Search
`
July 25, 2024

Mass. Legislature Faces Looming Deadline to Pass Permitting Reform

With Massachusetts’ legislative session ending July 31, lawmakers are on the clock to reach an agreement on a major climate bill centered around clean energy permitting and siting reform.

Culminating over a year-and-a-half of work on a wide range of proposed climate legislation, the Senate passed an omnibus bill in late June (S.2838), and the House of Representatives followed with its own legislation on July 17 (H.4884).

The bills contain closely aligned changes to how the state permits clean energy infrastructure but vary significantly beyond the permitting provisions and have elicited mixed responses from clean energy advocates in the state.

Permitting reform has been a major focus of the session. A state commission — featuring the House and Senate co-chairs of the Joint Telecommunications, Utilities and Energy Committee — issued recommendations in April. This was followed by negotiations between the two chairs and the administration of Gov. Maura Healey (D). (See Mass. Commission Issues Recs on Energy Project Siting, Permitting and Mass. Lawmakers Aiming for an Omnibus Climate Bill in 2024.)

The resulting proposal would streamline and consolidate state and local permitting of clean energy infrastructure. For large projects, the state’s Energy Facilities Siting Board (EFSB) would approve them through consolidated permits that encompass “all municipal, regional and state permits that the large or small clean energy infrastructure facility would otherwise need to obtain individually.”

Municipal permitting would remain under local control but be incorporated into the consolidated EFSB process. For smaller projects, all municipal permits similarly would be consolidated into a single application and approval process.

For large clean energy infrastructure projects — defined as including generation, storage, transmission and distribution infrastructure — the EFSB would be tasked with setting approval timelines that are specific to the infrastructure type, capped at 15 months after an application is deemed complete. Only the final consolidated permit could be appealed to the Massachusetts Supreme Judicial Court.

The approval timelines for small projects would be capped at 12 months. The local permitting decision could be contested with the EFSB, which would have six months to either affirm or overrule the local permitting decision.

The clean energy permitting provisions have received strong support from renewable developers.

“The solar and storage industry is glad to see lawmakers continue to push forward on common-sense reforms to reinforce the commonwealth’s place as a national clean energy leader,” Valessa Souter-Kline, the Solar Energy Industries Association’s Northeast regional director, said in a statement. “The reforms include time limits for permitting decisions, a streamlined appeals process and more predictable interconnection that will provide critical certainty for solar and storage businesses.”

Dan Dolan, president of the New England Power Generators Association, praised the approval time frames and consolidated EFSB process, adding there’s “a meaningful benefit to sending the subjective policy message that there needs to be an ‘all hands on deck’ approach to getting projects sited in the commonwealth.”

The legislation also includes funding that would help community organizations participate in EFSB and Department of Public Utilities proceedings. It would require developers to submit a cumulative impact analysis (CIA) intended “to evaluate and minimize the impacts of large clean energy infrastructure facilities in the context of existing infrastructure and conditions.”

While the CIA requirement has been a key priority of environmental justice advocates in the state, some have expressed concern the language included in the House and Senate bills is inadequate.

John Walkey, of the environmental justice group GreenRoots, said advocates are concerned the CIA definition will fail to include “a holistic consideration of all the factors that go into how environmental burdens are sited and experienced.”

“As we get ready for the conference committee, the CIA definition is still falling short,” Walkey said. “We hope that in the few opportunities that remain, the language will see the small adjustments needed to bring it in line with established practice.”

The changes also include provisions intended to contain costs associated with new electric transmission and distribution infrastructure. Developers would be required to consider advanced transmission technologies to receive approval. (See Panelists Call for a More Holistic Approach to Advanced Transmission Tech in Mass.)

Gas utilities would be required to consider “non-pipeline alternatives, the repair or retirement of pipelines, and other alternatives” to minimize costs when evaluating solutions to system needs.

Significant Differences

There are some significant differences between the two versions of the bill, with the Senate taking a more aggressive approach to phasing out gas infrastructure.

In approving requests for gas service, the Senate bill would direct the DPU to review climate impacts and whether there are other viable alternatives to gas heating. It would authorize gas utilities to submit decommissioning proposals for portions of the gas system and terminate gas service to customers along these segments, as long as customers receive “continuous access to safe, reliable and affordable energy services,” shifting their obligation to provide gas service to residents to an obligation to provide thermal energy services.

The bill also would require annual filings from the gas distribution companies “to ensure each gas company is meeting the appropriate pace to preserve and improve public safety, improve infrastructure reliability, minimize the risk of stranded assets and reduce greenhouse gas emissions.”

“The Senate’s provisions on the gas system are really important,” said Kyle Murray of the Acadia Center, adding they would “give the DPU the tools necessary to pursue an ordered transition off of natural gas.”

Caitlin Peale Sloan of the Conservation Law Foundation said the Senate bill includes “important early steps that we could put in place now” to help decarbonize the gas system while limiting long-term costs to ratepayers.

“Nothing in this space happens quickly — ever — so that’s why it’s important to be taking action now,” Sloan said.

Other components of the Senate bill include a ban on third-party competitive electric suppliers in the state, additional funding for electric vehicle rebates, provisions intended to increase access to EV charging and a requirement for the Massachusetts Bay Transportation Authority to fully electrify commuter rail service in the state by 2030.

In contrast, the House bill largely sidesteps the issue of gas system decommissioning and would not ban the practice of competitive residential electricity supply in the state.

Instead, it focuses on promoting energy storage and would direct electric utilities to pursue competitive solicitations for up to 5,000 MW of energy storage, including 750 MW of long-duration storage (between 10 and 24 hours) and 750 MW of multiday storage (greater than 24 hours).

The bill also includes language to promote advanced metering infrastructure, scale up a network of fast EV charging hubs across the state and create a study into the “feasibility of the electric vehicle-only sales mandate, which becomes effective in 2035.”

Both bills also include provisions that would enable additional procurement of clean energy. The House bill would authorize long-term contracts (up to 30 years) for up to 9,450 GWh of clean energy, while the Senate bill would give the Department of Energy Resources broad discretion to procure clean energy as needed to meet the state’s statutory climate targets.

Despite the differences in the bills, top legislators from the House and Senate have indicated they expect to reach some compromise by the end of the session.

“These are long bills; it will be interesting to see what shakes out,” Sloan said. “It’s still just the tip of the iceberg of what needs to be done on climate.”

Dam It! How the Hydro Industry and Environmental Groups Found Common Ground

It was 2018 and the hydropower industry and environmental and tribal advocates had battled themselves to a political stalemate, recalled Kelly Catlett, hydropower reform program director with the nonprofit American Rivers.

The environmental and tribal groups had enough votes in Congress to kill any bill supported by the industry, which likewise had the votes to kill any bills being advanced by the environmental and tribal groups, Catlett said during a July 18 briefing on how the opposing sides came together to find common ground through an “Uncommon Dialogue.”

“We weren’t getting anything done,” Catlett said. “We didn’t have open lines of communication. We didn’t understand each other’s perspective.”

While frequently discounted as renewable energy, hydropower accounts for close to 30% of carbon-free generation in the U.S., and unlike wind and solar, can provide dispatchable, flexible generation. According to the National Hydropower Association (NHA), hydro makes up just over 6% of U.S. power generation but provides 40% of the nation’s black start capacity.

At the same time, hydro comes with a legacy of concerns about its impacts on the environment and tribal land and fishing rights, on top of the usual permitting challenges, all of which have raised multiple obstacles to maintaining and expanding hydro and hydro pumped storage in the U.S.

Convened by Stanford University’s Woods Institute for the Environment, the Uncommon Dialogue on hydro aimed to change the adversarial dynamics of hydropower development, with a series of meetings where industry and environmental groups, government officials and academics could talk and listen to each other and build trust.

Participants included river advocates American Rivers and American Whitewater, the NHA, Natel Energy, a developer of fish-friendly hydropower turbines, and the U.S. Department of Energy, in an observer role.

“Where we [found] common ground is when we started thinking about it as dams,” said Malcolm Woolf, president and CEO of the NHA, noting that only 3% of the more than 90,000 dams in the United States produce electricity. The other 97% were “built for flood control, for irrigation, for water storage, for navigation, sometimes for recreation.

“By focusing on dams … we’re able to talk and make progress, I hope, both on carbon-free generation and river restoration,” he said.

The result, in 2020, was a joint statement from dialogue participants identifying seven areas for ongoing collaboration, including improving hydropower technologies to increase generation efficiency and output, improving dam safety and river restoration and accelerating licensing and relicensing of dams and pumped storage hydro facilities.

Moving forward on those points of collaboration has become increasingly important as a growing number of U.S. hydroelectric dams are up for relicensing ― a long and expensive process ― and many hydro dam operators consider surrendering their licenses, rather than contend with the cost and uncertainties of relicensing, Woolf said.

Either licensing or relicensing can take seven years or, in some cases, decades, he said. “You don’t know how long it’s going to take. You don’t know what’s going to be required, and so every part of the process creates uncertainty and prevents people from investing in modernizing their existing fleet or building more.”

No new dams or pumped storage hydro have been built in 20 years or more, he said, and according to DOE, between 2010 and 2022, 68 hydro projects totaling 322 MW surrendered their licenses.

Bills Supported but Stalled

Given the current deep divisions in Congress, continuing the work of the Uncommon Dialogue also has become essential on the policy front, Catlett said.

A broad range of industry and environmental groups support a set of bills aimed at maintaining and expanding hydro in the U.S. The bills were introduced in Congress last year, with both Democratic and Republican sponsors.

The Maintaining and Enhancing Hydroelectricity and River Restoration Act (S. 2994/H.R. 6653) seeks to provide existing hydro projects with the same kind of tax credits the Inflation Reduction Act offers to new hydro projects and other renewable or carbon-free power. Under the bill, a 30% tax credit would be available for hydroelectric projects that improve safe passage for fish, dam safety, water quality and public uses of and access to public waterways. The tax credit also would be available for projects that add power generation to an existing nonpower dam.

On the permitting side, separate and slightly different bills also were introduced in the House and Senate.

The Hydropower Clean Energy Future Act (H.R. 4045) officially defines hydro as renewable energy “for purposes of all Federal programs” and allows FERC on a case-by-case basis to exempt small hydro projects of less than 40 MW from some or all licensing requirements.

The bill also would give FERC a two-year cap on licensing for any hydropower or pumped storage projects deploying “next-generation” hydro technologies, for example, run-of-river hydro or technologies that “protect, mitigate, or enhance environmental resources, that [are] not in widespread, utility-scale use in the United States.”

In the Senate, the Community and Hydropower Improvement Act (S. 1521) puts a two-year cap on permitting for the addition of hydropower to existing dams and a three-year limit for licensing of closed-loop or off-stream pumped storage projects. The bill includes provisions that make engagement with tribal governments mandatory for hydro or pumped storage projects located on tribal lands and create a pathway for tribes to submit recommendations to FERC on the protection of fish and wildlife habitats.

While H.R. 4045 has been voted out of committee to the House floor, the other bills have not moved forward since their introduction last year.

Pivotal role

The U.S. Energy Association sponsored the July 18 event, and Woolf, a fervent proselytizer for hydro, came armed with facts and figures about the pivotal role NHA sees hydro playing in the energy transition.

Hydro generation powers 30 million American homes and businesses, while also providing flexible, dispatchable power for grid support services. Hydro pumped storage makes up 96% of the nation’s long-duration energy storage.

“It’s 80 GW of hydropower capacity and another 22 GW of pumped storage; so, it’s over 100 GW of largely dispatchable, flexible, carbon-free generation, and that’s in the United States,” Woolf said. Globally, hydropower produces more energy than all other renewables combined, he said.

Hydropower capacity in the U.S. has expanded slowly in recent years, due primarily to upgrades at existing projects or the addition of power generation to previously nonpower dams, according to the Department of Energy’s 2023 Hydropower Market Report.

From 2010 to 2022, about 2.1 GW of new hydro capacity came online, 75% of which was nonpower dam retrofits. New projects, however promising, move slowly.

At the end of 2022, the U.S. had 117 new hydro facilities in the development pipeline, but only eight were under construction, and 95% of the projects were nonpower dam retrofits, according to DOE. The pumped storage pipeline included 96 projects, only 10 of which have advanced beyond basic feasibility studies. Three had received permits from FERC; none were under construction.

The two Cushman dams in Washington state provide a case study on the challenges of hydropower relicensing, said Mary Pavel, a partner at Sonosky, Chambers, Sachse, Endreson & Perry LLP and a member of the Skokomish Tribe. When the dams originally were permitted back in the 1920s, her tribe’s fishing rights largely were ignored, and tribal access to the Skokomish River and fishery essentially were wiped out, Pavel said.

Sockeye salmon disappeared from the river for decades, which she called “an act of genocide.” Dams like the Cushman are “stealing” energy, Pavel said. “You’re stealing energy that’s necessary for my fishery resource, my wildlife resources or my cultural resources or my aquatic resources. That energy is there for a reason.”

Relicensing the dams took over 30 years and ended with a settlement between the tribe and Tacoma Public Utilities, which included a $50 million project to return salmon to the river, along with the return of tribal lands and cash payments totaling about $35 million, according to local media reports.

Both Catlett and Woolf agreed the era of building large dams is over, in part because the best sites already are developed. But Catlett said intensive community engagement will be critical to ensuring the mistakes of the past are not repeated.

“We need to be designing projects to avoid aquatic ecosystem impacts and impacts to the communities in which they are situated and think a little deeper about these projects and the way they are going to interact with the communities around them,” she said.

NJ Backs New Gas Plant, Sparks Opposition Anger

In a test of New Jersey’s new environmental justice law, the state Department of Environmental Protection (DEP) has concluded that a controversial proposal to build a gas–fueled generating plant in Newark can move forward, despite the high density of other emissions-generating plants in the area. 

The agency, in a decision released July 18, said the plant’s originators, Passaic Valley Sewerage Commission (PVSC), had agreed to include in its plan measures to curb emissions and use limits that would allow the plant to operate only 288 hours a year for testing and maintenance, unless an emergency forced its use. 

Because the DEP’s decision requires the sewerage commission, if it goes ahead with the plan as expected, to install pollution controls on existing equipment at the facility, the state’s action “will result in a net overall reduction of air pollutant emissions,” said Commissioner Shawn M. LaTourette at a briefing as the DEP released the decision. 

“This is a precedent-setting action,” he said, referring to the way the law was used to cut emissions across the facility.  “We believe that this is the kind of result that our environmental justice law was intended to achieve. It’s one that not only avoids casting more pollution upon an overburdened community, but also improves upon the existing conditions by reducing pollution that our neighbors are already experiencing.” 

Yet the DEP’s action immediately triggered vigorous pushback from environmentalists and local lawmakers, who have been fighting to stop the project for years. 

Food and Water Watch NJ called it an “absolute betrayal to Newark residents” and said the decision “completely undermines” Democratic Gov. Phil Murphy’s “own commitment to protect environmental justice communities and take meaningful climate action.” 

“Toxic air pollution from power plants and congestion have plagued our communities for decades, resulting in higher instances of asthma, cancer, cardiovascular disease and developmental disorders,” said state Sen. Renee C. Burgess (D), in a release put out by six legislators. “Just when we thought there was marked progress in combating the new development of these harmful facilities, DEP fails us.” 

Competing Goals

The debate underscores the difficulties of the state’s efforts to aggressively cut emissions while ensuring the state has access to enough electricity to meet its needs. In this case, the DEP also sought to balance competing public health concerns: those of the local community that would be affected by emissions from the plant and the threat if the lack of electricity during a disaster meant untreated sewage ran into area waterways. 

PVSC, which handles sewage from 48 municipalities and is the sixth-largest waste handling agency in the nation, conceived of the plant after Superstorm Sandy severely flooded the agency’s plant. The emergency shut down the main and backup power sources needed to treat wastewater and triggered the release of 840 million gallons of raw sewage into the nearby Passaic River and Newark Bay. 

In response, PVSC seeks to build an on-site emergency standby power generating facility (SPGF) with three 24-MW natural gas combustion turbine generators (CTGs) that is intended to provide power in case of a similar emergency. 

The commission’s application said the plant would be used only 3.5 hours a day or 1,285 hours a year. The commission predicted it would use the combustion turbine generators (CTGs) 480 hours a year for storm preparation, 300 hours a year for testing and maintenance, and 24 hours a year for “demand response” during peak hours to offset load. The DEP said PVSC had explored using electricity provided by solar, wind and battery systems to provide emergency backup, but found it would not be feasible, due mainly to onsite space limits.  

The DEP’s decision does not grant permission for the plant, but it does specify conditions in the project as it now advances through the DEP’s environmental permitting process. As part of the process, which is expected to take six months, the DEP will compile a draft permit for review by the federal government prior to the state making a final permit decision. 

The DEP reviewed PVSC’s plan under an environmental justice law that took effect in June 2023 triggered largely by concerns that communities — especially with a proportion of low-income residents, and those of color — were not being heard in decisions over environmental issues and were, as a result, heavily burdened by polluting facilities.  

Murphy, in backing the law, called it a “historic step” that made the state “home to the strongest environmental justice law in the nation.” The law requires applicants seeking to build potentially polluting facilities to dig deeper into the density, history and emissions of other facilities into the area and identify stressors on the community from any proposed facility and the impact on residents.  

The PVSC project is the last of three gas-generating plants that until recently were proposed for North Jersey. In October, Competitive Power Ventures (CPV) withdrew its plans for a 630-MW gas-fired generating plant Woodbridge, and in January, NJ Transit dropped plans for a 140-MW emergency resilience gas generator in Kearny. (See New Jersey Abandons Controversial Gas Generation Plant.) 

Special Requirements

The DEP’s 16-page decision allowing the PVSC project to “proceed with its proposed permit modification” says the agency’s environmental justice review “has ensured the imposition of special conditions that result in a net overall reduction of facility-wide emissions of air pollutants under regular operating conditions.” 

“I don’t expect anyone to praise this outcome,” LaTourette said. “That’s not the business we’re in. … But (it’s) rather to achieve a result that best protects public health and the environment.” 

The EJ law enabled the DEP to look “beyond the single source of pollution …. and to look broader at the facility as a whole, to achieve facility-wide reductions in pollution,” LaTourette said. “That additional oversight and authority has resulted in multiple new requirements for PVSC to reduce its existing pollution.” 

The requirements, which must be adhered to in the permitting process, included: 

    • limiting the plant’s use — to 48 hours before a storm, to no more than 10 times a year, to emergency “act of God”-type events, and to once a month for maintenance and testing 
    • air pollution control measures — PVSC must remove several existing gas boilers and install state-of-the-art pollution control equipment on four sludge boilers 
    • solar — the agency must install at least 5 MW of solar panels at the facility by the end of 2026 
    • storage — the agency must install at least 5 MW of battery storage capacity at the facility 
    • alternative fuels — the agency must “initiate the transition” of the burners to natural gas or green hydrogen in the near future. 

Community Impact

Lawmakers who represent districts that would be impacted by plant emissions demanded a reversal of the decision and highlighted the state’s history of putting polluting facilities in the Newark area. The city is already home to four electricity-generating plants, and pollution levels are elevated by truck traffic on several highways, much of it serving the Port of New York and New Jersey, which also is in Newark. 

State Sen. M. Teresa Ruiz (D) called the decision “an indefensible and hypocritical decision that blatantly violates New Jersey’s environmental justice law.” 

“It disregards the well-being of Newark residents who have long borne the brunt of toxic air pollution and negative health outcomes from nearby power plants built in their communities to shield more affluent areas from its harmful effects,” she said. “The administration cannot pat itself on the back for pioneering environmental justice policies and promoting environmental education in schools while continuing to harm the environment and the health of its most vulnerable residents.” 

State Briefs

ARIZONA 

Strata Clean Energy Enters BESS Agreement

Strata Clean Energy has announced it has secured a 20-year tolling agreement with Arizona Public Service for its 150-MW Justice Energy Storage project in Phoenix. The project is expected to be completed in April 2026. 

More: Energy Global 

GEORGIA 

Plant Vogtle’s Unit 3 Back Online After Valve Issue

Unit 3 at Plant Vogtle, which had been offline since July 8 due to a “valve issue,” is back online, Georgia Power said. The unit was shut down after a valve malfunctioned on one of the pumps that supplies “feedwater” to the steam generator, the company said. Feedwater removes heat from the reactor and is used to produce steam, which spins the generator’s turbines to create electricity. 

More: The Atlanta Journal-Constitution, The Telegraph 

ILLINOIS 

Plan to End Natural Gas Hookups Dies on City Council Desk

Chicago Mayor Brandon Johnson’s proposal to end natural gas connections in new homes and buildings is dead after a majority of council members opposed the idea. 

Johnson’s climate-fighting initiative, the Clean and Affordable Buildings Ordinance, is sitting in the council’s Rules Committee and doesn’t appear to be moving after at least 31 alderpersons signed a public statement opposing the plan. 

The plan largely would ban new gas hookups for cooking, heating and hot water tanks and require electric power for new construction, including homes and large additions. 

More: Chicago Sun-Times 

State Establishes Moratorium on CO2 Pipelines

Gov. JB Pritzker has signed legislation that will establish a two-year moratorium on the construction of carbon dioxide pipelines. 

The moratorium would run until July 2026 or when the federal Pipeline and Hazardous Materials Safety Administration adopts revised safety regulations, whichever comes first. The law also requires pipeline companies to show their pipelines will lead to net reduction in climate pollution and don’t add co-pollutants in the atmosphere. 

The bill passed the House (78-29) and the Senate (43-12) along party lines. 

More: Springfield State Journal-Register 

LOUISIANA 

Appeals Court Sends LNG Terminal Project Back to FERC

The U.S. Court of Appeals for the D.C. District has determined FERC did not adequately assess the cumulative and direct environmental and health impacts from the Commonwealth LNG terminal and will have to reconsider its review. 

FERC originally approved the project in November 2022. Commonwealth’s plan calls for construction to begin on the 150-acre site on the Calcasieu Ship Channel in the first half of 2025 and LNG production to start by the end of 2028. 

Neither FERC nor Commonwealth immediately commented on the ruling. 

More: Louisiana Illuminator 

MASSACHUSETTS 

DEP Says Holtec Can’t Dump Nuclear Wastewater into Cape Cod Bay

The Department of Environmental Protection said Holtec, the company decommissioning the former Pilgrim Nuclear Power Station, cannot discharge the wastewater into the Cape Cod Bay because is protected under the Ocean Sanctuaries Act. 

Holtec had hoped to dump 1.1 million gallons of treated water into the bay. The water had been used to cool spent nuclear fuel rods. The process is legal and deemed safe provided the water does not exceed radioactivity levels set by the Nuclear Regulatory Commission. 

Pilgrim went offline in 2019, and Holtec has begun the process of dismantling the plant and cleaning up the property. 

More: WBUR 

House Approves Bill to Boost Renewable Efforts

The House has approved a bill that will help boost the state’s reliance on renewable energy by streamlining the state and local permitting process for projects that shift away from fossil fuels. 

The measure would consolidate both state and local permitting and set 12- to 15-month limits for considering all final permitting decisions. It also calls for procuring additional clean energy resources and allows future offshore wind and clean energy contracts to be extended up to 30 years. 

The bill’s approval comes just weeks after the Senate approved its own bill to help the state meet its climate goals, including reaching net zero greenhouse gas emissions by 2050. 

More: The Associated Press 

PENNSYLVANIA 

Pittsburgh Officials Find No Evidence of Natural Gas Equipment Causing Rustic Ridge House Explosion

The Public Utility Commission Safety Division has found no evidence linking public utility natural gas equipment to an August 2023 house explosion in Allegheny County. Six people were killed, several others were injured and three homes were destroyed because of the explosion. 

More: KDKA 

TEXAS 

Restaurants Sue CenterPoint over Hurricane Beryl Response

Houston-area restaurants have filed a class action suit seeking more than $100 million from CenterPoint Energy, alleging incompetence and negligence in the utility’s efforts to restore power quickly following Hurricane Beryl. Tony Buzbee, a lawyer on behalf of the plaintiffs, said the case makes claims for negligence and gross negligence for “CenterPoint’s repeated failure to do what any reasonable and competent electricity provider would do and should do.” 

More: The Dallas Morning News 

Company Briefs

Clean Grid Alliance Welcomes Former Iowa Legislator Brown

Clean Grid Alliance has announced former Iowa Sen. Waylon Brown (R) will join the alliance as regional policy manager. Brown served in the Iowa Senate from 2017 to July 2024 leading the Commerce Committee, which oversees energy policy. 

More: Clean Grid Alliance 

SunPower Stock Collapses as Company Halts Leases, Installations, Shipments

SunPower’s stock collapsed 70% after the company informed dealers it no longer will support new leases, installations or product shipments, with analysts saying the company is on the verge of going out of business. 

SunPower stock has lost nearly all its value in the past 12 months, with the shares down 93% to trade at 79 cents on July 19. Guggenheim Securities has slashed its price target to $0 from $1. 

One analyst said the decision to effectively suspend operations is the result of SunPower’s weakened cash flow and balance sheet, as well as its inability to tap capital markets because the company is not current with the Securities and Exchange Commission. 

More: CNBC 

Woodside Doubles down on US, LNG with Tellurian Takeover

Australia-based Woodside Energy said July 22 that it intends to acquire Tellurian and its proposed LNG development in the southern U.S. for about $900 million. 

Tellurian owns the planned Driftwood LNG development near Lake Charles, La. Woodside said Tellurian’s directors support the transaction and that it aims to complete a deal in the final three months of 2024. 

The deal for Tellurian deepens Woodside’s commitment to the U.S., where it majority owns the Shenzi oil-and-gas field, about 120 miles off the coast of Louisiana.  

More: The Wall Street Journal 

Federal Briefs

DC Circuit Allows EPA Rule on Coal-fired Plants to Remain

The D.C. Circuit Court of Appeals has ruled that a new EPA regulation aimed at limiting carbon emissions from coal-fired power plants can stay in place. 

A three-judge panel rejected the request to block the rule, saying the groups had not shown they are likely to succeed on the merits. The judges also rejected the claim of immediate harm, saying compliance deadlines do not take effect until 2030 or 2032. 

Industry groups and some Republican-led states had asked the court to block the rule on an emergency basis, saying it was unattainable and threatened reliability of the nation’s power grid. The rule, announced in April, would force many coal-fired plants to capture 90% of their carbon emissions or shut down within eight years. 

More: The Associated Press 

EPA on Deadline to Spend on Climate Grant Program

EPA has until Sept. 30 to spend $27 billion to reshape impoverished areas of the U.S. by financing the installation of renewable energy and improving buildings’ energy efficiency. 

However, the initiative has a shoestring operating budget, and the program is facing charges of empty oversight and potential waste — and the prospects of a Republican feeding frenzy over the Inflation Reduction Act if the program stumbles. Analysts say out of all the programs authorized in the IRA, this one has the smallest amount of money allotted to hire staff and track spending. 

EPA has chosen 68 entities to use the money to underwrite projects. The agency is negotiating contracts with those recipients and has promised the money will be delivered before the IRA’s deadline. 

More: POLITICO 

Washington Man Arrested, Charged for 2022 Attacks on Oregon Facilities

Zachary Rosenthal, 33, from Tacoma, Wash., has been arraigned on federal charges for allegedly damaging two energy substations in Oregon in November 2022. 

Rosenthal is accused of damaging the Sunnyside Substation in Clackamas and the Ostrander Substation in Oregon City. The attacks were part of a national series of attempted disruptions to the grid that law enforcement warned had possible ties to extremist groups. Justice Department officials have not said if they have identified a motive. 

More: Oregon Public Broadcasting 

EPA Announces $4.3B in Climate Pollution Reduction Grants

Pennsylvania will use its $396.1 million Climate Pollution Reduction Grant (CPRG) on a statewide initiative to cut greenhouse gas emissions from industrial buildings through incentives for energy efficiency and emission-reduction technologies. 

Montana’s plan for its $49.7 million CPRG will focus on improving forest management across the state, expanding urban and community forests, mitigating wildfires and coal seam fires, and reducing pollution from agriculture. 

And in Connecticut, New Haven will get $9.4 million to build a networked geothermal system that will provide clean power and heat to Union Station, the city’s transit hub, with carbon-free electricity also going to a neighboring mixed-income housing development. 

EPA on July 22 announced these and 22 other projects that have been selected to receive more than $4.3 billion in CPRG funds from the Inflation Reduction Act, all aimed at reducing emissions, promoting clean energy and creating jobs. 

Announcing the grant awards at a concrete and asphalt plant in Pittsburgh, EPA Administrator Michael Regan said the federal dollars will “fund investment-ready projects targeting climate pollution from transportation, the electric power sector, commercial and residential buildings, industry, agriculture, natural lands, [and] waste and materials management. … These investments are going to change lives.” 

Combined, the 25 projects could reduce U.S. GHG emissions by 971 MMT by 2050, which, according to EPA, is the equivalent of the emissions from the energy used by 5 million average U.S. homes per year for more than 25 years. 

The IRA funds will “empower local ownership … and local solutions to help solve a global problem,” John Podesta, White House senior adviser on climate innovation and implementation, said during an advance press call July 19. “The climate crisis looks different in every community, from Colorado to Connecticut to Lincoln, Nebraska. More bike lanes and public transit may be the best way for one city to reduce emissions, and making a local steel plant more energy efficient might be the best path for another.” 

Lincoln Mayor Leirion Gaylor Baird agreed. “Local initiatives, when combined with federal funding, can transform ideas into tangible solutions,” she said. 

“Here in Lincoln, the planning phase of this grant program showed us that some of the greatest opportunities for emission reductions lie in enhancing the energy efficiency of homes and commercial buildings. Our analysis indicates that investing in energy efficiency and electrification could reduce Lincoln’s emissions by a whopping 77% from our baseline metrics by the year 2050.” 

The money also will be used for “critical home repairs for low-income members of our community” as part of the city’s efficiency and electrification efforts, she said. 

Lincoln’s programs are just one element of Nebraska’s plans for its $307 million in CPRG funding. The money also will go toward accelerating the adoption of climate-smart and precision agricultural practices and reducing agricultural waste from livestock. 

Precision agriculture uses digital tools and automation to improve farming efficiency and crop yields. 

EPA received nearly 300 applications for the grants, with funding requests totaling $33 billion, Regan said July 19. The 25 awardees were “the cream of the crop,” with projects offering “maximum penetration of greenhouse gas pollution reduction. But also, we wanted to be sure we saw the diversity across various industries, whether it be transportation, building, agriculture [or] the power sector.” 

Community benefits and job creation were additional priorities in evaluating applications, he said. “We have a very stringent program. These recipients also have demonstrated that not only could they identify the pollution reduction targets, but they could put metrics in place to prove it.” 

The CPRG funding contains an additional $300 million for emission-reduction projects submitted by tribes and territories, to be announced this year. 

Asked if the grants announced July 22 could be affected by a change in administration, Regan said all the funds would be “obligated” to the awardees by early fall, once all legal and administrative requirements are met. 

“We know these recipients are ready to receive these dollars and will be off to the races immediately,” he said. 

State Climate Plans

The grant announcements are the second phase of the CPRG program, which began last year, when EPA awarded $250 million in noncompetitive IRA funds to help state, city and tribal governments develop climate plans. Individual grants ranged from $1 million to $3 million. 

Plans were due March 1 for states and cities and April 1 for tribes and territories. 

Forty-five states and dozens of cities and tribes ― covering 96% of the U.S. population ― now have plans in place, according to EPA. While five states ― Florida, Iowa, Kentucky, South Dakota and Wyoming ― did not submit plans, cities in those states did. Rapid City, S.D., and Cheyenne, Wyo., submitted plans, as did Des Moines, Cedar Rapids and Iowa City in Iowa. 

Updated, comprehensive plans will be due around the middle of 2025, according to EPA. 

The second-phase grants are intended to help a small group of states and cities implement those plans and provide models that other states, cities and businesses can replicate. 

Pennsylvania Gov. Josh Shapiro, joining Regan in Pittsburgh, said the state’s $396.1 million CPRG is the second-largest federal grant in its history and will be used for its Reducing Industrial Sector Emissions in Pennsylvania (RISE-PA) program. 

Administered by the state’s Department of Environmental Protection, RISE-PA will issue grants “to manufacturing companies across this commonwealth,” Shapiro said. “These grants can be used for … improving energy efficiency, reducing emissions, implementing carbon capture … and replacing equipment with electric power options,” such as swapping out coal-powered smelters used to make steel for electric smelters. 

“I have always said we have got to reject the false choice between protecting our planet and protecting our jobs,” Shapiro said. “We can and we must do both.” 

Multistate and Regional Projects

Other award winners included several multistate and regional projects. 

Maine, New Hampshire, Connecticut, Massachusetts and Rhode Island are partnering on a New England Heat Pump Accelerator, which snagged $450 million, one of the largest grants announced. In states heavily dependent on winter heating oil, the project aims to install cold-climate air-source heat pumps, heat pump water heaters and ground-source heat pumps in 500,000 single-family and multiunit homes. 

New Jersey, Connecticut, Delaware and Maryland have formed the Clean Corridor Coalition, which will receive $248.9 million to install electric charging stations for medium- and heavy-duty trucks along Interstate 95, a major East Coast freight route. 

Maryland also is part of the Atlantic Conservation Coalition, joining Virginia and the Carolinas for a $421.2 million grant to be used to restore coastal habitats and peatlands, plant trees and improve forest management in Appalachia. 

The state’s slice of the two projects will total about $130 million, according to a press release from Gov. Wes Moore (D). 

“It isn’t enough to ask people to see themselves in the consequences of climate change — they also need to see themselves in the progress of climate action,” Moore said. “By moving in partnership with leaders at the local, state and federal levels, we are creating new green jobs, driving economic growth and building new pathways to prosperity for all, while protecting our planet.” 

PJM Presents Revised Reserve Requirement Study Values

PJM presented its Planning Committee with revisions to the 2023 Reserve Requirement Study (RRS) to reflect the marginal effective load-carrying capability (ELCC) analysis approach the RTO uses for most resource accreditation.

During the July 16 special meeting, PJM’s Patricio Rocha Garrido said the results of the reanalysis recommend increasing the installed reserve margin (IRM), which sets the targeted capacity level above expected loads, to 18.6%, up from the 17.6% stakeholders endorsed in the original study last year. The forecast pool requirement (FPR), which accounts for generator accreditation, would decrease from 11.65% to 9.37%. (See “Stakeholders Endorse Reserve Requirement Study Values,” PJM PC/TEAC Briefs: Oct. 3, 2023.)

The majority of resource classes saw a relatively minor change between their 2025/26 ELCC ratings and the 2026/27 target year for the 2023 RRS, with most increasing or decreasing within 2%. Gas combustion turbines saw the largest change, increasing 6% due to the number of CTs that have announced their deactivation. The overall impetus for rating changes across resource types was a small shift toward risk being concentrated in the winter.

The new values are being brought to the July 24 Markets and Reliability Committee and Members Committee meetings for a same-day first read and endorsement vote.

The marginal ELCC approach was one of several capacity market redesigns drafted through the Critical Issue Fast Path (CIFP) process last year and approved by FERC in January 2024. (See FERC Approves 1st PJM Proposal out of CIFP.)

The CIFP filing also revised three formulas central to the RRS analysis, including:

    • calculating the IRM by reducing total installed capacity (ICAP) by the capacity benefit of ties (CBOT);
    • determining the FPR by multiplying the IRM by the pool-wide average accredited unforced capacity (UCAP) factor, rather than forced outage rates; and
    • making the average accredited unforced capacity (UCAP) factor the ratio of UCAP to installed capacity (ICAP).

Stakeholders endorsed an earlier round of revisions to the RRS to reflect the impact of those design changes earlier this year. (See “Revised Reserve Requirement Study Values Endorsed,” PJM MRC/MC Briefs: March 20, 2024.)

Garrido said PJM also updated the assumed resource mix to include planned resources that submitted a notice of intent to offer into the 2026/27 Base Residual Auction. Gas generators that submitted dual fuel attestations were sorted into the corresponding ELCC classes, and resources that are scheduled to deactivate prior to the start of the delivery year were removed from the analysis. Generators expected to operate on reliability-must-run (RMR) contracts through the delivery year were included in the resource mix.

Paul Sotkiewicz, president of E-Cubed Policy Associates, said some RMR contracts do not require the generator to respond to PJM capacity deployments and should not be included in the resource mix.

“I think we’re actually overstating the amount of capacity that’s going to be there,” he said, adding it would distort market signals.

Sotkiewicz also questioned the assumption that outside capacity could be available for import during emergencies, saying that PJM has been exporting consistently during “emergency events and high load days.”

Garrido said PJM aims to model the system as it’s expected to exist in the target delivery year and that RMR resources should be included if they’re contracted to remain in operation. He stated any impact on the reliability requirement would be small.

NERC Submits Final Performance Assessment

NERC has submitted its final performance assessment to FERC, reviewing a turbulent five years in which NERC managed “significant collaboration” among the ERO Enterprise, stakeholder groups and government authorities that “resulted in high and improving grid performance.” 

The performance assessment covers the years 2019 to 2023, a period that saw the outbreak of the COVID-19 pandemic, several major severe weather incidents, the emergence of serious cybersecurity threats to multiple aspects of the electric grid and the ongoing shift from traditional thermal generation to renewable resources.  

In the report, NERC sought to highlight “the continued viability and effectiveness of the ERO model” at using “broad technical expertise across diverse stakeholder groups and [ensuring] the independence and agility required to advance reliability in a changing world.” 

FERC regulations require NERC to file an assessment of its performance every five years as a prerequisite to recertifying it as the ERO, and the commission approved the last assessment in 2020. (See NERC Wins Another 5 Years as ERO.) Three years ago, FERC floated a proposal to shorten this timeline to three years, but the commission withdrew the proceeding this year after NERC and the regional entities warned that a three-year assessment cycle might not allow it to conduct the same level of review that the current schedule allows.  

NERC posted a draft of this report in April, seeking stakeholder comments. (See NERC Makes Case for Recertification in Performance Assessment.) The finished assessment, filed July 19, “reflects feedback from [regional entities], industry stakeholders and commission staff,” NERC said, along with input gathered from stakeholders throughout the assessment period.  

In the final assessment, NERC focused on its accomplishments through four key areas: 

    • Energy: addressing challenges arising from the changing resource mix, providing sufficient energy and essential reliability services, improving system performance during extreme weather and adding transfer capability; 
    • Security: addressing cyber and physical security risks; 
    • Agility: becoming nimbler in risk identification and standards development; and 
    • Sustainability: investing in automation, eliminating single points of failure, and strengthening the ERO Enterprise’s long-term stability and success. 

The organization devoted a significant part of the report to its internal development and efforts to modernize and streamline its committee structure. These include the creation of the Reliability and Security Technical Committee in 2020 through the combination of several existing committees and the Regulatory Oversight Committee in 2023 to give NERC’s Board of Trustees “committee-level oversight of standards development.”  

NERC also discussed its efforts to improve cyber and physical security across the ERO Enterprise. It said that during the assessment period, it “zeroed in on structural cybersecurity challenges” to the grid, including supply chain vulnerabilities and information technology and operational technology system monitoring.  

In addition, the ERO highlighted its work developing the Energy Information Sharing and Analysis Center (E-ISAC), which “continues to play a vital role in securing the [grid] through sharing information on cyber and physical security threats and vulnerabilities with industry members, the vendor community, and government and cross-sector partners.” 

NERC received a single comment from the Edison Electric Institute, which it posted as an appendix to the assessment. EEI suggested that “it would be helpful if the [final] assessment explored the use and value of [self-certification and spot checks as] alternatives to full on-site audit engagements.” In response, the ERO asserted that it “has increased its use of self-certification and spot checks to support compliance monitoring and intends to continue to significantly leverage those methods.” 

NERC said that during the first quarter of this year, only 15% of its compliance monitoring engagements used full on-site audits. Among such engagements, 77% used self-certifications, while 8% used spot checks. NERC pledged to “continue coordinating across the ERO Enterprise to support consistent rationale in tool selection through its risk-based approach to” compliance monitoring and enforcement. 

Manchin-Barrasso Permitting Bill Would Give FERC Transmission Siting Authority

Sens. Joe Manchin (I-W.Va.) and John Barrasso (R-Wyo.) on July 22 introduced long-planned legislation on energy project permitting that would increase FERC’s power to approve new electric transmission.

The two senators are chairman and ranking member, respectively, of the Senate Energy and Natural Resources Committee, and their Energy Permitting Reform Act of 2024 is meant to accelerate the permitting process for critical energy and mineral projects of all types.

“The United States of America is blessed with abundant natural resources that have powered our nation to greatness and allow us to help our friends and allies around the world,” Manchin said. “Unfortunately, today our outdated permitting system is stifling our economic growth, geopolitical strength and ability to reduce emissions.”

Manchin said that after more than a year of hearings and negotiations, he and Barrasso put together a bill that is meant to provide more certainty for energy and mineral projects going through the permitting process without bypassing protections for the environment and impacted communities.

“For far too long, Washington’s disastrous permitting system has shackled American energy production and punished families in Wyoming and across our country,” Barrasso said. “Congress must step in and fix this process. Our bipartisan bill secures future access to oil and gas resources on federal lands and waters.”

The bill would end President Joe Biden’s pause on processing natural gas exports, which already was stayed by a federal court decision. (See Federal Judge Stays Biden’s LNG Export Application.)

On electric transmission, it would reform the existing backstop siting authority for interstate transmission lines and require interregional transmission planning.

The law would also let transmission developers ask FERC for permission to site lines that are in the national interest, in a process similar to how the commission sites natural gas pipelines. The lines have to be used in “interstate commerce,” which includes connecting offshore wind on the outer continental shelf to a state. States still would get one year to respond to siting applications before firms can go to FERC for siting.

FERC would have to find that such transmission lines are in the public interest, would cut congestion, benefit consumers and provide improved reliability. The transmission lines FERC sites would have to be consistent with national energy policy and enhance energy independence.

States, tribes, private property owners and other interested parties would have to have a reasonable opportunity to present their views and recommendations on transmission siting before FERC, the bill said.

FERC also would have to approve proposals for allocating the costs of such lines to beneficiaries of the resulting improved reliability, lower congestion, lower power losses, greater carrying capacity, reduced operating reserve requirements and improved access to cheaper generation. Customers who get no benefits from transmission lines cannot be allocated any of their costs.

FERC would be able to approve utility compensation to communities where transmission lines are located. The commission would have to prioritize using existing rights-of-way and the use of advanced conductors.

Interregional Planning Requirement

The bill also would require interregional transmission planning between neighboring transmission planning regions, including RTOs/ISOs and those set up to comply with FERC Order 1000’s regional requirements. The neighboring regions would need to use a common set of input assumptions and models on consistent timelines to pick projects based on a list of benefits around reliability and affordability.

Interregional plans would have to be submitted to FERC within two years of the process’ enactment and then every four years.

The bill specifically exempts ERCOT from the interregional planning and siting requirements.

Beyond the transmission provisions, it would require FERC and NERC to assess any future federal regulations that impact reliability and file comments with the agency working on them.

The Secretary of the Interior would be required to hold one offshore wind lease sale and one oil and gas lease sale per year from 2025 to 2029, which would not happen under current law.

The bill shortens the timelines before, during and after litigation for all federal authorizations on energy and mineral projects. Opponents would have to file lawsuits within 150 days after final agency action, courts would be required to expedite such cases, and agencies would have a 180-day deadline to deal with any remands from the courts.

Industry Groups Support Permitting Legislation

Americans for a Clean Energy Grid welcomed the permitting legislation, with Executive Director Christina Hayes saying it would bolster grid reliability by allowing for the timely deployment of transmission infrastructure.

“Of particular importance, FERC gaining plenary authority for transmission siting — just like it has for natural gas — would represent an important change in how the federal government permits transmission infrastructure in a timely and transparent manner,” Hayes said in a statement. “In combination with Order No. 1920 and the commission’s responsibility for ensuring reliability for customers, FERC is well positioned to center our nation’s efforts to build out the energy grid.”

Advanced Energy United also wants to see Congress move permitting legislation based on the Manchin-Barrasso bill.

“It has long been too difficult to build some of the critical energy infrastructure America needs, and this bipartisan proposal provides a good foundation on which to build a comprehensive package of legislative reforms,” AEU Managing Director Harry Godfrey said in a statement. “Both parties agree that unreasonable timetables and fragmented planning processes are making it too difficult to invest and build, providing Congress a unique opportunity to pass legislation that unlocks America’s innovative industries and improves grid reliability and energy costs for households and businesses.”