MISO and SPP are considering $276 million in potential transmission upgrades under a joint model for identifying congested flowgates that could be relieved by economic projects.
Emerging from that joint process so far are four potential projects that could generate $438 million in benefits to the RTOs over 20 years, RTO officials said last week at a meeting of the SPP-MISO Interregional Planning Stakeholder Advisory Committee.
Four projects may not sound like much. But it’s progress considering the RTOs’ contentious relationship since December 2013 when New Orleans-based Entergy joined MISO rather than SPP, which had served as the Independent Coordinator of Transmission for Entergy’s system since 2006.
Most visible is a dispute over flows between MISO’s northern region and its new, southern region. MISO began limiting flows between the regions last spring after SPP complained that MISO had breached their joint operating agreement by moving power over its transmission footprint in excess of a 1,000-MW physical contract path.
But that dispute seemed distant as staff from both RTOs convened last week in Little Rock, Ark. Some even joked that they’ve been talking so much with those at the other RTO that they’ve memorized their phone numbers.
“We’ve learned a great deal about each other’s processes,” said Clayton Mayfield, an economic planner at SPP.
Collaboration has also improved modeling practices and provided a better understanding of neighboring stakeholder groups, said Jenell McKay, a senior analyst at MISO.
Stakeholders and staff at SPP and MISO came up with 67 potential economic projects using a joint model based on each RTO’s regional model. It projected transmission needs for 2019 and 2024.
That was whittled down to seven projects with potential, but three of those didn’t provide a minimum 5% benefit set as a threshold under the joint model.
The four projects seen to have the most potential totaled $276 million. They include new and upgraded transmission lines and transformers in Louisiana, Kansas and Nebraska. Benefits range from a 21% congestion reduction to a complete reduction in congestion.
Still Fine-Tuning List
Mayfield cautioned that the project list is preliminary and that more projects will likely emerge from the ongoing collaborative effort.
He noted that some projects initially identified were dismissed, and others added, after assumptions changed about the future of the Tennessee Valley Authority’s Shawnee units. MISO’s 2014 Transmission Expansion Plan originally contemplated that Shawnee Units 1-10, totaling 1,369 MW, would be retired, but TVA has since decided to keep nine of the Shawnee units in service.
The IPSAC joint analysis is expected to result in final project recommendations by June 30. The committee also is looking at a handful of reliability projects to reduce overloads.
More Potential
Other joint studies may be underway. McKay said the RTOs have had discussions regarding a study involving the effects of the Environmental Protection Agency’s proposed Clean Power Plan.
Pat Hayes, senior transmission policy specialist at Ameren, told the committee it could be helpful if staff conducts a “post mortem” regarding what differences the RTOs ran into and how they could have impeded a project from going through.
Kip Fox, director of transmission strategy and grid development at American Electric Power, said his “personal observation” is that the RTOs are working better together. He noted, however, that MISO and PJM have not been able to get moving on a seams project after four years. “I don’t want the same thing to happen here,” he told the committee.
Warren Buffett’s energy businesses have been buying and building wind generation facilities in the Midwest and Great Plains for years.
But the Oracle of Omaha now has his eyes on bringing solar power to the central U.S., according to a recent filing with the Federal Energy Regulatory Commission.
Buffett’s Berkshire Hathaway Energy disclosed that it recently acquired a site for solar generation development in MISO’s central region. The “site” consists of 74 individual “locations” not to exceed 1 MW each, according to the company’s quarterly property acquisition report. (MidAmerican Energy Holdings changed its name to Berkshire Hathaway Energy in April 2014.)
The company did not disclose exactly where the site is located. The company is not ready to make an announcement on the project, spokesman David Caris said.
MISO is a new locale for the company’s solar portfolio.
Subsidiary BHE Renewables has more than 1,200 MW in existing solar generation, primarily in California and Arizona, including its 550-MW Topaz Solar Farms in San Luis Obispo County, Calif., which became fully operational in March. Berkshire Hathaway companies also operate 579 MW of solar generation in Los Angeles and Kern Counties and own 49% of a 290-MW solar generating site in Yuma County, Ariz.
Environmental Regulations Bring Opportunities
Berkshire Hathaway’s planned solar expansion in MISO’s coal-dependent central region — which includes Indiana, Michigan, Wisconsin and parts of Illinois — appears designed to take advantage of increased demand for renewables as a result of federal environmental regulations.
The company has also continued its investments in wind. In October, BHE announced its plans for a 160-MW wind farm in Adams County, Iowa, that could cost up to $280 million.
Late last month, the company filed plans with the Iowa Utilities Board to construct up to 552 MW of additional wind generation in the state at a cost of $900 million. The company said it would announce the location and other details later.
On April 30, BHE announced plans to build a 400-MW wind farm in Holt County, Neb., that would be the largest wind project in the state. The recent FERC filing said that Berkshire Hathaway acquired a site in SPP territory for up to 400 MW of wind-powered generation development. It wasn’t immediately clear whether it’s the same site.
BHE owns and operates more than 3,400 MW of wind, solar, geothermal and hydro generation.
At the Edison Electric Institute’s annual convention last June, Buffett said the company, which has already spent $15 billion on renewables, was prepared to double that investment.
ALBANY, N.Y. — Four former energy regulators who were in the middle of many of the electric industry’s watershed events of the past two decades reminisced — and expressed regrets for paths not chosen — at the Independent Power Producers of New York spring conference Wednesday.
Former Federal Energy Regulatory Commissioners William Massey (1993–2003), Nora Mead Brownell (2001–2006), Suedeen Kelly (2003–2009) and former chairman Pat Wood (2001-2005) expressed pride in the growth of wholesale competition and wistfulness over political compromises that prevented development of larger, more uniform markets.
In a later session, NYISO CEO Stephen Whitley (2008–present) and predecessors William Museler (1999–2005) and Mark Lynch (2005–2008) also shared war stories from the first 15 years of the ISO’s markets.
Open Access
Massey voted in 1996 for the landmark Order 888, which ordered transmission operators to open their lines to competition.
“We knew we would get pushback with everything we did, but if you’re going to be a regulator or run an RTO, you’ve got to have political courage,” said Massey, counsel to the COMPETE coalition, which represents more than 700 stakeholders in support of electricity competition.
And political courage failed him at the most crucial time, Massey admitted, recalling the California energy crisis of 2000-2001, which occurred after FERC’s misgivings about the poorly designed California market were cast aside.
Massey related how the 1996 utility restructuring law passed the California legislature unanimously. The entire California congressional delegation then wrote to FERC, saying that any tinkering by the agency would likely cause the plan to collapse “like a house of cards.”
FERC meekly went along. “We had the opportunity to vote yes or no,” Massey said. “That is the vote I’m most sorry about.”
California’s wholesale power market and customer-choice program began in 1998 and seemed to be working well until the summer of 2000, when electricity prices in southern California hit all-time highs, and generation shortages caused rolling blackouts in northern California. Escalating wholesale prices, combined with retail price caps, put the state’s three major investor-owned utilities in a vise, with Pacific Gas & Electric forced to declare bankruptcy.
In December 2000, FERC eliminated the requirement that the three IOUs purchase their power through the California Power Exchange. In June 2001, shortly after Wood and Brownell joined the commission, FERC expanded a price mitigation and market monitoring plan it had issued in April 2001.
The California price spikes and Enron’s implosion stopped restructuring dead in its tracks as a national policy, Wood recalled. “Years later we were still putting the pieces back together,” he said.
Wood, now chairman of the Dynegy Board of Directors, said the industry is still coping with the lessons from the California crisis, including the balancing of consumer interests and industry needs. “If you want to be an economic regulator, you’ve got to understand the economics [and] what it takes to incent investment,” he said.
What he most seemed to regret was how proposals to divide the country into four RTOs — the Northeast, Southeast, Midwest and West — were stymied. The country is still paying for the “balkanization” of the markets caused by the “hue and cry and pushback,” he said.
“I still think there’s a lot of enterprise that could occur between New York and New England. And the seams issues between PJM and MISO are just awful,” he said.
Former NYISO CEO Lynch said the vision of a larger, seamless market in the Eastern Interconnection is unlikely to be realized. “We may have missed our opportunity to get there,” he said.
Kelly, who worked on legislation to make restructured markets national policy as a Senate staffer before her FERC tenure, said its failure informed her tenure as a regulator. “Political courage is important, but even more important is political support,” she said. Kelly added that energy policy is one place where partisanship can melt away and consensus built.
But Brownell and NYISO CEO Whitley said that consensus-building can be unwieldy — “herding cats,” Whitley called it.
“I think the stakeholder process has grown into a cottage industry,” Brownell said. “I have great respect for the work they do, but I can’t imagine the New York Stock Exchange being developed by 400 people over a three-year period. We need to focus on the larger picture,” she said.
The larger picture, Brownell said, is electric markets’ role in developing the economy. “Where we begin to redefine this industry as economic development, we’ll move away from state versus federal [jurisdiction]. This is really about our competitive position in the world and social well-being.”
A New York clean energy developer has challenged a three-state effort to bring more renewable energy to New England.
Allco Renewable Energy Group filed suit against Connecticut in U.S. District Court in New Haven, claiming the joint effort and Connecticut’s renewable energy subsidies violate the U.S. Constitution’s Interstate Commerce Clause (3:15-cv-00608-CSH). Allco is also asking for an injunction to stop the joint procurement plan by Connecticut, Massachusetts and Rhode Island.
Allco CEO Thomas Melone unsuccessfully sued over Connecticut’s previous clean power plan, claiming the state illegally excluded renewable energy credits (RECs) generated by his facilities in other states from participating in Connecticut’s programs. RECs represent the environmental attributes of a clean energy project and are sold and traded separately from the energy produced. That case is under appeal. The claims made in that suit under the dormant Commerce Clause and the Federal Power Act are repeated in the new lawsuit.
Connecticut counts RECs from other New England states, and from New York and Canada, under certain circumstances. Melone is seeking to have his solar facilities in Georgia and New York qualified. The determination should be made by the Federal Energy Regulatory Commission and not the states, the suit says.
“The dormant Commerce Clause prohibits a state from using its regulatory power to discriminate against out-of-state businesses,” according to the suit, filed on April 26.
Allco sued the Connecticut Department of Energy and Environmental Protection and the state’s Public Utility Regulatory Authority.
“The three-state procurement is an innovative approach to meeting our renewable energy goals and securing clean power at the lowest possible price for our families and businesses,” Dennis Schain, a spokesman for DEEP said in a written statement to the Hartford Courant. “We believe the procurement is legally sound and will meet court challenges.”
MISO and ISO-NE said last week they have sufficient resources to meet this summer’s demand, but they warned that their reserve margins are shrinking due to plant retirements.
Reserves Good — for Now
MISO estimates that summer demand in its territory will peak at 127.3 GW, with 23 GW of reserve capacity available. That amounts to an 18% reserve margin, above the target of 14.3%.
However, the RTO projects reserve margins will erode because of “current environmental and microeconomic pressures.” That could result in emergency operations, such as suspending planned generation maintenance and the curtailment of non-firm energy sales.
Coal-fired generators are being forced into retirement by cheap natural gas and current and pending emissions limits on mercury and carbon dioxide.
“Starting in the next few years, we are seeing a dramatic shift in the resources available to meet demand during the hottest days of the year,” said Todd Ramey, vice president of system operations and market services at MISO.
ISO-NE Expects Sufficient Resources
ISO-NE also said it will have enough electric generation and demand response resources to serve its forecasted summer peak.
Under normal weather conditions of about 90 F this summer, electricity demand is forecasted to peak at 26.71 GW. Extreme summer weather, such as an extended heat wave of about 94 F, could push demand up to 29 GW. These forecasts take into account the demand-reducing effect of 1,685 MW of energy-efficiency measures acquired through the Forward Capacity Market.
Last year’s retirement of the 615-MW Vermont Yankee nuclear power plant will reduce the region’s reserve margin. Last summer, demand for power peaked on July 2, 2014, at 24.44 GW. The all-time record for peak demand was set on Aug. 2, 2006, when demand reached 28.13 GW after a prolonged heat wave.
Developers have released plans to build the world’s largest fuel cell park at a former gravel pit in Beacon Falls. CT Energy & Technology would develop and own the 63.3-MW park, which would surpass the 59-MW Gyeonggi Green Energy park in South Korea as the world’s largest.
“For practical purposes, the project location in Beacon Falls is perfect because it is next to an electric switch yard, a natural gas tie-in and water,” said William Corvo, president of CT Energy.
Under a letter of intent, FuelCell Energy of Danbury will supply the cells and is expected to operate and maintain the plant under a long-term service agreement. O&G Industries owns the property. CT Energy is developing and will own the project. Corvo declined to disclose the price tag for the project.
State Braces for Large Wind Expansion Because of Clean Power Plan
The state, which generates the majority of its electricity from coal, is anticipating a rapid expansion of its wind portfolio due partly to the Environmental Protection Agency’s proposed Clean Power Plan.
Only five other states are projected to boost wind power as much as or more than Indiana, according to the U.S. Department of Energy. The state could triple its wind power capacity over the next decade from 1,744 MW to more than 5,000 MW, said Sean Brady, Midwest policy manager for Wind on the Wires.
That would require 2,000 more wind turbines to join the 1,031 now located in the northern half of the state.
Gov. Paul LePage has nominated a University of Tennessee economist for the remaining slot on the Public Utilities Commission. Bruce Williamson, senior economist at the Institute for Nuclear Security at the university’s Howard Baker Center for Public Policy, told the Portland Press Herald, “I have no agenda in coming to Maine. I’m not bringing any prejudice about one type of energy versus another. It’s all about making sense financially.”
LePage favors policies that encourage expansion of natural gas pipelines and is opposed to subsidies to promote renewable energy and energy efficiency.
SunEdison, developer of the proposed 22-turbine Weaver Wind project near Ellsworth, recently released a statement saying it was withdrawing its power purchase plan and would try to sell its electricity elsewhere in New England, due to issues with the commission.
LePage’s Plan to Attract Nukes Blasted by Environmentalists
Environmentalists and anti-nuclear activists are blasting Gov. Paul LePage’s proposal to make it easier to bring small nuclear power plants to the state, because it would strip voters of the power to sign off on new plants, they say. Currently, voters must approve the construction of any nuclear power plant in the state.
LePage wants to remove that requirement for plants that generate 500 MW or less. But opponents say LePage’s proposal would silence those who could be greatly impacted by a potentially risky energy resource. The state’s only nuclear plant, Maine Yankee, closed in 1997, but only after surviving three referendums led by anti-nuclear activists — it closed due to operations and management problems. Patrick Woodcock, director of the Governor’s Energy Office, said the public would still have plenty of opportunities to weigh in through municipal permitting hearings.
Earthjustice Appeals Fed OK of Cove Point Terminal
Environmental group Earthjustice is suing the Federal Energy Regulatory Commission to reverse the agency’s approval of Dominion Resources’ Cove Point liquefied natural gas export terminal near Lusby, Md.
The group said FERC approved the project without conducting a rigorous environmental review. While the environmental studies did cover effects at the plant site, the group argues that it should have considered how increased demand for gas would result in increased pollution in the Marcellus Shale region where the gas is produced, as well as water pollution from increased shipping in the Chesapeake Bay.
Earthjustice — on behalf of state environmental groups Chesapeake Climate Action Network, the Patuxent Riverkeeper and the state chapter of the Sierra Club — filed the suit in the D.C. Circuit Court of Appeals after FERC denied its request for a rehearing last week. “After months of delay, we will finally get our day in court to challenge the fundamentally flawed approval of Dominion’s climate- and community-wrecking project,” said Mike Tidwell, director of the organization.
The takeover has met significant opposition in the state, where critics believe it would give the Chicago energy giant too much influence over electric service in the region. Criticism also has been fierce in D.C., which is expected to make its decision shortly after Maryland rules.
The acquisition already has won support from the Federal Energy Regulatory Commission and state officials in New Jersey, Virginia and Delaware.
Constellation, CCBC Team up to Build Solar Project
Constellation Energy and the Community College of Baltimore County are partnering to build a 5.1-MW solar generation project.
The system, spread among the college’s three main campuses, is expected to generate enough electricity to meet about 27% of the school’s electricity needs.
Constellation also will install 10 duplex electric vehicle charging stations as part of the project.
Constellation, the state’s top solar energy producer, will own and operate the systems. CCBC will buy the electricity under a 20-year purchase agreement.
The system will consist of about 16,500 photovoltaic panels on carports across the campuses.
The Pittsfield Community Development Board has approved a site plan for a commercial-scale photovoltaic power generation facility planned on three adjacent undeveloped lots in an industrial park. Solar panels on each lot are expected to produce 650 kW of energy at peak generation, according to officials with U.S. Light Energy.
William Heffernan, operations manager with the firm, said it plans to purchase the lots from Betnr Industrial Development and will produce electricity for distribution through Eversource Energy.
Tesla Motors has reached a deal to buy the Grand Rapids-based auto supplier Riviera Tool, marking the Silicon Valley tech company’s first acquisition, according to the Detroit Free Press.
Riviera makes stamping parts used by Tesla’s assembly plant in Fremont, Calif. Tesla is expected to continue adding jobs at Riviera.
PSC Approves Acquisition of Former Alliant Customers by Co-Ops
The Public Utilities Commission has approved the transfer of about 43,000 electricity customers from Alliant Energy to a consortium of co-ops. Alliant agreed in 2013 to the sale of its business to a group known as the Southern Minnesota Energy Cooperative, which will divide the southern service territory among adjacent co-ops.
The co-ops involved are: BENCO EC, Mankata; Brown County REA, Sleepy Eye; Federated REA, Jackson; Freeborn-Mower Cooperative Services, Albert Lea; Minnesota Valley EC, Jordan; Nobles Cooperative Electric, Worthington; Redwood EC, Clements; Peoples Energy Cooperative, Oronoco; South Central Electric Association, Saint James; and Steele-Waseca Cooperative Electric, Owatonna. Sioux Valley Energy, headquartered in Colman, S.D., would also add members in its Minnesota territory.
An independent state research institute has walked away from a $66,000 contract with Kinder Morgan to study the impact of a proposed natural gas pipeline, citing a disagreement over the terms of the research. The New Hampshire Center for Public Policy Studies has been at work on the Kinder Morgan proposal since early March and was scheduled to release its report in June. The non-profit think tank was hired by the energy company to conduct an objective analysis of its proposal for a new pipeline through southern New Hampshire. The work was under the direction of the center’s Executive Director Steve Norton, with most of the research conducted by economist Dennis Delay. A disagreement over the “terms of engagement” led to the cancellation of the deal, according to Norton.
Ambit Energy, an alternate energy marketer in the state, is under investigation by the Public Service Commission. Customers have complained about a lack of notification at the expiration of their contracts and the calculations used for guaranteed savings. Ambit says it is cooperating in the investigation.
The company said it met with the Department of Public Service “to explain how it calculates savings from its Guaranteed Savings Plan. The conversation expanded to include a discussion of the complaints the DPS received in 2014 and 2015 after consecutive, unseasonably cold winters in the state.” The newly formed Consumer Advocate office within the department is heading the investigation.
Hundreds of people turned out at the first of two Public Service Commission hearings on a proposal to subsidize the Ginna nuclear power plant. The hearing in Webster, a town close to the financially troubled nuclear facility and populated by many Ginna workers, was mostly supportive of the plan to prop up the plant to maintain system reliability.
Rochester Gas & Electric officials have said the transmission system is insufficiently robust to be able to deliver enough power to replace Ginna’s supply, should the plant be shuttered. A study done for the company raises the possibility of electricity shortages during periods of peak summertime demand if Ginna were to close now. Under that plan to guarantee rates, residential customers would pay an extra $163 over the next 3.5 years to keep Ginna running. Monthly charges would start at $6.11 and drop in subsequent years.
National Grid transmission-line upgrades would add $20 million to the tax base in the state’s Capital Region and lead to 264 new permanent jobs locally, according to a new study commissioned by the utility. The figures include data from Albany, Columbia, Montgomery, Rensselaer and Schenectady counties, where the construction would take place. Other counties involved in the project include Oneida, Herkimer and Dutchess counties. The total tax base benefit would be $30 million, and the addition to the job base would be 389 jobs.
National Grid is proposing a $1.2 billion upgrade to its high-voltage electric transmission system in the Mohawk Valley and the Hudson Valley.
Nuclear Transformer that Caught Fire was Subject of State Concerns
The state has had concerns for years about the reliability of transformers at the Indian Point nuclear generating station, where a transformer at Unit 3 exploded on Saturday night, spilling oil into the Hudson River.
The unit, which shut down automatically, could be out of service for weeks, according to a spokesman for plant owner Entergy. The fire, which sent black smoke into the sky, was extinguished by a sprinkler system and on-site personnel, the company said.
In 2007, state officials filed a petition with the Nuclear Regulatory Commission, saying the plant failed to operate an age management plan for transformers. The “failure to properly manage the aging of electrical transformers could have safety implications for the plant, such as affecting station blackout recovery,” the state told the NRC. Entergy responded that neither industry practice nor NRC staff guidance called for such a monitoring regime, according to a filing last year by the state as part of Indian Point’s licensing renewal application.
In 2013, the NRC’s Atomic Safety and Licensing Board ruled that the transformers fall under the scope of an age-monitoring review. An engineer called by the state as a witness testified that failure to properly manage transformer aging may compromise the safety of Indian Point, which is located about 35 miles north of midtown Manhattan.
The Republican-led House voted 77-32 to freeze the percentage of electricity sales mandated to come from renewable sources or energy efficiency as part of a regulatory reform package. It would stop an annual progression in a bill passed in 2007, setting the cap for renewable retail sales at 6%. And while the bill provides for local property tax breaks for solar, it also decreases the capacity threshold for solar and wind projects selling back to utilities. That particular amendment was seen as a major loss for solar advocates.
Officials Warn Against Drinking Water near Duke Coal Ash Pits
State environmental officials are warning residents near Duke Energy coal ash pits against drinking or cooking with well water after tests showed that 93% of the 163 wells tested so far showed high levels of toxic metals. It was the second warning about contaminated groundwater. Last month, state officials said 87 wells near eight Duke power plants failed to meet state groundwater standards.
Duke has 32 ash dumps at 14 power plants in the state. A law passed in the wake of a massive coal ash spill last year mandates testing at every site.
Senators Call for Better Tank Car Standards After Fiery Derailment
A crude-oil train’s derailment and explosion spurred the state’s U.S. senators to call for rapid upgrades of tank-car fleets to reduce the chance of future accidents. A 107-car BNSF train derailed and several cars burst into flames near Heimdal, but no injuries were reported.
“We must get the tanker car fleet updated,” Sen. John Hoeven (R-N.D.) said. “It’s all about safety and everyone … has a role to play.”
“Today’s derailment of a crude oil train is the second one in our state in the past year and a half,” Sen. Heidi Heitkamp (D-N.D.) said. “We cannot allow these to become the norm.”
Democrat Appointed to Chair PUC; Wolf Eyes Renewable Energy Policies
Gov. Tom Wolf has named fellow Democrat Gladys Brown chairwoman of the Public Utility Commission.
She replaces Robert Powelson, a Republican, who has led the five-member group since 2011. His term expires in 2019.
Wolf has not revealed his intention to reappoint or replace the other Democrat on the panel, James Cawley, whose term expired March 31.
Brown, 51, is a Harrisburg lawyer and former legislative aide who was named to the PUC in 2013.
Wolf said he looked forward to working with Brown “to ensure there is a stable balance between consumers and utilities, as well as utilizing PUC to advance the development of Pennsylvania’s infrastructure to support the natural gas industry.”
“I also believe we have a real opportunity to reposition the commonwealth as a leader in developing renewable energy and energy efficiencies,” Wolf said in a statement. “Gladys shares my vision and has the experience to help advance policies to achieve this.”
LITTLE ROCK, Ark. — SPP officials and market participants last week celebrated the first year of its Integrated Marketplace, boasting of its on-time, under-budget delivery, while acknowledging there is more work to do.
“We don’t have all the bells and whistles of everybody [else’s market]. But we do have a good pick-up truck to move us down the road,” said Jim Krajecki, Southwest director of wholesale services for Customized Energy Solutions, who moderated the headline session at the Gulf Coast Power Association’s briefing on SPP last week.
Krajecki noted that in its first year, SPP got 95% of its generation from the day-ahead market, while only 2.2% came through self-commitments and 2.5% from the reliability unit commitment (RUC) process. “Other regions took four to five years to get to these commitment levels,” he said.
David Walters, a former Oklahoma governor (1991–1995) who now runs his own international power development company, called the market “a game changer for developers.”
“I’ve been in this business for about 20 years. I think I spent the first … maybe 18 years complaining about SPP. I’ve been quoted as saying it was managed like the Bada Bing club,” the strip joint frequented by mobsters in “The Sopranos,” he said, prompting laughter from the audience of about 70 — and winces from SPP officials in attendance.
“But it’s a lot different now,” Walters continued. “I’m really excited about this Integrated Market. [It is] somewhat delayed compared with the other areas of the country but a remarkably complex system was established with very few hiccups.”
“From an operational aspect things have been very smooth compared to what I saw in ERCOT,” agreed Seth Cochran, manager of market affairs and origination for DC Energy. “Not only that but they didn’t have any slippage in the timelines and I think they did it for a quarter of the cost. So there’s a good story to tell there.”
Improvements Needed: Ramping Product
Speakers also discussed changes they’d like to see. Several speakers called for developing a ramping product to take advantage of the region’s wind resources and incentivize quick-start generators.
Cliff Franklin, senior regulatory specialist for Westar Energy, said SPP is overly reliant on RUCs compared with MISO, which he said makes better use of the day-ahead market.
“The reason that’s bad is because then deviations get hit with all that cost and that discourages imports [and] exports in real time,” he said. “When you need help you don’t want people worrying about their RUC distribution charges. You want people to efficiently trade in the market in real time.”
Krajecki noted that SPP’s available ramp has declined from about 375 MW/minute in August 2014 to 200 MW/minute in February 2015, which he said is leading to more constrained periods and market volatility.
Franklin said ramping can be improved with better compensation.
Fast-ramping units are “getting [payment for] energy and they’re typically at minimum load. That’s not real good incentive,” he said.
But it won’t be easy to achieve, said Richard Dillon, SPP’s director of market design. “It sounds very easy. I’m going to pay somebody for how fast they can press on the gas pedal and get out of the way of the truck coming up the back end. It sounds really easy but you set yourself up for: Am I offering ramp or am I offering energy? And they actually start contradicting each other if you don’t do the design correctly. … That is not going to be a small project.”
Jodi Woods, SPP’s manager of the day-ahead market, said the RTO is working to minimize use of the RUC process. “Some of it’s just been a learning process for the operators who are doing some of those commitments,” she said.
Transmission Congestion Rights Funding
DC Energy’s Cochran said the underfunding of transmission congestion rights has been a big disappointment for his company.
SPP’s 84.5% funding in March 2015 is “bottom-of-the-barrel,” he said, noting that ERCOT averages about 95%.
“If this goes on, it will ultimately drive out liquidity. People won’t want to participate. I’ve talked to numerous traders. When their targeted amounts are getting hair-cut by [as much as] 40% … it just disincentivizes trading. They no longer want to participate in that kind of market.”
Overcollection of Losses
SPP’s Dillon said overcollection of marginal losses is causing too much day-ahead trading at the expense of the real-time market. “As in many designs you go in and you have a lot of theories. And overcollected losses was one of those where it actually played out and we went, ‘Oops, this is providing the wrong incentive.’”
RTO officials hope a revised rule, effective May 29, will solve the problem.
Seams Coordination
Dillon said SPP also is considering changes to rules setting a single interface price for the seam with MISO, which leaves the RTO vulnerable to gaming by traders — an issue that will become more acute when the Heartland Consumers Power District, Basin Electric Power Cooperative and the Western Area Power Administration’s Upper Great Plains Region join SPP in October. (See Spurned by Entergy, SPP Expands in Great Plains.)
“Our border is very long to begin with,” Dillon said. With WAPA “you have a single price representing from the Gulf Coast all the way up to Canada, [although] the Entergy area is very different from [the] Kansas City area, which is very different from the North and South Dakota area. SPP is looking at [whether it can] mitigate the gaming such that we can break it into multiple prices.”
A former Nuclear Regulatory Commission employee was charged with trying to sell sensitive nuclear weapons information to a foreign government after he was caught by an FBI sting operation. Charles Harvey Eccleston’s attempts to glean information from government computers came to the attention of investigators after he entered an unidentified foreign embassy and offered to sell information.
Investigators said he offered to design malware that would pluck information from government computers in a method known as “spear-phishing.” He was caught in the Philippines on March 27.
NRC Approves Plan to Build at Fermi — but DTE isn’t Building
While the Nuclear Regulatory Commission has approved plans to build a new reactor at DTE’s Fermi 2 site, the company announced that it doesn’t plan to act on that approval.
A company spokesman said the construction license was sought to preserve DTE’s options. The plan allows for a 1,560-MW facility, which would boost the site’s capacity from the 1,170 MW already in operation.
DTE plans to retire some of its coal plants in the next five years, but the company said it is eyeing natural gas-fired plants if it pursues any immediate construction plans.
The Federal Energy Regulatory Commission approved Spectra Energy’s plans to begin site preparation work on its Algonquin Pipeline expansion in New Jersey. Called the AIM Expansion, the project is designed to improve natural gas supply to the Northeast Region of the U.S., which experienced gas shortages during winter peaks.
Delaware Urges Interior to Keep Offshore Water Survey-Free
Delaware’s top environmental official is urging the U.S. Department of the Interior to not permit any seismic surveys off the state’s coast because it is not part of the federal government’s immediate plans for oil and gas development.
“The extent of proposed surveys into waters offshore of Delaware does not correlate to the leasing program areas and we do not see the need for surveys in areas that are not currently subject to leasing,” Department of Natural Resources and Environmental Control Secretary David Small said in a letter.
The Interior Department has granted seismic surveying off the coasts of other Mid-Atlantic states. Information from the surveys will be part of the Bureau of Ocean Energy Management offshore lease programs.
NRC Investigating Incidents at Exelon’s Three Mile Island
The Nuclear Regulatory Commission is looking into two recent incidents at Exelon Nuclear’s Three Mile Island generating station in Pennsylvania. Two Sundays ago, a control rod dropped inside the reactor. Four days later, a valve opened and allowed steam to be vented into the atmosphere. Low levels of radiation were in the steam, according to the NRC and Exelon officials.
NRC investigators are determining the cause of both incidents.
FERC Grants Initial Approval to Palmetto Pipeline Project
The Federal Energy Regulatory Commission has granted pricing and service conditions for Kinder Morgan’s proposed Palmetto Pipeline. The pipeline runs from South Carolina to Florida. When completed, the pipeline will have the capacity to move 167,000 barrels of oil or petroleum products daily.
Kinder Morgan said the project will cost about $1 billion.
Tesla CEO Elon Musk announced the electric automaker’s next new product: the Powerwall, a modular battery storage system aimed at the residential sector. The lithium-ion battery pack, which can be combined with as many as eight other units, mounts to a wall and stores energy from solar collectors.
“If you have the Tesla Powerwall, if the utility goes down, you still have power,” Musk said. “The whole thing is an integrated system that works.” The components will be built at the company’s $5 billion Gigafactory now under construction near Reno, Nev. The company announced two versions of the battery: a 10-kWh unit for $3,500 and a 7-kWh one for $3,000, the latter of which is designed for daily cycling. Tesla is also marketing a version for the commercial sector called the Powerpack.
Initial reaction from analysts was positive. Tesla said it received more than 38,000 orders for the product, including 2,800 for the commercial version. “We’re basically sold out through the first half of next year,” Musk said.
Other companies are working on the same idea, including NRG Energy, which is developing battery storage products. “We have to be in this space,” NRG Home CEO Steve McBee said. “If your goal is to build a meaningful solar business that is durable over time, you have to assume that the solar business is going to morph into a solar-plus-storage solution.”
Dominion’s Annual Meeting Scene of Pipeline Protest
The Dominion Resources annual meeting drew more than 100 protesters opposed to the Atlantic Coast Pipeline. The Richmond, Va.-based company is a major partner in the $4.5 billion plan to build a 500-mile pipeline across rural parts of West Virginia, Virginia and into North Carolina to bring shale gas to eastern markets.
“I think that we’ll get the attention of the shareholders of the corporation that don’t realize they’re risking lives,” said Yvette Ravina of Churchville, Va., a rural area. Picketers gathered outside the site of the meeting, and at least six were inside the meeting itself.
CEO Thomas F. Farrell II said the pipeline would be critical to providing the natural gas necessary to meet growing customer demand, especially now that the pressure is on to meet Environmental Protection Agency emissions mandates. “Virginia and North Carolina in particular do not have enough gas infrastructure,” he said. “This is extremely important. … it’s going to result in much cleaner air.”
Exelon’s Oyster Creek Down for ‘Electrical Disturbance’
Exelon Nuclear’s aging Oyster Creek Generating Station was taken offline Thursday due to what the company termed “an electrical disturbance on the non-nuclear side of the plant.” They said there was no release of radiation.
“We want to make sure why it happened, but for public safety and the plant workers the plant is safely shut down,” said Nuclear Regulatory Commission spokesman Neil Sheehan. “Now it’s a matter of troubleshooting exactly what occurred.”
The 636-MW plant on the New Jersey coast also shut down in March. It is the oldest in the company’s fleet and is scheduled for decommissioning in 2019. The plant received a “white” performance indicator from the NRC because of four unplanned shutdowns in 2013 and 2014. It received a more serious “yellow” finding last month after problems were found with two of five reactor pressure valves.
Duke Energy will buy a 7.5% stake for $225 million in a proposed natural gas pipeline that is to run from Alabama, through Georgia and terminate in Florida. The other partners in the 500-mile Sabal Trail Transmission project are Spectra Energy (59.5%) and NextEra Energy (33%). The pipeline is scheduled to begin operations in 2017.
Southern Co. said it is researching the possible use of drones to inspect its thousands of miles of power lines. It has asked for and received clearance from the Federal Aviation Administration to test unmanned aerial systems for business purposes.
The company has more than 27,000 miles of transmission lines throughout the Southeast. COO Kimberly Greene said the use of drones could expedite storm recovery, and drone inspections could be done safely and cost effectively.
Southern Co. subsidiary Mississippi Power is partnering with Origis Energy to build a utility-scale solar farm in Sumrall, Miss. It will be Mississippi Power’s third renewable project in the state. The company is also building a 450-acre, 50-MW solar station in Hattiesburg, and a 3 to 4-MW facility in conjunction with the U.S. Navy at the Naval Construction Battalion Center in Gulfport. All three projects, pending approval of the Public Service Commission, are expected to be in service by the end of next year.
Ohio Religious Leaders Appeal to FirstEnergy for Reform
A group of 38 Ohio religious leaders, concerned about low-income customers, have asked FirstEnergy CEO Charles Jones to change the way the utility does business. “It’s time that we as citizens demand corporate America be accountable to us,” Eugene Ward Jr., a Baptist bishop from Cleveland, wrote in the letter to Jones. “We can’t afford the higher rates nor the damage that FirstEnergy is wreaking on our environment.”
Many of the clergy face staggering utility bills from heating and cooling old, inefficient churches. The group also denounced FirstEnergy’s attempt to get approval for its Electric Security Plan, which would guarantee income for underperforming plants.
“This subsidy would rob the poorest among us for the profit of a massive corporation and hurt families by forcing them to underwrite the costs of outmoded facilities whose harmful byproducts make them sick,” the letter said.
PPL’s Susquehanna-Roseland Tx Line About to Go into Service
A 130-mile, $632 million transmission line running from PPL’s Susquehanna nuclear plant near Berwick, Pa., to a substation near Newark, N.J., is set to go into service. Under construction since 2012, the development of the line prevailed despite community opposition. The line follows a previously existing transmission corridor through the Delaware Water Gap National Recreational Area. PPL officials said testing is being done on the line now, and it should go into service by the end of the month.
The 500-kV line was fast-tracked by federal authorities as part of the Obama administration’s drive to upgrade the nation’s power grid. It was constructed in collaboration with Public Service Electric & Gas.
Annual Market Report for RGGI CO2 Allowances Released
No evidence of anti-competitive conduct has been found in the market for Regional Greenhouse Gas Initiative CO2 allowances, according to Independent Market Monitor Potomac Economics’ 2014 Annual Report on the Market for RGGI CO2 Allowances.
Firms acquire the RGGI CO2 allowances in the primary market, mainly the RGGI CO2 allowance auctions, and can also buy and sell CO2 allowances in the secondary market. According to the Monitor, the average 2014 auction clearing price was $4.72, a 62% increase from $2.92 in 2013. Secondary market prices were generally consistent with auction prices at an average price of $4.82.
Demand for allowances at auction also increased in 2014. For the second year in a row, no allowances offered at auction have gone unsold. Compliance entities held 85% of the CO2 allowances in circulation at the end of 2014, an increase from 81% at the end of 2013.
PJM made it through the winter without having to invoke a temporary cost-based energy offer cap of $1,800/MWh, the Independent Market Monitor reported last week.
In the 75 days ending March 31 that the waiver was in effect, there were 54 cost-based offers between $1,000/MWh — the historical cap — and $1,800/MWh, but none cleared, according to the report, which the Federal Energy Regulatory Commission ordered in granting the waiver Jan. 16 (EL15-31). (See FERC OKs $1,800 Offer Cap.)
“None of the cost-based or price-based offers between $1,000 and $1,800/MWh cleared with an incremental rate above $1,000/MWh, although one unit with an incremental offer curve that included points below $1,000 and above $1,000/MWh was dispatched at incremental offers below $1,000/MWh on three days,” it said.
“The Market Monitor’s review … indicates that energy offers with scheduling rates or with incremental curve offer components above $1,000/MWh did not affect energy market prices or result in uplift payments to generators,” it said. “LMPs greater than $1,000 were the result of transmission constraint penalty factors and not the result of unit offers.”
The Monitor said it was “investigating the offer behavior of several units and will take appropriate actions consistent with Attachment M of the PJM Tariff.”
PJM requested the waiver over concern that some natural gas-fired generators might encounter the same fuel price spikes that occurred during the polar vortex in January 2014. PJM asked for the allowance to ensure that generators would recover their costs if called upon during periods of high demand.
In fact, the cold temperatures of this past winter sent PJM to a new winter record for electricity use on Feb. 14, and the RTO still was able to avert use of the higher cost-based offer cap. Demand hit about 143,800 MW, surpassing the previous peak of 141,846 on Jan. 7, 2014. (See Cold Sends PJM to New Winter Record.)
Analysts have attributed this winter’s lower natural gas prices to ample supply, a later onset of cold temperatures and increased imports of liquefied natural gas to the Northeast.
The waiver request was made as a section 206 filing after stakeholders failed over eight months to come to a consensus.
At the time the waiver was being debated, Market Monitor Joe Bowring said fewer than 25 offers had breached $1,000 in January 2014. While some of the proposed offers were in the $1,700/MWh range, he said, there had been no legitimate offers greater than $1,400/MWh.