Search
`
November 17, 2024

FERC Rejects Claims that MISO Snubs Generation Alternatives

By Chris O’Malley

The Federal Energy Regulatory Commission last week declined to rehear DTE Electric’s contention that MISO rules put generation developers at a disadvantage in the competition for reliability projects.

misoDTE had sought review of FERC’s September 2014 ruling approving MISO’s requirement that a proposed generator must have filed an interconnection agreement to be considered as an alternative to a transmission solution. The agreement is due before the date MISO must initiate the transmission project to meet its required in-service date.

Comparable Treatment

The commission agreed with MISO that the requirement is comparable to those required for transmission solutions in its Transmission Expansion Plan process (MTEP). FERC also accepted MISO’s compliance filing in response to the commission’s Order 809 transmission planning requirements (OA08-53-005, ER15-133).

To allow generator proposals to progress through the interconnection process, DTE said more time is needed between when MISO identifies a system need and when it approves a transmission facility to meet the need. The time it takes MISO to complete interconnection studies “makes it more likely than not that a generation project could never even be considered by MISO as an alternative to a transmission project,” DTE said.

The company said generation developers won’t have the information they need regarding potential system needs until Sept. 15, when transmission owners must identify and submit new transmission projects within the MTEP process.

FERC said that developers should be able to identify system needs based on power flow models available in June. But DTE countered, “It is far-fetched to believe that a proponent of a generation solution would be able to use that data to determine that a transmission problem existed or even if it could, offer a generation solution to that problem in the allowed timeframe.”

The commission was not persuaded. DTE “does not explain why a generation developer must wait until a transmission facility is proposed before it can identify potential generation solutions to the needs the transmission facility is meant to address,” FERC said. “Just as the proponent of a transmission solution considers system needs to identify potential transmission facilities to meet those needs, so too can the proponent of a generation solution.”

Catch 22?

Developers have until April to submit generation projects — including executed interconnection agreements —  as alternatives to transmission projects that were proposed the preceding September.

DTE disputed the commission’s finding that a generator that may mitigate a particular transmission need is likely being evaluated in the interconnection process long before the April deadline.

The company noted that generators in the interconnection process are considered operational. As a result, it said, any transmission projects identified in the MTEP process will be those needed in addition to generation in the interconnection process, and any new generation alternatives would be precluded from ever being evaluated against the newly identified transmission need.

FERC saw it differently. “If a generation solution that goes through the interconnection process and has an interconnection agreement filed with the commission does in fact address the need, MISO will not identify a transmission facility to meet the need and the generator alternative will have successfully replaced a transmission facility,” the commission said.

Not Viable

FERC agreed with DTE that MISO is unlikely to replace an approved transmission facility with a generation solution if the transmission developer has already begun right-of-way acquisition, completed design and engineering, ordered material and obtained permits.

“That means only that the generation solution did not have the necessary contractual commitments for MISO to consider it a viable alternative to the transmission solution before the transmission solution had to begin being developed,” FERC said.

SPP Markets and Operations Committee Briefs

KANSAS CITY — SPP’s Markets and Operations Policy Committee voted last week to change the annual auction revenue rights allocation system capacity to better match the annual transmission congestion rights (TCR) auction and reduce underfunding.

sppActing on a recommendation by the Market Working Group, the MOPC changed the percentage for the ARR allocation from the original 60% of system capacity to 80% for the seasonal, or shoulder, months. The percentages are unchanged for June (100%) and July-September (90%). The modified revision request will now go before the Board of Directors for final approval.

Those pushing the 60% allocation for seasonal months said it was an aggressive number and would solve the TCR markets’ underfunding problem, but they recognized it would cause problems for some market participants.

SPP “staff felt it was really struggling to get this change in,” said Debbie James, SPP’s manager of market design. “While 80% is an incremental improvement, we really need to get rid of the carry forward. We need to match them up.” (Unsettled ARRs are carried forward to be settled in the monthly processes.)

In opposing the original 60% allocation, Xcel Energy’s Bill Grant said, “We thought 100% to 60% was overkill. Eighty percent is probably a better number in our minds.”

“I’m leery about making a change on the fly,” said Bill Dowling of Midwest Energy. “Eighty percent will still mitigate the problem, but it’s not a perfect fix.”

An ARR is a financial right that entitles the holder to a share of the auction revenues generated in the TCR auctions or the right to convert them into TCRs. ARRs were originally designed to be allocated in the annual process, meaning the full system capacity was allocated and only new entitlements were offered in the monthly allocation. In 2012, however, FERC required the monthly process be available to all existing candidate ARRs. However, updates to the full annual allocation were not made after the FERC order, resulting in the mismatch between percentages of ARRs and percentages of TCRs.

Under the current market design, ARRs are allocated based on 100% of system capacity, while TCRs are primarily awarded at 60% to 90%. That has made annual ARRs infeasible, as less available capacity is carried forward to the monthly processes. Many of the previously infeasible annual ARRs are still infeasible in the monthly process. Infeasible capacity held by these ARRs is guaranteed through limit expansion and goes to either the ARR holder as an ARR self-convert or another TCR auction participant.

The MWG recommendation will settle or convert all annual ARRs during the annual process. No ARRs would be carried forward, and infeasible TCRs would be reduced. All residual capacity would still be allocated and auctioned in monthly processes.

The MOPC had an easier time approving the MWG’s Revision Request 93 (Market Registration and Timeline Changes), which cleans up Tariff language and makes it easier to dispatch generation in the SPP footprint, and RR 99 (STRUC With QS Carve Out), which provides more accurate operational information than the current intraday reliability unit commitment process.

The MOPC approved another nine RRs recommended by the MWG as part of the consent agenda, along with four RRs from other working groups.

2017 ITP10 Update

ITC Great Plains’ Alan Myers, chair of the Economic Studies Working Group, updated the MOPC on the group’s work on the 2017 Integrated Transmission Planning 10-Year Assessment, just two months into its 18-month cycle.

spp“Our original intent was to bring you the [assessment’s] entire scope today, but we just have an update,” Myers said. “We expect to bring you something in October with better quality and [that is] more formulaic than we have in the past.”

Myers told members the ITP10 will implement new criteria for modeling future resources, defining bounds around specific resources stakeholders can submit for inclusion in ITP10 and ITP20 studies.

The 2017 study will also rank constrained flowgates’ congestion costs. Up to 25 constraints — with a minimum of $50,000 in annual congestion each — will be identified as economic needs.

The study will use financial advisory firm Lazard’s 2014 Levelized Cost of Energy Analysis, as well as other metrics such as 2012 hourly wind profiles; Department of Energy growth rates and NYMEX futures for natural gas prices; and ABB’s North American Electric Reliability Corp. data for coal, oil and uranium prices.

The ESWG has completed a load and generation review and a survey of anticipated renewable energy mandates and goals. It is currently working on developing the ITP10’s scope and futures, various resource plans and building an economic model.

The model will assume SPP’s 13.6% reserve margin, and 5% and 10% accreditation for future wind and solar resources, respectively.

The study will use three futures revolving around a regional Clean Power Plan solution: one assuming the rule’s regional implementation, a second assuming state-by-state implementation and a third assuming business as usual. Each future also assumes competitive wind, plentiful natural gas (due to hydraulic fracturing), normal load growth and large-scale solar generation development.

Prioritizing Revision Requests

The MOPC approved the creation of a more formal process for prioritizing RRs, including a scoring system and facilitated quarterly discussions open to all stakeholders. If approved by the board, the process would begin with the first two quarterly cycles of 2016.

“This will be transparency stakeholders have never had before,” said Xcel Energy’s Grant, the chair of the Stakeholder Prioritization Task Force, which recommended the changes.

Grant said the new prioritization process would not evaluate projects that don’t clear the working group process. The process would use a standardized scoring tool to rate RRs and enhancements, including capital projects and RRs initially scored by SPP staff and working groups. The results would be tabulated in a portfolio report listing projects, RRs, enhancements, defects and associated data (priority scores, initial cost estimates and target implementation dates).

An open stakeholder meeting would be held each quarter to discuss the report; an updated portfolio and written meeting summary would be published for each MOPC meeting. The committee would review and discuss during its regular member forum.

The SPTF’s proposal addresses a request for stakeholders’ increased transparency and input into the prioritization process.

The MOPC also approved the task force’s request to extend its charter an additional year. “We want to stick around long enough to make sure the process is providing the desired stakeholder input,” Grant said.

RCAR Remedies

The Regional Allocation Review Task Force updated the MOPC on its work on a business practice to correct imbalanced cost allocations. Potential remedies would be added to the Tariff as part of SPP’s Regional Cost Allocation Review (RCAR).

American Electric Power’s Richard Ross, the task force vice chair, said the RCAR II analysis needs to be completed by October 2016. That requires, in turn, transmission topology updates to the RCAR models be completed by Oct.  1, 2015, and member commitment to provide the necessary help.

“We need creative solutions, because the process is not working as well as it was intended,” Ross said.

SPP staff has been developing a strawman business practice in coordination with SPP’s Regional State Committee, documenting remedies and clarifying their implementation. Remedy requests and any changes to the business practice would go to the RARTF.

The business practice comes in response to FERC’s rejection of a February 2015 filing that would have added remedies to Attachment J of the Tariff.

Xcel Energy protested the filing, asking the commission to reject the proposed remedies and have SPP develop modifications to the existing methodology for new transmission projects. Rather than refile, the RARTF directed SPP staff to create a strawman business practice.

Transmission Planning Improvement Update

The Transmission Planning Improvement Task Force reported good progress since its formation in the spring. The team has met four times, said Jason Atwood of Northeast Texas Electric Cooperative, with a goal of making transmission planning’s model building, transmission assessment and engineering services “bigger, better and quicker.” It will spend the next few months looking at futures, scenarios and sensitivities.

The task force is discussing whether to conduct the 10-year, near-term and transmission-planning assessment studies at the same time in an 18-month overlapping process, which would produce study results on an annual basis. Atwood noted an annual basis could provide more accuracy.

Wind, Solar Ratings Unchanged

The Generation Working Group recommended no changes to SPP’s methodology for establishing net capability for wind and solar facilities. SPP currently requires that wind resources’ ratings correspond to the load-serving members’ peak hours. The GWG’s data indicate that the value varies from 5% to more than 50%, dependent upon location and timing of peak load.

“This confirms the methodology that the wind resource’s planning capability should be based both on location and tied to load,” the GWG’s report said. The report also confirmed the current default value of 5% used for facilities in commercial operation for three years or less “is reasonable.”

Charter Revisions OK’d in Preparation for Integrated System

The MOPC approved charter revisions for five working groups, allowing them to add Integrated System representation when the IS joins SPP on Oct. 1. Business Practices will go from 10 to 12 members, Economic Studies from 14 to 18, Operating Reliability from 12 to 17, Operations Training from 11 to 15 and Reliability Compliance from 15 to 17.

The committee also approved a name change for the Reliability Compliance Working Group — subbing “regional” for “reliability” — accurately reflecting the group’s purpose and scope. It also gave the go-ahead to a revised scope for the Economic Studies Working Group to allow for additional reviews and approvals of items that align with its knowledge base and current Tariff processes.

‘Incredible Improvement’ in Reliability

Noting a continued decreased trend in violations, Ron Ciesiel, general manager of SPP’s Regional Entity, reported to the MOPC only one category 1 event — a loss of an hour or more of monitoring or control at a control center — was analyzed in the second quarter.

Ciesiel also said the SPP RE has completed its ninth consecutive quarter without a vegetation-contact report. SPP was the last region in the NERC to report a contact, in the first quarter of 2013.

Ciesiel also noted that there are some days in which NERC has no reportable incidents in all of North America.

“That is an incredible improvement from where we were eight years ago,” he said.

— Tom Kleckner

SPP Z2 Project Team Still Grappling with Problem’s Size

By Tom Kleckner

KANSAS CITY — SPP’s Z2 credit project, years in development and the source of much member frustration, is on track to be completed in 2016. But those involved say they can’t estimate the size of the bills SPP may be handing out as a result.

“We don’t know if this is a bread box or a semi-trailer yet,” said Dennis Reed, chair of the Regional Tariff Working Group, who briefed the Markets and Operations Policy Committee last week.

The purpose of the project is to create software that would properly credit and bill transmission customers for system upgrades under Tariff attachment Z2. The problem has been trying to avoid over-compensating project sponsors and include a way to “claw back” revenues from members who owe SPP money for other reasons. Accounting for transfers of reservations has also been a challenge.

“This policy decision was made 10 years ago … we didn’t plan for [the bills] to build up over time,” said Kansas Power Pool’s Larry Holloway, one of several members expressing frustration. “I asked SPP at the time if they had enough Commodore 64s to get this done, and they said they did.”

Reed, director of FERC compliance for Westar Energy, said his group and SPP staff are working to estimate the amount of crediting, but he noted an accurate number can’t be made until the software is completed.

“We have to go through the bulk of the process before we know what the numbers will be,” explained SPP Chief Operating Officer Carl Monroe.

Reed said possible methods of phasing in catch-up payments are also being developed.

Reed said installment payments would help “the smaller entities who don’t have big budgets — say a small city — that all of a sudden [are] faced with a huge bill.”

Reed said the RTWG would bring back some ideas to the October MOPC meeting that “may or may not require” a Tariff filing.

Accenture, which helped SPP implement the Integrated Marketplace on time and on schedule last year, has been hired to manage the Z2 project. The company expects to have a production-ready system built and tested by the end of January 2016.

Following the system’s implementation, SPP will begin the process of calculating past billings and payments, billing customers and paying those who funded network upgrades. Monthly billing will be a change for current long-term service customers.

“The number is going to come out. We can’t predict it, but the cloud of uncertainty is there,” said Aundrea Williams of NextEra Energy Resources. “I need to get ready for the number and to start planning for it.”

SPP Frustrated over Transmission Project Overruns

By Rich Heidorn Jr.

KANSAS CITY — SPP members approved four over-budget transmission projects and sent three others back to the drawing board last week amid widespread criticism of the process used to estimate project costs.

spp
SPP Director of Planning Antoine Lucas makes a presentation to the Markets and Operations Policy Committee as board members Harry Skilton and Phyllis Bernard (front row) listen.

Of 30 committed projects resulting from the 2015 near-term (ITPNT) and 10-year (ITP10) planning processes, 23 are facing cost estimate increases exceeding 30%, SPP officials told the Markets and Operations Policy Committee last week. Three projects are coming in more than 30% below estimates with only four within the 30% “bandwidth.”

Describing a 152% increase on the Hobart-Roosevelt Tap-Snyder rebuild in American Electric Power territory in Oklahoma, SPP Director of Planning Antoine Lucas said “it makes us question whether this was the right project.”

“I find this really appalling,” SPP Board Chairman Jim Eckelberger said. “We’ve taken a huge step backwards. We need a procedural adjustment.”

A third-party engineer estimated the project — rebuilds of a 10-mile, 69-kV line from Hobart to Roosevelt and an 18.7-mile, 69-kV line from Roosevelt to Snyder — would cost $14.3 million.

SPP now expects it to cost $36 million due to additional right-of-way acquisition; licenses and permits; additional substation work; and costs related to a crossing through Mountain Park Wildlife Management Area. SPP also cited AEP’s recommendation that the project be designed anticipating an eventual conversion to 138 kV.

Fire the Engineer

SPP should fire the third-party engineer “and never use him again,” Eckelberger said, drawing applause from many of the about 120 in attendance.

“I’ve seen this over and over again,” Director Julian Brix complained. “This is not a 69-kV project [as originally approved by SPP]. It’s a 138-kV project. This is not the first or second or third time we’ve seen this. This is why we get into trouble with the [Regional State Committee],” he said, referencing state regulators who must collect from ratepayers for transmission upgrades.

AEP officials said the use of 138-kV standards was responsible for only $400,000 of the additional costs. “A no-brainer,” AEP’s Richard Ross said. AEP’s Terri Gallup called complaints of “scope creep” unfair, saying the company had proposed the rebuild as a 138-kV project — that would initially be operated at 69 kV — to begin with.

Xcel Energy’s Bill Grant noted that incumbent transmission owners would become responsible for providing cost estimates for non-competitive projects under a plan approved by the MOPC earlier in the meeting. (See related story, “Initiative on Non-Competitive Studies Advances” in SPP Strategic Planning Committee Briefs.) “I think we have a solution,” Grant said.

Marguerite Wagner of ITC Holdings said transparency would improve the process, calling for release of cost estimates to stakeholders. “If a project is not competitive, how is releasing the cost estimate competitive information?” she asked.

Director Harry Skilton said the cost estimate increases represented a “lesson learned” as the RTO begins considering competitive projects. “We’re going to need a feedback loop” regarding costs, he said.

NTCs Withdrawn

SPP planners recommended that notifications to construct (NTCs) for seven projects with the largest overruns be suspended and the projects restudied, including the Hobart-Roosevelt project.

But Gallup said Hobart-Roosevelt and two other AEP reliability projects on the list had in-service dates that might not be met if they were delayed for more study.

The MOPC ultimately voted to retain the three projects and one in Westar territory, suspending NTCs for only three of the seven recommended by planners: South Shreveport-Wallace Lake 138-kV rebuild (AEP); Martin-Pantex North-Pantex South-Highland Park 115-kV reconductor (Southwest Public Service); and Iatan-Stranger Creek 345-kV voltage conversion (Westar/KCP&L Greater Missouri Operations).

SPP Members Reluctantly OK Day-Ahead Change

By Tom Kleckner

KANSAS CITY — SPP’s Markets & Operations Policy Committee voted to move the deadline for day-ahead market offers up 90 minutes to 9:30 a.m. CT, following a lengthy discussion about whether the benefits justified the change and its price tag.

sppThe committee approved the recommendation by the Gas Electric Coordination Task Force by voice vote.

Assuming approval by the Board of Directors and the Federal Energy Regulatory Commission, SPP will post day-ahead results at 2 p.m. CT, up from 4 p.m. It also shortens the reoffer period to 45 minutes, with reliability unit commitment (RUC) offers due at 2:45 and results posted by 5:15.

The Tariff changes are a first step in complying with FERC’s Order 809, which moved the timely nomination cycle deadline for gas to 1 p.m. CT from 11:30 a.m. and added a third intraday nomination cycle (RM14-2). The commission ordered RTOs to adjust the posting of their day-ahead energy market and reliability unit commitment process results “sufficiently in advance” of the revised gas cycles, or explain why it is not suitable for their markets.

‘Very Little Gain’

SPP’s northern members voiced their continued opposition to the recommendation, saying the adjustments did little to increase the knowledge of next-day gas prices.

“Most winter gas doesn’t trade until 10 p.m.,” said the Omaha Public Power District’s Troy Via.

“I’m really surprised we went down this route,” said Lincoln Electric System’s Dennis Florom. “We see very little gain. We’re making a lot of adjustments, but we’re not getting the key benefit — a timely nomination. By making this adjustment, we are moving further away from the next operating day.”

The Nebraska Public Power District’s Paul Malone, the MOPC’s vice chair, noted that while the GECTF’s recommendation was approved by four lower stakeholder groups, the votes were far from unanimous. The Market Working Group, for example, voted 7-5 in favor with five members abstaining. (See SPP Moving to 9:30 Day-Ahead Close.)

Malone contended FERC’s order was intended to address “critical” gas days.

“This is a change for all days,” Malone said. “The real value we see is better pricing discovery. To get a half-hour change … we’re just struggling with that.”

The revised timeline would not provide day-ahead market results before the 1 p.m. CT nomination deadline, but it would provide 30 minutes before the Intraday 2 nomination. RUC results would be available 45 minutes before the 6 p.m. evening gas nomination.

Enhanced Combined-Cycle Project

In presenting the GECTF’s recommendation, Oklahoma Gas & Electric’s Jake Langthorne said the changes would provide an opportunity to use the evening gas nomination period and provide some price formation in the morning before the day-ahead market closes.

Langthorne also said the move would allow for continued progress with the enhanced combined-cycle project, an effort to provide more sophisticated modeling that captures such plants’ flexibility. The board last year suspended work on the project until after the Integrated System entities join the RTO as full members in October, allowing time for a more thorough cost-benefit study. (See Combined-Cycle Model’s Cost, Benefit Uncertain.)

SPP has estimated it will take approximately $1.5 million and 14 months to implement the schedule changes next year, which would require new software.

SPP Director of System Operations Sam Ellis said “almost 100%” of the spending on the scheduling change would also benefit the ECC project.

“I think $1.5 million is more than enough money,” Ellis said. “Both projects are investments in reducing the market-clearing engine’s solution time.”

Dogwood Energy’s Rob Janssen, a member of the task force, seemed to sway some minds when he expressed a similar long-term view.

“I’m always concerned about costs, but I’m comfortable with this after discussions with staff,” Janssen said. “The staff believes this will improve the market over time. While $1.5 million shows up as a red light, it would be hidden over time the next three to five years. We might as well make the investment and get some value for gas-electric coordination in response to FERC’s order.”

Midwest Energy’s Bill Dowling suggested a shorter RUC process to get gas nominations in as early as possible for the next day. He added, “I do find it compelling to spend some of this money on the ECC project.”

Company Briefs

AlliantSourceAlliantAlliant subsidiary Interstate Power & Light is retiring or switching five Iowa power plants from coal to natural gas and upgrading two other Iowa coal-fired plants as part of a settlement with the Environmental Protection Agency and the U.S. Department of Justice.

Plants in Cedar Rapids, Dubuque, Burlington, Clinton and Marshalltown will be switched to burn natural gas or retired, and new emissions controls will be installed at its two largest coal-fired plants, in Lansing and in Ottumwa. “The terms we negotiated in this settlement are consistent with our long-term plan for clean energy,” said Doug Kopp, Alliant Energy president. “We settled with the EPA to avoid unnecessary delays and ongoing uncertainty associated with litigation.”

The settlement closes out litigation in which the EPA said Alliant upgraded plants in 2006 and 2009 without installing required emissions controls. The upgrades will cost about $620 million, the company said, on top of the $6 million it will spend on environmental mitigation projects and a $1.1 million civil penalty.

More: The Gazette; Journal Sentinel

Kinder Morgan Board Gives Go-ahead for $3.3B Pipeline

TennesseeGasPipelineSourceTGPThe Kinder Morgan Board of Directors approved the $3.3 billion Northeast Energy Direct natural gas pipeline that will run from Wright, N.Y., to Dracut, Mass. But the pipeline will have a smaller capacity than originally estimated.

The 30-inch diameter pipeline to be constructed by Kinder Morgan’s Tennessee Gas Pipeline Company will carry up to 1.3 billion cubic feet per day, down from initial estimates of 2.2 bcf per day. The company said it would amend its application with the Federal Energy Regulatory Commission if circumstances dictated the need to increase capacity.

The project is designed to deliver Appalachian shale gas to New England utilities and power plants. The company said the lack of pipeline capacity caused customers of ISO-NE to pay $7 billion more for electricity during the past two winters than they did during the winter of 2011-12.

More: BusinessWire; MassLive

NRG to Switch Sandwich Plant to Natural Gas

NRG’s Canal Generating Station in Sandwich, Mass., will be returning to service, fueled by natural gas, according to Sandwich town officials.

Town manager Bud Dunham said NRG confirmed that the plant would switch from fuel oil to natural gas. The 1,112-MW plant, formerly a Mirant asset, has been inactive for several years. The repowering project is expected to be completed in 2019.

“After many years of anticipation, NRG let us know they are formally announcing plans for a repowering project in Sandwich,” Dunham said. NRG has not yet made a formal announcement.

More: Wicked Local

Birds Block High-Voltage Project in Wisconsin

RTO-XcelXcel Energy, Dairyland Power Cooperative and WPPI Energy will have to submit a new construction plan to Wisconsin regulators for a high-voltage transmission line under construction near La Crosse to halt activity during a sensitive bird nesting season.

Construction stopped last month in an area where state-protected birds were nesting. The Wisconsin Department of Natural Resources said that a 1-mile section of the project must halt during nesting season, but work in areas outside of the nesting zone will be allowed to continue.

The $500 million, 345-kV line will run between La Crosse and Rochester, Minn.

More: Milwaukee Journal Sentinel

Emera Investing $80 Million in Tiverton Power Station

TivertonSourceEmeraEmera Energy is investing $80 million to upgrade its 265-MW Tiverton power station in Rhode Island, boosting the output of the combined-cycle gas plant by 22 MW and improving its efficiency.

The upgrades to the plant’s gas turbines will save an estimated $1 million per month in fuel costs, allowing it to be dispatched more often by ISO-NE. The project will be completed during a planned maintenance outage in April.

More: Businesswire

Another Coal Company Falls Victim to Low Prices

AlphaNatResourcesSourceAlphaAlpha Natural Resources, a Bristol, Va.-based coal producer, says its shares will be delisted from the New York Stock Exchange because its stock price is too low.

The company said the exchange suspended trading of its shares, which were priced last at 24 cents. Alpha recently announced it was cutting 800 jobs.

Coal mining companies are under stress, especially those in the East, because of low coal prices, low natural gas prices and competition from other states. Patriot Coal in May filed for bankruptcy for the second time in three years.

More: Casper Star Tribune

Newly Crowned Utility King Yet to Find Castle

WECEnergySourceWECWEC Energy Group, the newly created $9 billion merger of Wisconsin Energy Corp. and Chicago-based Integrys Energy, appears to be in no hurry to set up new corporate headquarters.

WEC hasn’t narrowed down a location nor has it hired commercial real estate brokers to assist in the search, WEC spokesman Brian Manthey told the Milwaukee Business Journal. For now, WEC’s center of gravity remains in Milwaukee, the home of the former Wisconsin Energy Corp.

Most of the management in the new WEC Energy consists of Wisconsin Energy executives, including CEO Gale Kappa. WEC said its new headquarters will be in the Milwaukee area but it will retain separate offices for operating units. Wisconsin Public Service Corp., which was owned by Integrys, will keep offices in Green Bay. Integrys’ former Peoples Gas unit will retain divisional offices in Chicago.

More: Milwaukee Business Journal

Xcel’s Monticello Nuclear Plant Running at Increased Output

MonticelloSourceNRCThe Nuclear Regulatory Commission has granted permission for Xcel Energy’s Monticello Nuclear Generating Plant to operate at a higher capacity following upgrades that cost $748 million.

The permission allows the plant in Monticello, Minn., to operate at 671 MW, up 12% from 600 MW.

The NRC action also means Xcel can include the upgrade costs in its next rate case. The cost of the project ballooned from $320 million to $748 million. The Minnesota Public Utilities Commission blamed the problems on Xcel’s “imprudent management” and didn’t allow the company to receive a return on its investment. Xcel wrote off $125 million, nearly half of its first-quarter profits.

More: Star Tribune

Help Wanted at Dynegy

earningsDynegy is on the hunt for corporate employees following a flurry of acquisitions over the last year. The company said it was looking to fill 113 jobs, with some of them needed at its Houston headquarters where about 300 people now work.

Dynegy has made a total of $6.25 billion in acquisitions in the last year. They include the purchase of EquiPower Resources and Brayton Point Holdings. It also snapped up $2.8 billion in commercial generating assets from Duke Energy.

More: Houston Business Journal

Invenergy to Build 200-MW Wind Project in Minnesota

InvenergySourceInvenergyInvenergy announced plans to build a 200-MW wind energy facility near Albert Lea, Minn. The company has been working to obtain landowner agreements for seven years. Invenergy said the 29,000-acre site would have about 100 turbines.

At the same time, MISO is looking at plans to construct high-voltage transmission lines to deliver the power from southern Minnesota to markets.

Invenergy also owns and operates the 357-MW Cannon Falls Energy Center, a natural gas-fired plant that went into operation in 2008.

More: Midwest Energy News

PSEG Long Island Remains Last in Customer Service Ranking

PSEGLongIslandSourcePSEGPSEG Long Island remains last in the country among major electric companies in residential customer satisfaction, but it managed to increase last year’s score by 10%, according to a J.D. Power survey.

PSEG Long Island scored 584 out of a total 1,000 points in the survey, which reviews factors such as power quality, billing, affordability and communications. The utility’s score was 52 points higher than in 2014, when Public Service Enterprise Group took over the Long Island Power Authority. In 2013, LIPA scored 519.

Daniel Eichhorn, vice president of customer services at PSEG Long Island, said the figures showed the utility was the most improved among a list of utilities with more than 750,000 customers. “The numbers tell us we’re very focused on customer satisfaction. We are trying to create a better customer experience, to make it easier to do business with us, and improve reliability.”

More: Newsday

ISO-NE says June Saw Lowest Monthly Prices in 12 Years

ISONewEnglandSourceISONEWholesale power prices in New England fell in June to under $20/MWh, according to ISO-NE. The regional grid operator said it was the lowest monthly price in the 12 years of the competitive power markets and nearly half of the $37.92 price last June.

“It’s supply and demand,” said Matthew White, chief economist at ISO-NE. “With June’s mild weather, demand for natural gas and electricity were both low, and the pipeline capacity was available to deliver a plentiful supply of exceptionally low-priced natural gas.”

White noted that the dip in prices illustrates the seasonal volatility of prices in the New England market, which he attributed almost entirely to natural gas pipeline constraints.

More: ISO-NE

Study: RGGI Added $1.3B, 14,000 Jobs to State Economies

By William Opalka

The Regional Greenhouse Gas Initiative provides substantial economic benefits and has not raised prices or impaired reliability, according to an independent study released at a meeting of state regulators last week.

rggiThe report by economic consulting firm Analysis Group said that RGGI added $1.3 billion in economic value, created more than 14,000 new jobs and saved consumers $460 million on electricity and heating bills from 2012 through 2014.

“Based on an analysis of years of hard data, RGGI shows that multi-state, market-based carbon control mechanisms work and can deliver positive economic benefits,” Analysis Group Vice President Paul Hibbard said. “That’s not to say programs designed to cut greenhouse gas emissions are economic development programs — their goals are different. But the data clearly show that cutting carbon emissions can be a net positive for the economy.”

The report’s authors said the findings “provide valuable lessons for states” preparing for the Environmental Protection Agency’s proposed Clean Power Plan. The report was released last Tuesday at the summer meeting of the National Association of Regulatory Utility Commissioners in New York.

RGGI regulates carbon emissions from power plants in the six New England states, New York, Maryland and Delaware. The states have received about $2 billion in auction proceeds over its existence, investing those funds in energy efficiency programs, low-income assistance and clean energy development.

The report said initial costs are more than recovered in customer savings. “Although CO2 allowances tend to raise electricity prices in the near term, there is also a lowering of prices over time primarily because the states invest so much of the allowance proceeds on energy efficiency programs,” the report said.

rggi

The region also cut annual carbon emissions by about a third, from 140 million metric tons in 2008 to 90 million tons in 2014, according to the report. RGGI also reduced dollars used to pay for fossil fuels imported from outside the region by more than $1.27 billion in 2012-2014.

“The implementation of RGGI over six years has not adversely affected power system reliability in New England, New York or PJM. The pricing of carbon in Northeast and Mid-Atlantic electricity markets has been seamless from an operational point of view and successful from the perspective of efficient pricing of emission control in regional markets,” the report said.

The report was funded the Barr Foundation, the Energy Foundation, the Thomas W. Haas Foundation and the Merck Family Fund.

PJM: Reject DR, EE in Transition Auctions

By Rich Heidorn Jr.

PJM told federal regulators last week they should reject requests to incorporate demand response and energy efficiency in upcoming transition auctions for the RTO’s new Capacity Performance regime.

But the RTO also offered two alternatives for including DR and EE in the auctions, saying the “less risky” option would be to limit participation to previously cleared resources.

Consumer groups and others asked the Federal Energy Regulatory Commission earlier this month to compel PJM to allow DR and EE to participate in the auctions, which begin July 27. (See Regulators, Generators, IMM Seek Changes to PJM Capacity Performance Order.)

Load Forecast Challenge

On Monday, PJM also responded to a separate challenge by consumer advocates who asked FERC to order the RTO to use an improved load forecasting model for the transition auctions and the Base Residual Auction set for Aug. 10-14 (EL15-83).

PJM said the changes in the new model “are yet to be finalized and are not ready to implement.”

“In essence, the complainants seek to utilize the complaint process to supplant a technical regional transmission organization process of testing and review of load forecasting enhancements [that is] still underway.”

Glide Path

PJM said the transition auctions were designed to “provide a glide path” for generation resources that needed time to make investments to meet Capacity Performance requirements and were not necessary for other resources. PJM also said it was concerned about the continuing uncertainty following the D.C. Circuit Court of Appeal’s EPSA ruling voiding FERC’s jurisdiction over DR.

The RTO, however, offered what it called “constructive alternatives” should the commission grant the complainants’ request.

Given the risk that EPSA could be upheld by the Supreme Court, “it is reasonable to limit participation of DR and EE to previously cleared Annual DR and EE for these transitional auctions,” PJM said in its July 15 filing (ER15-623, EL15-29).

PJM said the 1,246 MW of DR and EE that cleared for the 2016/17 delivery year and the 2,828 MW that cleared for 2017/18 could submit sell offers in the transition auctions to convert to a Capacity Performance product.

“PJM cautions the commission from allowing more Annual DR and EE than that which has already cleared from being eligible to participate in the transition auctions. This limitation would allow previously cleared DR to become eligible as Capacity Performance without increasing the magnitude of any unwinding and replacement of DR should the Supreme Court’s ruling be adverse to the commission,” PJM said.

More Risky

The RTO said a “much more risky and less preferred option” would be to allow previously offered but uncleared Annual DR and EE to participate in the transitional auctions. That would allow participation of as much as 4,337 MW for 2016/17 and 8,981 MW for 2017/18.

The practicality of either option is questionable under the current schedule, however. The transition auction for 2016/17 is set for July 27-28 and that for 2017/18 for Aug. 3-4.

PJM said the resources would have to submit updated DR sell offer plans 15 days prior to the auction and EE measurement and verification plans 30 days prior to the auction, as they had to do for participating in the Base Residual Auctions. All of those dates have expired, PJM said.

FERC Rejects Bid to Broaden Scope of Gas-Electric Info Sharing

By Suzanne Herel

Federal regulators last week rejected a request by a natural gas distributor to relax restrictions on its sharing of non-public information received from electric utilities.

The Federal Energy Regulatory Commission dismissed National Fuel Gas Distribution’s request in two rulings. In one, FERC dismissed the company’s request for clarification on communication allowed under Order 787, saying it was beyond the purview of its rulemaking (RM13-17-002). The other rejected NFG’s rehearing request on rules adopted by PJM under the order (ER14-1469-002).

With Order 787, the commission in 2013 opened up the sharing of non-public operational information between interstate natural gas pipelines and public utilities, saying that increased coordination would benefit reliability. (See Talk among Yourselves: FERC Urges Gas-Electric Coordination.)

Impact on Local Distribution Companies

It did not codify, however, how utilities could share such information with local distribution companies, leaving the issue to RTOs and ISOs to address individually through tariff changes. Subsequently, FERC received filings from PJM and NYISO amending their rules. (See FERC OKs Gas-Electric Talk.)

NFG is an LDC serving western New York and northwestern Pennsylvania.

FERC ultimately approved a PJM Operating Agreement change requiring LDCs and intrastate pipeline operators to promise not to disclose non-public, operational information received from PJM to third parties “or in an unduly discriminatory or preferential manner or to the detriment of any natural gas or electric market.” It also barred sharing of the information through a “conduit.”

No intervenors opposed PJM’s proposal, which was approved by FERC in July. But a month later, NFG came forward to say that a blanket restriction forbidding LDCs from disclosing such information to any third party “may inhibit appropriate sharing of operational data and discourage LDCs and intrastate pipelines from maximizing use of the data to improve reliability.”

It pointed out that “third parties” would include pipelines already qualified to receive information under Order 787 and others with whom LDCs need to coordinate to increase reliability.

For example, it said, if an expected increase in a generator’s use of natural gas in one part of the pipeline could affect a load pocket of the LDC, the company would want to be able to warn large customers in that area of an imminent capacity constraint.

NFG also took issue with the notion of requiring LDCs to guarantee their use of data would not be “to the detriment of any natural gas or electric market,” contending that “changing capacity use inevitably affects some retail customers negatively just as changing upstream supplies may affect market participants negatively.”

‘Very Broad’

In denying NFG’s request, FERC said it intentionally made the scope of information-sharing under Order 787 “very broad.” Quoting from the order, FERC added, “The commission is intentionally permitting the communication of a broad range of non-public, operational information to provide flexibility to individual transmission operators, who have the most insight and knowledge of their systems, to share that information [that] they deem necessary to promote reliable service on their system.”

It said that the potential for competitive harm under that broad scope warranted limiting it with a blanket authorization.

When Order 787 was announced, several commenters called the no-conduit rule too restrictive and offered modifications, including exclusions from the third-party restriction. FERC denied those requests.

“PJM states that it intended its restrictions on LDCs and intrastate pipelines to be an extension of the commission’s no-conduit rule to non-FERC jurisdictional facilities, applied in a manner that mimics, as closely as possible, those restrictions,” it said.

‘Untimely’

As for NFG’s request for a rehearing, FERC determined it “untimely and thus statutorily barred.”

It also noted that nothing in PJM’s Tariff precluded NFG or any other entity from sharing non-specific information needed to ensure the reliability of system operations.

“As long as NFG Distribution does not reveal, directly or indirectly, the non-public, operational information shared by PJM (e.g., information concerning a particular electric generator), NFG Distribution can request or direct its customers and operational counterparties to perform specific actions based on such information,” it said.

Talen Entering NYISO in $1.2B Deal

By Rich Heidorn Jr.

Talen Energy announced its first post-spinoff acquisition Monday, agreeing to spend $1.175 billion to purchase 2,500 MW of combined-cycle generation that expands the company’s presence in ISO-NE and marks its entry into NYISO.

talen
(Click to zoom.)

The company, which completed its spinoff from PPL and Riverstone Holdings on June 1, announced it will acquire three generators from MACH Gen: the 1,080-MW New Athens plant in Athens, N.Y.; the 360-MW Millennium plant in Charlton, Mass.; and the 1,092-MW New Harquahala plant near Tonopah, Ariz.

The key to the deal for Talen is the two plants in NYISO and ISO-NE, regions in which the company had previously said it was setting its sights. The acquisition will increase its geographic diversity, reducing PJM’s share of its fleet from 83% to 71% while doubling ISO-NE’s share to 2%.

It also reduces its dependence on coal and nuclear power, with coal’s share of the fleet dropping from 40% to 34% while natural gas increases from 22% to 33%.

All of those numbers will change as a result of the company’s need to divest 1,300 MW to meet market power concerns. Pre-divestiture, the company’s fleet would total 17,600 MW. (See PPL, Riverstone Accept FERC Mitigation Plan on Talen Spinoff.)

Immediately Accretive

Talen said the acquisition brings substantial tax benefits and will be immediately accretive to earnings despite poor “market dynamics” that have limited the Arizona plant to less than a 20% capacity factor, resulting in losses. All three plants are powered by Siemens 501G engines installed between 2001 and 2004.

Talen also said it expects the economics of the Athens plant to improve with the completion of pipelines that will give the plant access to low-cost Marcellus shale gas and electric transmission improvements expected to reduce congestion in NYISO’s Zones F and G.

‘Powder’ for Future Deals

Importantly, said CEO Paul Farr, the deal will retain flexibility to make additional acquisitions. “We still have dry powder given the mitigation process underway,” Farr said in a conference call with stock analysts.

The purchase will be financed with a combination of debt and cash but the precise mix would depend on interest rates and the status of its divestiture efforts, Talen said. The company said earlier this month that it had a $1 billion “war chest” for future acquisitions.

The company is believed to be considering the acquisition of American Electric Power’s merchant fleet in Ohio and Indiana, which AEP announced in January it was putting on the block. (See AEP Considering Sale of 8,000 MW in Ohio, Indiana.)

UBS Investment Research says there is a 50% probability Talen will purchase AEP’s assets. It said Talen could swallow AEP’s assets even after the MACH Gen deal because an AEP deal is not likely to occur until late 2015 or early 2016 because of pending Ohio regulatory proceedings.

Arizona Plant a Throw-In

talen
(Click to zoom.)

It appears that taking on the money-losing Arizona plant was a condition for acquiring the assets Talen did want. Talen, which has no other assets in the region, said it may move the plant elsewhere or sell it for parts.

MACH Gen, which was owned by affiliates of Credit Suisse Group and Bank of America among others, filed for Chapter 11 bankruptcy protection in March 2014, saying it had assets of $750 million and liabilities of $1.6 billion. The company said it had a net loss of $120 million on $350 million in operating revenue in 2013.

The company said the Federal Energy Regulatory Commission’s rejection of its plan to sell the Harquahala plant had undermined its efforts to cut its debt. FERC said the sale — to investors that also owned two of the four natural gas generating units in Gila Bend, Ariz. — would have harmed competition within the Arizona Public Service balancing authority area (EC13-11).

The company said most of its creditors had agreed to a prepackaged reorganization that would give its second-lien debt holders 93.5% of the restructured company and reduce about $1 billion of debt. FERC approved the restructuring in April 2014 (EC14-46).