FERC has accepted ISO-NE’s compliance proposal for Order 2023, setting the stage for sweeping changes to the RTO’s interconnection procedures.
The April 4 ruling came nearly eight months after ISO-NE’s proposed effective date of Aug. 12, 2024, and followed months of stakeholder requests for rapid action to preserve the transition timeline and prevent significant delays to projects in the interconnection queue (ER24-2009, ER24-2007).
FERC’s ruling largely accepted ISO-NE’s proposal but directed the RTO to make relatively minor changes in an additional filing.
Order 2023 and the follow-up ruling, Order 2023-A, require transmission providers to transition from serial interconnection processes to cluster study processes, in which interconnection requests will be studied simultaneously.
ISO-NE filed its Order 2023 compliance proposal in May 2024 with the support of NEPOOL after an extensive process of stakeholder engagement and revisions. (See NEPOOL PC Backs ISO-NE Tariff Revisions for Order 2023 Compliance and ISO-NE Order 2023 Compliance Proposal Fails to Pass NEPOOL TC.)
In comments submitted to FERC, developers generally supported the filing, though several groups requested changes, such as a shorter cluster study timeline and reduced study deposit requirements. (See Clean Energy Groups Respond to ISO-NE Order 2023 Filing.)
Allco Finance had urged the commission to reject the proposal due to impacts it would have on distribution-level projects and argued ISO-NE does not have jurisdiction over state-level interconnection procedures. But FERC ruled the complaint was outside the scope of the proceeding, finding the company had not demonstrated ISO-NE failed to comply with Order 2023 or Order 2023-A.
Despite arguments from some stakeholders that ISO-NE should adopt the 150-day cluster study timeline outlined by Order 2023, the commission accepted the RTO’s proposal for a 270-day process. ISO-NE said a 150-day timeline would be infeasible for the region.
FERC agreed the 270-day timeline “reflects ISO-NE’s unique regional issues and the comprehensive scope of its studies, including electromagnetic transient studies for inverter-based resources.”
The commission also approved ISO-NE’s proposal to reduce the cluster restudy timeline from 150 to 90 days, noting the RTO “will use the same base case data as the cluster study and will involve fewer interconnection requests, thereby allowing interconnection requests to proceed expeditiously through the interconnection study process.”
FERC also accepted ISO-NE’s proposal to require a flat $250,000 deposit and a $50,000 application fee for the cluster study, writing that “extending the $250,000 deposit to smaller generators is reasonable due to regional differences because … project size is not a ready indicator of study cost or complexity for interconnection requests in New England.”
It rejected arguments by Glenvale Solar that ISO-NE’s proposed deposit requirements are prohibitive for smaller projects participating in the process, saying the “proposed flat deposit structure reasonably approximates study costs in New England.”
The commission also approved ISO-NE’s proposal for a $500,000 initial commercial readiness deposit, writing that the amount will help deter speculative interconnection requests. Order 2023 requires commercial readiness deposits to be twice the size of study deposits.
“While higher than the pro forma [Large Generator Interconnection Procedures], we find the variation is justified because the $500,000 amount reflects historically high network upgrade costs in ISO-NE,” FERC wrote.
Optimism Around Transitional CNR Study
FERC also accepted ISO-NE’s initial prohibition of using surety bonds for deposits, despite Order 2023’s direction to do so, saying the RTO demonstrated it needs more time to develop the procedures for accepting the bonds. The order directed the RTO to submit more information about when it will begin accepting surety bonds for commercial readiness and study deposits.
ISO-NE’s transition process for adopting the changes also largely complies with Order 2023, FERC wrote. The commission wrote that the creation of a transitional capacity network resource (CNR) group study helps to appropriately balance “the need to move expeditiously to the new cluster study process with the need to respect the investments and expectations of interconnection customers at an advanced stage in the existing interconnection process.”
The transitional CNR group study is intended to allow projects with complete system impact studies to gain capacity interconnection rights without needing to go through the full cluster study. Going forward, interconnection customers will achieve capacity interconnection rights through the cluster studies.
In recent months, project developers have raised alarms that FERC’s inaction on ISO-NE’s compliance proposal could threaten the ability to align the transitional CNR study with the qualification activities for ISO-NE’s 2025 reconfiguration auction (RA). (See New England Generators Remain in Limbo on Interconnection Reform.)
ISO-NE had said it would need a ruling by March 31 to align the transitional CNR group study with the 2025 RA qualification process due to a show-of-interest submission deadline at the end of April. On March 31, FERC took the unusual step of informing ISO-NE and stakeholders that it planned to issue an order in the coming days. (See FERC Announces Impending Order on ISO-NE Order 2023 Compliance.)
Alex Lawton of Advanced Energy United, who has been vocal about the importance of the transitional CNR study, said he’s optimistic FERC’s ruling will enable ISO-NE to proceed with the study.
A representative of ISO-NE said the RTO “is reviewing the April 4, 2025, order in detail and assessing next steps.”
The ruling also accepted independent entity variations related to site control requirements, the opportunity to reduce project size prior to a cluster restudy, energy storage modeling and the evaluation of alternative transmission technologies.
FERC directed ISO-NE to make a series of relatively minor changes to its proposal within 60 days, including to correct multiple “unexplained deviations” from the pro forma language, and to add pro forma language that was omitted. The commission also found the proposal did not comply with Order 2023’s ride-through requirements.
The commission accepted ISO-NE’s proposed Aug. 12, 2024, effective date and the June 13, 2024, deadline for interconnection customers to have a valid interconnection request to be eligible to participate in the first cluster study. While the RTO briefly reopened its interconnection queue April 1, requests submitted after this date will not be eligible to participate in the transitional cluster study. (See ISO-NE to Reopen Queue as it Continues to Wait on Ruling from FERC.)