Search
`
November 5, 2024

PJM Operating Committee Briefs

VALLEY FORGE, Pa. — PJM staff introduced a problem statement at last week’s Operating Committee meeting to address concerns that the RTO is purchasing too much fast-responding “RegD” resources, which is negatively affecting regulation and reliability.

pjm

The problem statement calls for a reevaluation of the marginal benefits factor used in the regulation market optimization solution, which appears to over-value the contribution of RegD resources as a substitute for traditional RegA.

“In order for the regulation market to arrange the optimal, least-cost combination of RegA and RegD to meet [area control error] control requirements, the marginal benefits factor function needs to be accurately defined,” according to the problem statement. (See PJM Market Monitor: Faulty Marginal Benefit Factor Harming Regulation.)

Generators’ Non-Compliance Continues

PJM staff continues to struggle with generators’ non-compliance with training and certification requirements.

While transmission owners generally are in compliance, 10 generators (12%) were non-compliant for certification, and two (3%) were non-compliant for training as of May, PJM’s Glen Boyle told the Operating Committee. Four demand response companies (17%) were non-compliant for training. In addition, four small generation companies (20%) were non-compliant for training.

While non-compliant companies are supposed to submit mitigation plans, many have not, and there are no financial penalties for failing to do so.

Stakeholders suggested PJM identify a compliance officer at each organization with whom to follow up. (See PJM Operating Committee Briefs, Sought: Ways to Incent Training, Certification Compliance.)

SPS Removals in PPL

PPL Electric Utilities is removing three special protections schemes (SPS).

  • Susquehanna Loss of Outlet Scheme: The SPS would trip Susquehanna Unit 2 when two 500-kV outlets were open at the same time. The SPS is no longer needed with the May addition of the Susquehanna-Roseland 500-kV line.
  • Wescosville T3 SPS: The Wescosville 500/138-kV Transformer T3 would trip when the Alburtis end of the Susquehanna–Wescosville-Alburtis 500-kV line was open. The SPS is no longer needed with the May installation of the Breinigsville 500/138/69-kV substation.
  • Montour Runback SPS: During construction of the 230-kV line between Lackawanna and Bushkill and on one of the two Susquehanna-Harwood 230-kV lines, certain contingencies could overload the remaining second line. This SPS either reduced the output of Montour Units 1 and 2 or tripped the units to alleviate the overload. The SPS is no longer needed with the rebuilt line between Lackawanna and Bushkill and the Susquehanna-Harwood lines being back in service. It is blocked and will be removed in September.

— Suzanne Herel

PJM Transmission Expansion Advisory Committee Briefs

VALLEY FORGE, Pa. — Maryland and Delaware officials are protesting PJM’s proposal to allocate most of the cost of the stability fix at Artificial Island to Delmarva Power & Light ratepayers.

pjmPJM planners expect to present their recommended fix to the Board of Managers on July 27, after a meeting with the board’s Reliability Committee, which is made up of four of the board’s 10 members.

The project has been mired in controversy since planners last summer recommended Public Service Electric & Gas for the job, only to have the Board of Managers reopen the bidding following an outcry from finalists, environmentalists and New Jersey officials. On April 28, planners completed a second review, recommending selection of a proposal by LS Power. Including upgrades by PSE&G and Transource, the project is expected to total more than $200 million. (See PJM Staff Picks LS Power for Artificial Island Stability Fix; Dominion Loses Out.)

The recommendation has drawn comments and complaints from several losing bidders and the public service commissions of Maryland and Delaware, which objected to the cost allocation. The Delaware Public Advocate and Old Dominion Electric Cooperative also raised objections over the allocation.

Steve Herling, vice president of planning, told the Transmission Expansion Advisory Committee that the allocation is based on the location of the solution, not the problem. In this case, while the stability fix affects nuclear generators located in New Jersey, the project would entail transmission terminating in Red Lion, Del.

In its letter to the board, the Delaware PSC estimates that the AI fix could boost Delmarva’s annual transmission revenue requirements by $30 million over the current $121 million, an increase of almost 25%. Ratepayers of ODEC and the Delaware Municipal Electric Corp. also would be affected.

The Maryland PSC echoed its neighboring state’s concern, saying, “We do not view such a cost allocation as reasonably comparable to the benefits received from the project, which we believe would flow equally to at least New Jersey and Pennsylvania residents. Thus, such an allocation of costs, we believe, is in violation of FERC’s Order 1000 cost allocation principles and directives.”

PJM Holds Firm on its Pratts Decision

PJM planners reaffirmed their recommendation to select Dominion Resources and FirstEnergy to resolve reliability problems near Pratts, Va., despite feedback from several stakeholders questioning their decision. (See Tx Developers Challenge PJM Choice on Pratts Project.)

The feedback was received from three entities that were unsuccessful in vying for the project: Ameren, ITC and LS Power’s Northeast Transmission Development.

“We’ve been pretty consistent in the way we’ve been evaluating all the proposals submitted in a proposal window,” said Paul McGlynn, PJM general manager of system planning, noting that the key factors in PJM’s decision were performance, cost and risk associated with siting, feasibility and cost commitment.

PJM will continue to accept comments regarding the decision until July 13. It plans to make its recommendation to the Board of Managers at its meeting July 27.

— Suzanne Herel

PJM Market Implementation Committee Briefs

VALLEY FORGE, Pa. — A months-long debate over whether to create “historic” capacity rights for some load-serving entities took a twist last week when PJM staff returned with a different proposal angled to achieve the same result.

“This has very little similarity, if any, to the previous approach,” PJM’s Jeff Bastian told the Market Implementation Committee on Wednesday.

PJM has been wrestling with how to help the Illinois Municipal Electric Agency meet its internal resource capacity requirements when it needed to use resources located outside of the Commonwealth Edison locational deliverability area to serve its Naperville, Ill., load. (See PJM Debate over ‘Historic’ Capacity Rights Gets a Face: IMEA.)

After failing to gain traction with skeptical stakeholders, staff veered from the notion of “historic” capacity to recommend a proposal that would apply only to Fixed Resource Requirement (FRR) entities — LSEs permitted to avoid direct participation in the Reliability Pricing Model auctions by meeting their capacity requirements using internally owned resources.

Under a proposal approved by PJM, the Independent Market Monitor and IMEA, the internal capacity requirement would not have an effect unless there was price separation for the relevant LDA.

IMEA will put in its offer after PJM defines the auction parameters. If its LDA has price separation when PJM clears the auction, it will be required to meet the internal requirement for the next auction, avoiding the internal capacity rule for only one auction, Market Monitor Joe Bowring explained.

The changes put IMEA where it was before PJM changed the rules regarding the trigger for the internal capacity requirement.

“Within an LDA that is being modeled separately, for reasons other than [Capacity Emergency Transmission Objective or Capacity Emergency Transmission Limit] threshold test or non-zero locational price adder in past three auctions, the FRR entity would not be subject to an internal minimum requirement until the first year after the LDA actually in an auction — or they could resort back to RPM the following year,” Bastian said.

Stakeholders, however, asked for more information regarding the thought process behind the changes before they considered approval.

Proposals Address Tier 1 Synch Reserve Compensation

Committee members were presented with the first read of three competing proposals addressing the issue of how to compensate Tier 1 synchronized reserves.

pjm

Since October 2012, Tier 1 reserves have been compensated at the synch reserve market clearing price (SRMCP) when the non-synch reserve market clearing price (NSRMCP) is greater than $0. While Tier 1 reserves are paid the same as Tier 2, only the latter is subject to penalties for non-performance.

The problem statement the proposals seek to solve asks whether it’s appropriate for such reserves to be credited when they are not responding to a synch reserve event, and if so, how much? (See Monitor: Cut Pay for Tier 1 Synchronized Reserves.)

Tier 1 reserves are made up of on-line resources that are able to ramp up from their current output within 10 minutes in response to a synchronized reserve event.

The proposals come from PJM, the Independent Market Monitor and PJM’s Industrial Customer Coalition.

The PJM proposal would retain the status quo of paying Tier 1 reserves the SRMCP when the NSRMCP is greater than zero. The ICC recommends paying the non-synch reserve price in that scenario. The Monitor says Tier 1 resources should not be paid except during a synch reserve event.

PJM’s proposal alone would impose an obligation on Tier 1 resources to respond, with a refund owed for nonperformance.

Independent Market Monitor Joe Bowring said the payments to Tier 1 resources are an unnecessary “windfall” that have totaled up to $15 million in the first quarter of this year alone.

“There’s no reason to pay Tier 1 anything additional than what they’re being paid now,” Bowring said. “That’s fully compensatory for what they’re doing.”

Changes Would Allow Earlier Replacement Transactions

The committee will be asked to vote at its next meeting on manual changes that would allow replacement capacity transactions earlier than Nov. 30 prior to the start of the delivery year.

Such replacements would be permitted when the owner of the replaced resource could show the expected final physical position of the resource at the time of the request.

Existing generators could engage in such transactions if they are being deactivated, while new generators could replace themselves if their project is cancelled or delayed. Demand response or energy efficiency resources could be replaced due to the permanent departure of their loads.

Resources replaced would not be able to be recommitted for the delivery year.

— Suzanne Herel

PJM Planning Committee Briefs

VALLEY FORGE, Pa. — PJM will propose a two-tiered fee schedule for proposed transmission projects, officials told the Planning Committee last week.

Instead of asking for $30,000 to study any project costing at least $20 million, it will request that amount only for projects of at least $100 million.

For projects between $20 million and $100 million, PJM will recommend collecting a fee of $5,000.

The $30,000 fee proposal was approved Feb. 26 by the Markets and Reliability and Members committees after the Federal Energy Regulatory Commission rejected as discriminatory a previous plan to apply the charge to all greenfield projects but not upgrades of less than $20 million. (See FERC Rejects Fee on Greenfield Transmission Projects.)

“Because we put this threshold in place, we were going to be collecting for a larger number of projects,” PJM’s Fran Barrett told the committee. “Staff said that we could find ourselves over-collecting.”

The Planning Committee will be asked to approve the proposal, which would be tested over a two-year period, at its next meeting on July 9.

The fee schedule would be applied based on the cost estimates presented by those proposing the projects.

“If it turns out that a lot of people are trying to get around that with [estimates of] $99,999,000 we’ll have to revisit it,” said Steve Herling, vice president of planning.

Task Force Would Create Standards for Order 1000 Projects

A problem statement and issue charge introduced on first read Thursday would create a task force to develop minimum design standards for competitively solicited greenfield projects under FERC Order 1000.

The idea arose from concern that the designated entities for such projects would not be required to follow the design standards of the zonal transmission owner.

“We don’t want this new product to fix one problem but introduce a weak point in the system,” PJM’s Suzanne Glatz said, reflecting stakeholder feedback.

The design standards would apply to transmission lines, substations, and system protection and control design and coordination. They would take into consideration geography and physical and local needs of the project.

The task force would be open to all PJM stakeholders and would report to the Planning Committee.

Still Searching for Ways to Incent Early Project Submissions

The committee endorsed a problem statement and issue charge to find ways to incent customers to submit transmission projects earlier in the queue window.

pjm
(Click to zoom)

The issue will be assigned to the Planning Committee, which will have three to six months to identify better incentives to encourage earlier participation. (See PJM to Try Again to Speed Interconnection Filings.)

The imposition of non-refundable fees that escalate later in the queue window have had little effect on changing participants’ behavior, said Dave Egan, manager of interconnection projects.

Meanwhile, those who have done their due diligence in their submittals are being held up by late, deficient entrants, PJM says.

— Suzanne Herel

Duke, ODEC Denied ‘Stranded’ Gas Compensation

By Michael Brooks

The Federal Energy Regulatory Commission last week rejected requests by two PJM generators seeking the recovery of “stranded” natural gas costs incurred during the polar vortex last year.

But the commission also ordered PJM to change its Tariff to allow generators to submit day-ahead offers that vary by hour and to update their offers in real time. PJM is the only RTO that doesn’t allow such variable offers.

pjmDuke Energy (EL14-45) and Old Dominion Electric Cooperative (ER14-2242) both argued that they were owed compensation due to the events of January 2014, when a cold snap sent gas prices soaring. Duke purchased $12.5 million worth of natural gas for its Lee plant in Illinois, only to have it not called on in real time. Similarly, ODEC complained that PJM canceled multiple dispatches that left gas it had purchased for its plants unused.

ODEC also said its plants’ operating costs on Jan. 23, 2014, exceeded what it could recover in the day-ahead market due to the $1,000/MWh offer cap at the time. The co-op asked for an extension of the waiver FERC granted PJM on Jan. 24, which allowed capacity resources to receive make-whole payments if their costs exceeded the offer cap for a limited time.

Duke, which was able to resell some of its gas, sought $9.8 million, while ODEC said it was due nearly $15 million.

Different Arguments, Same Result

While PJM supported the companies receiving one-time waivers, FERC denied both requests, citing its rules against retroactive ratemaking. The commission said that in both cases, ratepayers had not given prior notice that they would be responsible for natural gas-related costs.

Additionally, FERC disagreed with Duke’s assertion that it was due indemnification under section 10.3 of the PJM Tariff, which the company claimed required PJM to hold it harmless for obligations to third parties as a result of directives from the RTO. Duke told FERC that PJM had effectively ordered it to buy gas on Jan. 27, as it was likely Lee would be called upon to maintain reliability.

Although PJM supported the waiver requests, it said it was not permitted to provide Duke relief under the Tariff. “Any extension of section 10.3 to cover the type of loss Duke incurred under the circumstances at issue would read the indemnification provision into a blanket insurance policy for losses of whatever sort, caused by accident, act of God or plain misfortune that a market seller may incur in responding to PJM dispatch,” PJM told FERC in response to Duke’s complaint. (See PJM Backs Duke’s $9.8M ‘Stranded Gas’ Claim.)

FERC agreed with PJM’s interpretation of the section. “The PJM indemnification provision should not be interpreted to guarantee reimbursement of a generator’s losses on gas purchases incurred in meeting its capacity resource obligations in PJM,” the commission said. “Fulfilling its energy market commitments are among the risks the generation capacity resource has assumed … when choosing to participate in the market.”

FERC also disputed Duke’s claim that PJM’s communication with Duke on Jan. 27 constituted a “directive” by the RTO. FERC said that PJM was merely advising that Lee was likely to be dispatched for reliability reasons.

And while PJM’s Independent Market Monitor objected to ODEC receiving compensation for its purchases of gas, it supported the co-op’s request to extend FERC’s waiver by a day in order to receive $2.7 million in make-whole payments. FERC said it saw no difference between the requests.

Offer Flexibility

FERC, however, found that PJM’s Tariff may be unjust and unreasonable because it does not allow generators to submit offers in the day-ahead market that vary hourly or to update their offers in the real-time market. ISO-NE gave its generators that flexibility in December, leaving PJM as the only RTO that does not allow such changes. (See related story, ISO-NE Prices Down Sharply in Q1; Generators Using Offer Flexibility Rule.)

The commission said it expects PJM to implement new rules allowing such changes by Nov. 1 and said refunds would be effective with the order’s publication in the Federal Register. PJM was ordered to report within 30 days on its planned response (EL14-45, EL15-73).

In April, the Markets and Reliability Committee authorized the creation of the Generator Offer Flexibility Senior Task Force to consider how to implement the changes under a problem statement proposed by Calpine, which is seeking $3.3 million in compensation for stranded gas-related costs (ER15-376). (See Bid for Generator Price Flexibility Draws Debate over 10% Adder.) The commission has not ruled on Calpine’s request.

Moeller Dissents

Commissioner Philip Moeller agreed with the majority that PJM’s Tariff was potentially unjust due to the lack of offer flexibility, but he said that he was “troubled” that it was unwilling to grant the companies any relief.

PJM’s “inflexibility contributed to the inability of generation units … to recover legitimate fuel costs,” Moeller said in his dissents to the orders. The companies “acted in good faith to preserve system reliability during a time of extraordinary system stress and deserve appropriate compensation.”

Moeller also said that the majority ignored the companies’ arguments and applied “an overly narrow reading of the prior notice rule and prohibition against retroactive ratemaking to find that ratepayers somehow lacked adequate notice that they would, in fact, be responsible for paying the cost of services provided to them to ensure resource availability during system emergencies.”

The complaints should have at least been set for hearing and settlement judge procedures, he said.

Lake Champlain Cable into New England Progresses

By William Opalka

The second transmission line proposed to bring Canadian hydropower into the Northeast under Lake Champlain has advanced with the release of its draft environmental impact statement.

transmission
(Click to zoom.)

The New England Clean Power Link, proposed by Transmission Developers Inc.-New England (TDI-NE), is a high voltage, direct current line that would transport 1,000 MW of electricity 154 miles from Quebec to Ludlow, Vt. Ninety-eight miles of the cable would be buried under Lake Champlain, and most of its land-based route would be underground.

The U.S. Department of Energy released the draft on June 3 for the $1.2 billion for the project, which it says should be issued a Presidential Permit, required for the border crossing.

TDI also is planning another 1,200-MW line using a path underneath the lake and through existing rights-of-way to New York City. This project is furthest along the regulatory path, having received its final permits in April. (See Quebec-NYC Tx Line Clears Final Regulatory Hurdle.)

A third high-voltage transmission line proposed to transport Canadian hydropower into the Northeast, Eversource Energy’s Northern Pass in New Hampshire, is expecting its final EIS next month, as its review is taking longer than expected to complete. (See Eversource: Northern Pass Delayed Until ’19; Earnings Up.)

TDI-NE touts the Vermont project as a way to deliver renewable energy from Canada to the ISO-NE market. The company estimates that the regulatory process will take until the end of the year, with construction starting in 2016. The project is expected to be in service by 2019.

TDI-NE still needs permits from Vermont and has yet to announce customers for its electricity.

The release of the draft opens a 60-day comment period that is scheduled to close on Aug. 11.

Connecticut Officials at Odds over Plant Clean-up, Merger

By William Opalka

Connecticut environmental officials are at odds with utility regulators over whether the state should seek cleanup of an abandoned power plant as a condition for Iberdrola’s acquisition of UIL Holdings.

connecticutAttorney General George Jepsen, the state Department of Energy and Environmental Protection and the City of New Haven see the merger as the best chance to clean up the contaminated site in the city, but the Public Utilities Regulatory Authority doesn’t seem inclined to force the issue.

Spanish conglomerate Iberdrola announced in February it would acquire UIL Holdings, which has electric and gas units in Connecticut and Massachusetts, in a $3 billion cash and stock deal. (See Iberdrola Broadens Northeast Footprint in $3B UIL Deal.)

English Station

The power plant that has emerged as a flashpoint is the English Station, a coal- and oil-fired generator that dates to the 1920s and sits on a man-made island in the Mill River. The plant was shut down by United Illuminating, the electric utility subsidiary of UIL, in 1992 and sold eight years later.

The new owner intended to revive the plant, but environmental problems killed that plan. It was later sold to a real estate developer.

State environmental regulators have closed the site pending an estimated $30 million cleanup of toxins. DEEP’s environmental remediation order for the site — while not yet final — would require UI and the subsequent owners to clean up the site.

In a brief filed June 5, the attorney general said the state should require the merger applicants to place $30 million in an escrow fund to pay for cleanup of the site, with an additional promise that Iberdrola pay any additional costs more than that amount. Jepsen said UIL “bears a significant portion of responsibility” for the contamination.

The utilities and PURA say that the environmental issues are beyond the scope of the merger.

‘Devoid of Evidence’

In a reply filed Friday, the companies rely on a recent PURA order that removed English Station from the merger’s consideration. “The record is devoid of any evidence upon which the authority could base a condition such as that recommended by the AG. As such, the authority should not entertain conditions related to matters it has already decided are beyond the scope of the proceeding and its authority and upon which it has no record evidence to decide,” they wrote.

PURA had said its docket is not the “appropriate forum” on responsibility for the cleanup.

“English Station property is already the subject of pending legal actions in other appropriate forums such as [DEEP] and the U.S. Environmental Protection Agency,” it wrote in a May order.

FERC Approval

Iberdrola USA owns utilities New York State Electric & Gas and Rochester Gas & Electric in New York, Central Maine Power in Maine and significant wind power assets from coast-to-coast.

The Federal Energy Regulatory Commission approved its takeover of UIL on June 2 (EC15-103).

FERC said acquiring an electric utility in Connecticut and gas distribution companies in Massachusetts and Connecticut presented no significant concerns about the combined companies’ market power.

In the PURA docket, however, Jepsen has listed other objections to the takeover, joining the state’s consumer counsel in saying consumer benefits promised by the merging companies are elusive or non-existent.

Municipal Eligibility for RTO Adder Questioned by MISO

By Chris O’Malley

MISO and its Transmission Owners sector have raised doubts about the eligibility of some municipal transmission owners that are seeking a 50-basis-point RTO adder, asking the Federal Energy Regulatory Commission for clarification in separate filings.

Last week, MISO filed a limited protest to a compliance filing it submitted last month on behalf of several municipal TOs who requested an adder as an incentive for RTO membership. FERC had ordered MISO to make it clear that only municipals that have turned over functional control of their transmission to MISO, or provide service over non-transferred transmission facilities with MISO acting as agent, may receive the RTO adder. MISO also said that all of the municipals who are seeking the adder fulfill these requirements.

MISO’s protest seeks to clarify that non-integrated facilities for which a TO receives credits under section 30.9 of the MISO Tariff are not eligible for the RTO adder (ER15-1067).

In its protest, the TO sector asked FERC to reject the compliance filing outright, asserting that MISO had not adequately fulfilled the commission’s requirements in its revisions.

“While the Tariff language submitted in the compliance filing appropriately limits the collection of the RTO adder, the compliance filing appears to state that certain municipals that do not meet these requirements but instead only use Attachment O of the MISO Tariff to calculate their revenue requirements for credits under section 30.9 of the MISO Tariff, are eligible to collect the RTO adder,” the TOs said.

MISO filed on behalf of the Municipal Energy Agency of Nebraska, the Central Minnesota Municipal Power Agency, Cedar Falls Utilities and about 15 member cities, boards and agencies.

Federal Briefs

epaAn Environmental Protection Agency study of the practice of hydraulic fracturing found no evidence of widespread water supply contamination — but the agency said there is still a potential risk. The draft report detailed several instances where the practice — known as fracking, which has contributed to a domestic oil and gas boom — contaminated some drinking water supplies. It noted, however, that the number of instances was small considering the number of wells examined in the study.

The study examined more than 3,500 reports, studies, articles and other sources. It said that more than 25,000 wells were fracked each year between 2011 and 2014. EPA determined that there were about 6,800 public water systems within a mile of a fracked well.

Both supporters and opponents of fracking seized on the results. The draft report shows that “hydraulic fracturing is being done safely under the strong environmental stewardship of state regulators and industry best practices,” according to Erik Milito, director at the American Petroleum Institute. But Michael Brune, executive director of the Sierra Club, said the report vindicated arguments against the technique. “The EPA’s water quality study confirms what millions of Americans already know — that dirty oil and gas fracking contaminates drinking water,” he said.

More: The New York Times

Cardin Introduces Bill to Close Fracking ‘Loopholes’

Cardin
Cardin

A U.S. senator has introduced a bill that will close what he calls “loopholes” that exempted some of the processes used in hydraulic fracturing from the Clean Water Act.

Sen. Ben Cardin (D-Md.) introduced the Focused Reduction of Effluence and Stormwater Runoff Through Hydraulic-Fracturing Environmental Regulation (Fresher) Act. Exemptions in 1987 and 2005 exempted fracking from certain provisions of the Clean Water Act involving collection and disposal of stormwater runoff and byproducts.

Environmentalists applauded the measure. “It’s well past time for the oil and gas industry to be held accountable to our core environmental laws,” Rachel Richardson, director of Environment America’s Stop Drilling Program, said in a statement.

More: The Hill

House Bill Would Cut EPA Budget by 9%

AppropriationsSourceGovHouse Republicans have crafted a spending bill that would cut the Environmental Protection Agency’s budget by 9% and slice its workforce to 15,000, down from a high of about 17,300 five years ago.

The bill, made public by the House Appropriations Committee, also covers the Department of the Interior and the Smithsonian Institution, as well as other agencies. Altogether, it set spending at $30.2 billion, about $246 million below last year’s budget and $3 billion less than the Obama administration requested.

“These reductions will help the (EPA) streamline operations, and focus its activities on core duties, rather than unnecessary regulatory expansion,” the committee said in a press release.

More: Associated Press

DTE Energy Gets NRC Nod to Build New Reactor

GE-Hitachi Nuclear ESBWR
GE-Hitachi Nuclear ESBWR

The Nuclear Regulatory Commission has approved DTE Energy’s plan to build and operate a new reactor at its Fermi site. Although the company has not yet committed to go ahead with the project, NRC approved plans to build a third unit at the existing 1,170-MW plant near Newport, Mich.

DTE is considering building a GE-Hitachi Nuclear Energy Economic Simplified Boiling Water Reactor (ESBWR) that will be rated at approximately 1,535 MW. It has passive safety features, such as the ability to cool itself for a week in the case of a complete power loss.

The company worked six and a half years to attain the combined operation license. The project is the fifth reactor nationwide to receive a combined license. “The potential of additional nuclear energy gives us the option of reliable, baseload generation that does not emit greenhouse gases,” said Steven Kurmas, DTE’s president and COO.

More: Zacks; Energy Online; Detroit Free Press

Entergy to Appeal ‘White’ Finding Levied by NRC at Pilgrim

PilgrimSourceNRCEntergy is appealing a Nuclear Regulatory Commission sanction assessed following the shutdown at Pilgrim Station during a winter storm. NRC found that the scram was caused by a sudden loss of outside power during the storm and gave the power station a “white” safety finding.

“One of the complications during the shutdown involved the use of safety relief valves to reduce reactor vessel pressure as part of the reactor cool down process,” according to the NRC report. “During attempts to open one of the plant’s safety relief valves, the valve did not open based on observed system response. Plant operators safely completed the cool down using two other of the plant’s four safety relief valves.”

The inspectors said the operators should have anticipated the safety valve issue. Entergy says it has addressed all the safety concerns raised by the report, and that it will seek to have the “white” finding reduced.

More: Mattapoisett Sentinel

Atlantic Coast Pipeline Opponents Say Meeting Transcripts Garbled

AtlanticCoastPipelineSourceDominionOpponents of the proposed 550-mile Atlantic Coast Pipeline (ACP) were shocked when they read transcripts of the Federal Energy Regulatory Commission scoping meeting where they spoke and were unable to make sense of how a stenographer recorded their comments.

In many cases, opponents say, their transcribed comments from a March 18 meeting in Nelson County, Va., were so “garbled” that it is “literally incomprehensible,” according to Joanna Salidis, president of Friends of Nelson.

One resident said at the meeting: “The one-mile swath of pipeline proposed for Shannon Farm would tear up sensitive wetlands and plow through the climax breech forest in our designated wilderness area. It would disrupt our organic gardens, where some members … grow a sizeable portion of their food.”

The FERC transcript reads: “The one hot swath of pipeline proposed for Shannon Farm would tear up sensitive wetlands and plow through the planet’s beech forests in our designated wilderness area and would destruct our organic environments for some members … for a sizeable portion of their food.”

“Again, we see that the agency charged with evaluating whether the ACP’s benefit to the public outweighs its harm does not take public concerns seriously,” Salidis said.

More: Daily Progress

Tidal Power Project Asks for 2-Year License Extension

TidGenSourceCobscookBayTidalThe developers of a tidal power project off Eastport, Maine, are asking the Federal Energy Regulatory Commission for a two-year extension of its license to complete testing of some technology.

The 300-kW Cobscook Bay Tidal Energy Project, run by Ocean Renewable Power Co., received its license in 2012 and began operations later the same year. Its license was granted as a pilot project, used to study the effect on ocean life and to test hydrokinetic technology.

Pilot licenses are granted to small, short-term projects that must be removable or able to be terminated at short notice. The Cobscook Bay project is ongoing, but the company wants an extension instead of a new license. Although it has been online since 2012, the technology is not suitable for commercial applications.

More: HydroWorld (subscription required)

MISO Stakeholders Voting on Day-Ahead Market Schedule

By Chris O’Malley

MISO stakeholders will complete voting on June 16 on three options for responding to the Federal Energy Regulatory Commission’s final rule on coordinating gas and electric schedules (RM14-2, Order 809). MISO could post ballot results as early as June 19 and announce a decision by June 30 for discussion at the July 7 Market Subcommittee meeting.

miso

Order 809 moved the timely nomination cycle deadline for scheduling gas transportation from 11:30 a.m. to 1 p.m. CT (from 12:30 p.m. to 2 p.m. ET). It also added a third intraday nomination cycle.

MISO and other RTOs are required to make compliance filings by July 23 that move the clearing and posting of the day-ahead market’s results to before the timely nomination deadline — or explain why it is not appropriate within their footprint. During a joint meeting last week of the Market Subcommittee and of the Reliability Subcommittee, Jeff Moore of Ameren asked MISO officials to what degree stakeholder votes will influence MISO’s final decision. “Is MISO going to consider themselves bound by the stakeholder vote? Are there other considerations?”

Kevin Vannoy of MISO said stakeholder votes “are very important to us” but noted a number of considerations are in play, including alignment with other RTOs and scheduling, staffing and market administration issues.

Moore said his takeaway from a natural gas availability study presented earlier in the week led him to believe natural gas supplies appear to be adequate in MISO in the years ahead and asked whether that would affect MISO’s decision regarding the three options presented for the day-ahead market.

“That’s something we’ll discuss as part of our final decision,” Vannoy said.

The three alternatives are:

  1. No changes. The day-ahead market closes at 11 a.m. ET, with next-day forward reliability commitment assessment (FRAC) results posted by 8 p.m. ET.
  2. Align the day-ahead market with the timely gas nomination cycle by closing the day-ahead two hours earlier during daylight saving time (one hour earlier during standard time) and reducing clearing windows by one hour.
  3. Align the FRAC with the evening gas nomination cycle by closing the day-ahead one hour early during daylight saving time and reducing the clearing window by one hour.

The status-quo alternative would require MISO to make a convincing filing with the commission, Joe Gardner, vice president of forward markets and operations services at MISO, told the Electric and Natural Gas Coordination Task Force on June 10.

Gardner said MISO estimates that alternative No. 2 could make available over one year an average of 7,500 MW more generation, while No. 3 could free up about 5,000 MW more than under the current system.

“Units that previously were not able to be considered because they [had] an hour or two longer start-up notification time than other units are able to be considered” in alternatives 2 and 3, he said.

“This allows basically just a few more units to be available for reliability purposes as part of the normal process,” Gardner added. “There is a reliability and an economic benefit.”

Other RTOs

ISO-NE reported last year that system operations had improved following changes it implemented in 2013 to move the day-ahead market and initial reserve adequacy analysis (RAA) timelines earlier in the day. It said the number of units committed in the day-ahead or RAA that were completely unavailable in real time due to gas procurement issues dropped from seven in the winter of 2012/13 to zero in the winter of 2013/14. Over the same period the number of generators with long start-up times dispatched before the day-ahead offer and bid deadline dropped from 12 to zero.

PJM, which currently posts its day-ahead results at 4 p.m. ET, is considering ways to post its results by 1 p.m., an hour before the first gas nomination deadline at 2 p.m. (See PJM Markets and Reliability Committee Briefs, “Members OK Gas-Electric Initiative.”)

Importance of Stakeholder Votes

During Friday’s MSC/RSC meeting, Lin Franks, senior strategist at Indianapolis Power & Light, said stakeholder votes are important for MISO to have a better understanding of generation owners’ concerns. That came after one stakeholder expressed reservations about MISO releasing to the public comments stakeholders made with their votes. (MISO agreed to withhold release of those comments upon a stakeholder’s request.)

“Fuel assurance is not MISO’s responsibility and that’s at the crux of this issue — managing the risks of natural gas. MISO did an amazing amount of work to formulate options for stakeholders to consider that appear to mitigate most of the concerns and risks we expressed with MISO collectively and individually,” Franks said.

MISO estimates that natural gas-fired generation could rise to 50% of its generation pool in 2016/2017 as coal-fired plants are shuttered in response to the Environmental Protection Agency’s Mercury and Air Toxics Standards. EPA’s proposed Clean Power Plan is expected to increase natural gas use further.