore wind power.

Massachusetts Gov. Maura Healey on June 7 offered an assessment similar to Hochul’s:

“Our administration is grateful for the important work being done by Vineyard Wind, Avangrid, CIP, DEME and labor partners to bring clean, affordable energy to Massachusetts. We’re thrilled to see this historic project move one step closer to completion and committed to supporting the offshore wind industry across the state.”

NERC Committee Delays Guidance on Grid-Forming Batteries

A white paper on a pressing matter — managing battery systems connected to the grid — bogged down in a debate over its details as NERC’s Reliability and Security Technical Committee (RSTC) met Wednesday.

A request for approval of “Grid Forming Functional Specifications for BPS-Connected Battery Energy Storage Systems” was tabled to allow time to seek industry comment and potentially rework the report.

It was the only matter on the 27-item agenda that drew any votes of opposition.

Shortly before the vote, RSTC Chair Greg Ford said the subject is important but that getting the report correct is important as well.

“As a matter of fact, it’s probably one of the more important documents we’ve talked about in a while as we move this grid transformation and this whole idea of bringing batteries into the fold of dispatch,” he said.

“We’re trying to make this paper as solid and informative as we can so that we can allow it to take us to the next steps, whether that be guidelines or SARs [standards authorization requests] in the future, depending on how batteries come into play.”

The debate and discussion touched on the input the Inverter-Based Resource Performance Subcommittee sought as it wrote the white paper — one speaker said he saw no NERC-registered entities on the list — but centered more on the wording of the report, which some felt was too strong.

Growing Need

The version of the white paper before the committee Wednesday states that:

Studies have shown that absent supplemental synchronous machine-based solutions, grids dominated by inverter-based resources (IBRs) need grid-forming (GFM) IBRs to maintain stable operation.

Accordingly, the need for GFM technology is expected to accelerate with the rapid growth of IBRs, and planning is necessary to ensure sufficient GFM IBRs are installed.

One of the largest obstacles to installing GFM on the bulk power system (BPS) is establishing clear interconnection requirements for the performance, testing and validation of the technology.

So, the paper addresses how transmission owners, planners and coordinators can establish these requirements and test interconnecting resources.

It gives generator owners clear performance expectations for GFM resource interconnections so they can work with manufacturers before interconnection studies begin and possibly streamline the interconnection queue process.

A common question among industry stakeholders is how many IBRs should be deployed with GFM functionality; there is not a single answer, but initial studies indicate upward of 30% may be necessary.

Since the current percentage is near zero in nearly all large, interconnected power systems, the paper recommends starting to require and enable GFM in all future battery energy storage systems (BESS), a relatively low-cost step to ensure system stability.

Industry should begin specifying, requiring and implementing GFM for all new BPS-connected BESS.

Sticking Points

Words like “requiring” and “should” were problematic for some at the meeting.

“I think in this white paper, if it was just providing the technical recommendations on the specifications, I think I would let it go,” one speaker said. “But this is going further and it’s recommending that you ‘shall,’ in all battery storage applications, install grid-forming and enable it. That’s quite a strong statement to make without having industry comment.”

Ford agreed on the power of words, saying that “should be doing” and “should be considering” are different things.

Others emphasized the importance of the issue beneath the semantic debate.

“This is critical for reliability, the work that y’all are doing, and this paper is really important,” another attendee said. “Bringing the grid-forming characteristics to the surface is pretty important because we can’t wait till we need it to start thinking about getting it, because it’s too darn late at that point.”

Another said: “This is something this group asked for. We’ve been talking about it for three years. Our interconnection queue is getting tremendously bogged down with battery storage. … We are always struggling on this. Any delay is not going to do us much of a service, quite honestly.”

Another sought to reverse-engineer a solution to the debate, asking: “What are we trying to achieve here with this white paper?”

“The goal is to provide some guidance to utilities in areas that are already … considering grid-forming today,” subcommittee Chair Julia Matevosyan said.

Another speaker said he saw a wide leap in functionality between a white paper offering helpful ideas and one leading to SAR that “sets off bells and whistles of importance.”

“There ought to be a way to distinguish between the two,” he added.

Matevosyan did her best.

“If I may, I would just like to reiterate that this is just a white paper, there is no talk of SAR,” she said.

Wednesday’s vote pushes any RSTC action on the white paper back at least until the group’s September meeting.

“That was — fun,” Ford said as he called a recess, closing the matter after more than an hour of discussion.

Blackstone Infrastructure to Scoop up Minority Stake in NIPSCO

Blackstone Infrastructure Partners will pick up a nearly 20% stake in Northern Indiana Public Service Co. for a little more than $2 billion, parent NiSource announced Tuesday.

NiSource has been on the hunt for a buyer for a noncontrolling equity interest in NIPSCO since late last year. (See NiSource Selling Minority Interest in NIPSCO.) The $2.15 billion deal will have Blackstone acquiring a 19.9% stake and pledging an additional $250 million in equity to fund a pro rata share of NIPSCO’s ongoing capital needs, according to NiSource.

NiSource said the purchase will help finance NISPCO’s continuing transition to a decarbonized fleet and reinforce grid resilience while “accelerating the reindustrialization of the Midwest.” It also said Blackstone is interested in a “long-term buy-and-hold approach to large-scale infrastructure assets.”

NIPSCO said it expects to invest $3.5 billion in the grid through 2030, with most of that going to new renewable generation to replace coal-fired assets. The company said it will end reliance on coal by 2028; that’s compared to the 75% coal generation mix it employed in 2018.

The transaction is expected to close by the end of 2023, pending FERC approval.

NIPSCO President Mike Hooper said the deal will allow NIPSCO to invest in large renewable generation projects while making capital improvements to its electric and gas infrastructure.

NiSource CFO Shawn Anderson added that the utility is “confident this is the right path forward” to boost NIPSCO’s balance sheet and “navigate the current challenging interest rate backdrop” while the utility establishes a more sustainable and reliable system.

“We’re pleased to reach this agreement at a compelling valuation following a robust and competitive process and are confident that Blackstone is the right partner for NIPSCO and NiSource going forward, given its global footprint and deep infrastructure experience, including in renewable development and procurement,” NiSource CEO Lloyd Yates said in a press release. “With this transaction, our commitment to Indiana remains unchanged, and we will be able to drive further sustainable growth for our stakeholders. This financing transaction will have no impact on NIPSCO’s current strategic direction or on our commitment to our gas and electric customers in Indiana.”

Blackstone Global Head of Infrastructure Sean Klimczak said the deal “underscores Blackstone’s commitment to decarbonization to create value for our investors and our desire to help facilitate the reindustrialization of the Midwest.”

WoodMac: More than 1.8 GW of US Energy Storage Projects Delayed in Q1

After a strong showing last year, the U.S. energy storage market shrank in the first quarter of 2023, with grid-scale installations dropping 21% year over year, according to a new report from industry analysts Wood Mackenzie and the American Clean Power Association (ACP).

Installations fell from 697 MW in the first quarter of 2022 to 554 MW this year, primarily due to a backlog of more than 1.8 GW of storage projects that were scheduled to come online in the first quarter but have been delayed by supply chain and interconnection bottlenecks, the report says.

“Late-stage projects are facing rolling delays, with 80% of delayed projects from Q4 2022 scheduled to come online in Q1 once again pushed to later quarters of the year,” the report says.

Wood Mackenzie expects about 1.4 GW of the backlog to go online in the second quarter but cautions that “volatility quarter to quarter is still strong, and additional delays should be expected.”

On the upside, the residential storage sector hit a record high of 155.4 MW deployed in the quarter, while community, commercial and industrial (CCI) installed 69.1 MW, the sector’s second highest quarter on record. Wood Mackenzie defines grid-scale as storage interconnected to the transmission system, while CCI and residential are classified as on the distribution system. All sectors have experienced supply chain and interconnection delays. (See Report: Storage Projects Stymied at Distribution System Interconnection.)

Despite the grid-scale slowdown, which Wood Mackenzie says could continue through 2024, the report still expects the U.S. to add 75 GW of storage between now and 2027, with grid-scale accounting for 81% of the total.

But will that be enough to get to President Joe Biden’s 2035 goal of a completely decarbonized grid? Probably not, said Vanessa Witte, Wood Mackenzie’s senior analyst for energy storage. Using conservative estimates, “our base case analysis projects about 65% zero-carbon electricity by 2035, not 100%,” Witte said in an email to NetZero Insider.

An August 2022 study from the National Renewable Energy Laboratory sets a much higher target for energy storage by 2035, calling for 120 GW to 350 GW of “diurnal storage” — that is, with a duration of 2 hours to 12 hours.

However, the U.S. market is also lagging on duration, a critical need for grid reliability, according to Wood Mackenzie. For example, the 554 GW of grid-scale storage installed in the first quarter can deliver about 1,553 MWh of energy, which averages out to less than 3 hours of duration. The figures for residential and CCI are similarly low.

Witte sees duration as a reflection of how storage is currently being used on the grid, which varies by geography. California and Texas dominate the U.S. market, with about 84% of grid-scale deployments, the report says.

“In California, storage is predominantly being used across the hours that are required to gain resource adequacy, which are the ramping hours between around 5 p.m. to 9 p.m. … which has driven the 4-hour durations,” Witte said. “In other markets though, such as Texas, lower durations are more typical because there is no capacity [or resource adequacy] market, so storage is predominantly used to capture price spikes. It is a purely economic play, and this does not require or incentivize more than 1-2 hours of duration.”

“Outside of California and Texas is a bit of a mixed bag,” she said. “Storage isn’t always being used for firming or resiliency purposes, which would incentivize a 4-hour or longer duration,” although storage with 4-hour duration is becoming more common, she said.

Solar + Storage

The report sees several markers for storage market growth.

The pipeline of new projects is growing, the report says. Project announcements jumped year over year, from 42 GW in the first quarter of 2022 to 75 GW this year. Similarly, storage capacity sitting in interconnection queues rose from 315 GW to 430 GW.

Costs are also coming down, the report says, from $1,896/kW in the first quarter of 2022 to $1,778/kW this year, a 6% drop. Witte said those figures represent a median, “turnkey” price that includes not only the battery packs, but the balance of system and other installation costs, minus developer and interconnection fees.

The growth of the solar market is still another driver, as more solar systems are paired with storage, Witte said.

“Solar-paired systems made up 64% and 42% of installs in 2021 and 2022, respectively, and [are] projected to be about 54% of the 2023 installs,” she said. “Each year has some amount of variation, though we do expect solar-paired systems to take up a large chunk of the installs moving forward.”

One highly uncertain variable is the energy storage supply chain — specifically, how quickly the U.S. industry can wean itself off its dependence on China for the processing of critical minerals such as lithium, cobalt and nickel — and manufacturing of storage cells and battery packs.

The tax credits and other incentives in the Inflation Reduction Act will have a “tremendous impact” on the storage supply chain, Witte said. A recent report from ACP found that 10 utility-scale battery storage manufacturing plants had been announced since the IRA passed in August.

NE Stakeholders Debate Future of Everett at FERC Winter Gas-Elec Forum

FERC commissioners on Tuesday questioned ISO-NE officials and New England state regulators on the region’s short-term winter reliability challenges and the need for the Everett LNG import terminal, at a forum on gas-electric coordination in Portland, Maine.

While much of the discussion focused on similar topics to the FERC reliability forum held in Burlington, Vermont, in September 2022, the tone of this year’s conference was less dire. A joint study released in May by ISO-NE and the Electric Power Research Institute (EPRI) found that the risks of a supply shortfall in New England during extreme winter weather events are “manageable” through 2027, even without Everett, though the RTO has pushed to keep the terminal operating because of longer-term reliability concerns. (See FERC Comes to Vermont and Leaves with a New England-sized Headache and Study: Limited Exposure to Supply Shortfall for ISO-NE During Extreme Weather.)

But this led to skepticism from Commissioner James Danly, who has warned of a looming resource adequacy crisis because of retiring fossil fuel-fired generators. He repeatedly questioned RTO officials on the study’s assumptions.

One of the findings of the study was that behind-the-meter solar was underestimated.

“I have to admit, I’m surprised to think that the hopes for winter reliability in New England hang entirely on one set of assumptions on one technology that is ‘surprisingly’ being deployed at the rate that it is,” Danly told ISO-NE COO Vasmi Chadalavada. He asked what other assumptions have changed since last year.

Chadalavada noted that the RTO’s position that Everett should be retained has not changed, but that the study focused on the electric system, not the gas system.

“In the longer run, I’m still as concerned as I’ve ever been,” ISO-NE CEO Gordon van Welie told the commissioners. “I think it would be extremely unwise were we to let that facility go until we know where we are with regard to these variables.”

Commissioner Allison Clements said she found the study to be “really comprehensive” and that it “provides key parameters to consider, and the resulting low odds of load shedding are encouraging.” She acknowledged, however, that ISO-NE “notes itself that it’s not equipped to assess the gas system’s effects without Everett because only” the gas industry “can speak to that.”

Vermont Department of Public Service Commissioner June Tierney observed that “nine months ago, the message was, ‘Oh my word, the sky is falling’; today the message is, ‘Well, we’ve got some breathing room.’”

“I can relate to the bewilderment sense that Commissioner Danly has,” she continued, as nothing seems to have materially changed since the Burlington conference. But, she said, ISO-NE “did the analysis, and they’re to be congratulated for that. And it being ISO’s analysis, I have no question that it was done well.”

She advised FERC to formally solicit information from ISO-NE about the assumptions and inputs that it used for the study, not just for its ratemaking benefit but also for public transparency.

Everett

Much of the daylong forum’s discussions focused on Everett and the Mystic plant.

Richard Levitan, president of the consulting firm Levitan & Associates, called Everett “the insurance that helps to safeguard both electric and gas reliability on extremely cold days.”

Carrie Allen of Constellation Energy — the parent company of both Everett and its primary customer, the Mystic generation plant — agreed that the facility is needed and added that the region is “running out of time” to keep the plant open, noting the long regulatory process that would be required if an agreement is reached.

New Hampshire Consumer Advocate Donald Kreis, however, said ratepayers have been overpaying for reliability “insurance,” and he opposes burdening consumers with additional costs from new reliability programs.

“We can design markets to force ratepayers to buy every last aliquot of reliability that industry can conjure, but I beg you not to do that,” Kreis said. “In particular, I beg ISO New England not to seek, and I beg FERC not to approve, some new market mechanism — or worse, some out-of-market mechanism — to guarantee that the Everett terminal stays in business.”

In written comments submitted to FERC for the forum, Kreis expressed concern about the true benefits of the current Mystic agreement, designed to keep the generator in service through this winter. He cited the extreme weather conditions on Dec. 24 that required ISO-NE to declare a capacity deficiency as an example of what he said were dubious reliability benefits provided by the agreement.

“It was shocking to learn that Mystic station had not been dispatched as a resource adequacy crisis loomed, given the vast sums of free money that had been awarded to the facility’s owners via the FERC-approved reliability-must-run arrangement,” Kreis wrote.

In contrast, gas utility and pipeline industry representatives expressed their concern that ISO-NE is underestimating the reliability risks to the region and argued that the region should maintain Everett and look to build additional gas infrastructure to address reliability concerns.

James Holodak of National Grid said that until renewables can displace significant natural gas demand in the region, “the prudent decision would be to keep Everett open” while expressing his frustration with the difficulties of constructing new natural gas infrastructure in the region.

“All the solutions that we’re talking about are fairly expensive relative to the potential for a new pipeline into the area,” Holodak said.

Ernesto Ochoa, Kinder Morgan | FERC

Ernesto Ochoa of Kinder Morgan said the penetration of renewables will increase the need for gas infrastructure.

“We believe that more infrastructure is needed in the region, not less, and we’re going to continue to say so forever,” Ochoa said.

Richard Paglia of Enbridge agreed on the need for additional gas infrastructure to bring more natural gas to the region.

“To me, the glue that holds all of this together are the gas plants that are highly dispatchable … but we don’t have the supply to allow those plants to run when needed,” Paglia said.

Massachusetts Energy and Environmental Affairs Secretary Rebecca Tepper pushed back on the idea that the region should pursue additional gas infrastructure.

“The region’s problem is an overreliance on natural gas,” Tepper said, saying policymakers need to focus on valuing storage, energy efficiency and demand response programs. She declined to give a definitive answer as to whether Gov. Maura Healey’s administration supports the retention of Everett beyond the end of the Mystic agreement.

Notable Absences

Energy industry representatives and state regulators made up a large number of speakers at the forum, which notably lacked direct representation of environmental justice or climate-focused organizations, while Kreis was the only ratepayer advocate to serve as a panelist.

Massachusetts EEA Secretary Rebecca Tepper | FERC

“I think this hearing would have benefited from some additional voices today, particularly from the environmental and environmental justice communities, and particularly [from the city] of Everett,” Tepper said.

Vermont Commissioner Tierney echoed Tepper’s comments, saying, “There are voices out there of people who have not been a part of these discussions to date, and who are also not being directly addressed by this conversation.”

She noted that officials often stress the importance of gas during the transition to clean energy: “Every time we say that there are people saying, ‘Do you not get it? We need to stop burning fossil fuels.’”

“I worry that our conversation today — which, again, was expert and highly incisive and elucidating — I worry about it coming across as tone deaf. … The problem I see continues to be, to the folks we’re trying to reach — the hearts and minds that need to join us in this process — they continue to feel like they’re not included in the study thinking.”

While environmental justice groups were not included as speakers at the forum, several groups did submit written comments or release statements about it, including the Berkshire Environmental Action Team, No Coal No Gas and the Fix the Grid Coalition.

“As fossil fuel-dominated interests gather in Portland, Maine, on June 20 for the 2023 New England Winter Gas-Electric Forum, we expect them to double down on rhetoric that we need even more fossil fuel infrastructure, in the name of reliability,” No Coal No Gas wrote in a statement prior to the event. “Yet we expect that most of the panelists will be silent on lessons learned from the most recent epitome of winter reliability failure, a widespread failure of fossil fuel generators (particularly gas generators) to deliver on Dec. 24, 2022, a cold snap when they were most needed.”

In a letter signed by representatives of local climate and environmental justice organizations, Fix the Grid called for a “more holistic approach to grid planning and management,” taking into account “the public health and environmental impacts of current and future winter reliability policies and programs, including markets, on low-income environmental justice communities across New England.”

The campaign also advocated for an analysis of the reliability potential of increased transmission, energy storage and demand-side solutions including demand response, energy efficiency and conservation.

“We would like to see FERC encourage ISO New England to work with states and public interest organizations to envision a reliable grid that is also affordable and sustainable for all communities,” the group wrote

Conservation Helps ERCOT Meet High Demand

AUSTIN, Texas — ERCOT officials issued their first voluntary conservation call of the year Tuesday as the Texas grid flirted with peak-demand records during an oppressive heat wave.

The grid operator asked Texans to voluntarily reduce their electric use between 4 and 8 p.m., “if safe to do so,” because of extreme heat and forecast record demand. ERCOT also requested that the state’s government agencies reduce energy use at their facilities as much as possible.

Demand peaked at 79.2 GW during the hour ending at 6 p.m. Tuesday, the last official day of spring. That fell short of ERCOT’s record peak of 80.1 GW, set in August. It was also short of the new peak record for June, set Monday at 79.3 GW.

The grid operator last week had projected record peak demand of 83.2 GW for Tuesday. (See ERCOT: Prepared for Expected Record Demand.)

“ERCOT is not experiencing any emergency conditions right now,” CEO Pablo Vegas told the Board of Directors during its bimonthly meeting Tuesday.

Vegas told the directors that voluntary conservation is a “very widely used industry tool” to help lower demand during certain times of the day. ERCOT credited the conservation efforts and other reliability tools with surviving the tight periods Tuesday.

As it normally does when ERCOT needs every megawatt possible to meet demand, the Texas Commission on Environmental Quality accepted the grid operator’s request to exercise its enforcement discretion for any generator’s exceedance of the agency’s air-permit limits. The discretion ended at midnight Wednesday.

ERCOT recently rolled out a new notification system to help alert Texans to grid conditions before an emergency is called. Last week, it issued its first weather watch, extending through Wednesday, to draw public attention to potential high demand triggered by extreme hot temperatures. (See “New Grid Notifications Added,” ERCOT Monitor Recommends New Market Design in Report.)

A dangerous heat wave has settled over much of Texas since last week. Humid conditions have sent heat indexes above 120 degrees Fahrenheit in some portions of the state and caused the National Weather Service to issue excessive heat warnings and heat advisories.

ERCOT is expecting demand to exceed 83 GW next Monday and Tuesday. However, its projections have often come up short.

Extreme heat has Texans taking every precaution. | Mothers Against Greg Abbott PAC

Several cities have set record highs this week, with Laredo hitting 115 F on Monday. That day, Houston reached triple digits a month earlier than normal.

Despite the sizzling temperatures during the waning days of spring, Woody Rickerson, ERCOT’s vice president of system planning and weatherization, told the board that staff are expecting temperatures this summer to be average and not as extreme as last year, the second-hottest summer on record. A developing El Niño and May rains have lessened the chance for above-normal temperatures, Rickerson said.

Solar energy has carried the load for ERCOT, providing as much as 12.2 GW of energy Tuesday, close to its summer-accredited capacity of 12.6 GW, which is up 50% over last year. Rickerson said the increase in solar resources has moved the ISO’s normal summer peak from the 5 p.m. hour to 9 p.m.

“The amount of solar we have on the system has really helped mitigate what used to be our peak hour before,” he said. “Now, we’re a little more worried about moving to the 9 p.m. hour. Load will drop from 5 to 9 p.m., but the solar is dropping more than the load drops, so that makes your tightest hour to be later in the day.”

That makes ERCOT dependent on wind to meet the summer demand, Rickerson said. ERCOT has a little over 10 GW of summer-accredited wind resources, but more than three times that in nameplate capacity.

“That’s the reality of where we are. Every day, we’re going to have to look at what the wind is doing,” he said.

Washington Looks to Lead on Clean Aviation

Washington is expanding efforts to make the state a leader in emissions-free aviation, Gov. Jay Inslee signaled at the Paris Air Show this week.

Inslee on Monday joined ZeroAvia CEO Val Miftakhov at the air show to announce that the state will invest $350,000 to aid ZeroAvia’s expansion at Boeing’s Paine Field in Everett, Wash., where the company is working to develop an electric engine to be installed in Dash 8-4000 76-seat aircraft. The state previously provided $350,000 to ZeroAvia in 2022.

Meanwhile, another Washington-based project will begin to use renewable energy and water to transform carbon dioxide into a synthetic aviation fuel.

Inslee is in Paris because aviation is a major state industry. The sector also accounts for 2.5% of the world’s carbon emissions, according to governor’s office.

ZeroAvia is developing hydrogen-electric planes, targeting a 300-mile range for nine- to 19-seat aircraft by 2025, and a 700-mile range for 40- to 80-seat aircraft by 2027. The company says it is has secured $10 billion in pre-orders from several airlines.

“ZeroAvia is a key member of the rapidly growing ecosystem of world-leading innovators located in Washington state who are building the future of sustainable aviation fuels and zero-emission propulsion systems,” Inslee said in a press release.

In the same release, Miftakhov said: “The support from Governor Inslee and the Washington Department of Commerce enables us to push forward quickly on our targets for commercial flight of up to 20-seat aircraft by 2025, and up to 80-seat aircraft by 2027.”

In April, the Washington legislature appropriated $6.5 million to build a sustainable aviation fuel (SAF) research center at Paine Field with the effort to be led by Washington State University.

‘Perfect Location’

In the second announcement, Inslee and SAF producer Twelve announced the company will break ground next month on a Moses Lake plant to produce jet fuel from renewable electricity, water, and CO2 — which will be sourced from landfills and waste from food processing plants. The company has dubbed its fuel E-Jet.

“Commercial-scale production of E-Jet fuel is a major milestone in our mission of creating a world run on air,” Twelve CEO Nicholas Flanders said in a statement. “Washington is the perfect location for our facility, with its abundant renewable energy resources to power our carbon transformation process and longstanding global leadership in the aviation industry.”

SkyNRG recently announced plans to build a $800 million sustainable aviation fuels plant at an undisclosed location in Washington. It was encouraged by the state legislature passing a major tax break for such plants.

The new law sets a business-and-occupation tax rate of 0.275 percent for any plant that would produce annually at least 20 million gallons of low-carbon jet fuel. Most B&O tax rates in Washington range from 0.47 percent to 0.9 percent. A B&O tax is a tax on the business’ gross receipts.

The law’s purpose is to construct an alternative jet fuel plant in Washington. A few years ago, the predicted cost of building such a plant was at least $1 billion.

TransWest Express Transmission Line Breaks Ground

The TransWest Express transmission project, designed to carry 3,000 MW of Wyoming wind power to the Southwest and California, broke ground Tuesday on a typically windy day in Carbon County, Wyo.

Energy Secretary Jennifer Granholm, Interior Secretary Deb Haaland and Wyoming Gov. Mark Gordon participated in the ceremonial groundbreaking at a cattle ranch where the line’s northern HVDC terminal will be built.

The Biden administration said the groundbreaking represented a milestone in its push for faster transmission buildout.

“The TransWest Express project will accelerate our nation’s transition to a clean energy economy by unlocking renewable resources, creating jobs, lowering costs and boosting local economies,” Haaland said in a statement.

TransWest got the go-ahead to build in April, when the U.S. Bureau of Land Management issued a notice to proceed. It was the final step in an approval process that began 15 years ago. (See TransWest Express to Break Ground After BLM Approval.)

The 732-mile high-voltage line will be capable of transmitting 3,000 MW of energy from wind farms near Rawlins, Wyo., to consumers in California, where it is regarded as an important component of the state’s push to achieve 100% clean energy by 2045.

To meet the goal, the state will need to import as much as 10 GW of out-of-state wind by 2040, at least half of it from Wyoming, according to projections by the California Public Utilities Commission and California Energy Commission.

CAISO’s inaugural 20-year transmission outlook estimated that carrying wind from the Great Plains and Rocky Mountain states to California to achieve 100% clean energy would cost $12 billion.

Last summer, TransWest’s developers asked to join CAISO as a participating transmission owner under a new subscriber model, in which a line’s subscribing customers pay its costs. The ISO’s Board of Governors approved the request in December, and FERC approved the agreement between CAISO and TransWest in March as a step toward PTO status. (See FERC OKs CAISO-TransWest Move Toward PTO Status.)

If the arrangement wins final FERC approval, CAISO will operate the line, and its entire capacity will be allocated to the Power Company of Wyoming (PCW), owner of the 3,000-MW Chokecherry and Sierra Madre Wind Energy Project being constructed in the south-central part of the state. FERC approved the arrangement in February 2022.

Both TransWest and PCW are wholly owned affiliates of The Anschutz Corp., a privately held company controlled by billionaire Phillip Anschutz.

Once built, TransWest will consist of 732 miles of transmission lines in three linked segments: a 405-mile, 3,000-MW HVDC system between Wyoming and Utah; a 278-mile, 1,500-MW HVAC line between Utah and Nevada; and a 49-mile, 1,500-MW HVAC transmission line in Nevada.

It will connect in Utah to lines serving the Los Angeles Department of Water and Power and in Nevada to CAISO’s balancing authority area.

Construction is expected to begin by the end of this year, with energization scheduled for 2027, TransWest has said. The line is expected to create about 1,000 jobs during its construction phase.

Other major Western lines being developed to transmit wind energy from the Great Plains and Rocky Mountains include PacifiCorp’s Gateway South transmission line across Wyoming, Colorado and Utah. PacifiCorp, owned by billionaire Warren Buffet’s Berkshire Hathaway, plans to add more than 3.7 GW of new wind power by 2040 in Wyoming and five other Western states.

Pattern Energy’s SunZia transmission project, a 550-mile line from New Mexico to Arizona, received route approval from BLM in May, with construction expected to start this summer. The line will carry energy from Pattern’s 3,500-MW SunZia Wind project in central New Mexico to markets in Arizona and California.