Search
`
July 30, 2024

FERC Orders PJM to Include DR, EE in Transition Auctions

By Rich Heidorn Jr.

PJM will delay the transition auctions for the new Capacity Performance regime to comply with a Federal Energy Regulatory Commission order that the RTO include demand response and energy efficiency.

FERC ruled 4-1 late Wednesday that the auctions, which were set to begin July 27, would not be just and reasonable without permitting DR and EE resources to participate. PJM must make a filing within 15 days describing how it will comply with the order and setting a new schedule.

The commission ruled in response to a joint complaint by the PJM Industrial Customer Coalition, environmentalists and regulators or consumer advocates from Delaware, D.C., New Jersey, Maryland, Pennsylvania, Illinois and West Virginia. A coalition of DR providers had filed a separate challenge to PJM’s exclusion.

New Schedule

Stu Bresler, senior vice president of market services, told the Markets and Reliability Committee on Thursday morning that the RTO will schedule the transition auctions after the Base Residual Auction Aug. 10-14.

The transition auction for 2016/17 had been set for July 27-28 and that for 2017/18 for Aug. 3-4. In a filing Tuesday, PJM set the 2016/17 auction for Aug. 26-27, with results posting on Aug. 31. The transition auction for the 2017/18 delivery year will be held Sept. 3-4, with results posted on Sept. 9.

PJM had said the transition auctions were designed to “provide a glide path” for generation resources that needed time to make investments to meet Capacity Performance requirements and were not necessary for other resources. PJM also said it was concerned about the continuing uncertainty following the D.C. Circuit Court of Appeal’s EPSA ruling voiding FERC Order 745, which set compensation rules for the resource in RTO energy markets.

FERC said, however, that Tariff provisions barring DR and other non-generation resources from participating in the transition auctions were “unduly discriminatory as applied to technically capable resources willing to perform as a Capacity Performance resource” (ER15-623, EL15-29).

Similarly Situated

“PJM has failed to provide an adequate explanation … as to how non-generation resources are not similarly situated to generation capacity resources for purposes of providing the capacity services PJM plans to procure through the transition auctions,” FERC continued.

The commission rejected PJM’s argument that participation in the transition auctions should be limited to resources that need to make investments to meet performance and fuel assurance requirements. “The purpose of the transition auctions is to procure a more reliable portfolio of capacity resources, and we see no basis for excluding non-generation resources capable of providing that service from participating,” the commission said.

FERC also dismissed PJM’s attempt to justify the prohibition on DR on the uncertainty over FERC’s jurisdiction. The commission’s appeal of the EPSA ruling is now pending before the Supreme Court.

The commission noted that it had previously rejected similar arguments as premature. It also observed that DR and EE resources selected in prior auctions are still expected to deliver on their capacity commitments. (See FERC: PJM Demand Response Stop-gap Measure ‘Premature.)

The commission said PJM must file revisions to Attachment DD of its Tariff to allow all resources that qualify as Capacity Performance to participate in the transition auctions.

In its response to the complainants, PJM offered two alternatives for including DR and EE in the auctions, saying the “less risky” option would be to limit participation to previously cleared resources.

FERC said neither option was sufficient because they would bar participation in the auctions by DR and EE that did not previously submit sell offers for the delivery year.

“PJM’s current [Tariff] does not place such restrictions on generation capacity resources, and the commission finds that PJM has failed to support a disparate treatment of other Capacity Performance resources in its proposed alternatives,” FERC said.

Dissent

Commissioner Tony Clark dissented, saying the order was improper procedurally because the commission had previously approved “unambiguous” Tariff language barring DR and EE from the auctions.

“It is not PJM’s burden to now prove that an already agreed on transition incremental auction methodology is just and reasonable. Rather, it is complainants’ burden to explain why now, just weeks after the commission’s Capacity Performance order and just days before the first transition incremental auction, the plain Tariff reading of Attachment DD, section 5.14D(B)(3) is unjust and unreasonable.”

Commissioner Philip Moeller responded in a concurring statement. “While a close reading of PJM’s proposed Tariff provisions indicates that non-generation resources would be excluded from participation in the transition auctions, PJM’s voluminous filing did not make this fact, or its underlying justification, clear to PJM stakeholders or the commission,” Moeller wrote.

“PJM initially represented that its Capacity Performance proposal ‘preserves its current approach’ to demand response participation, in contrast to its more recent position that it intended to limit non-generation resource participation in the transition auction due to the uncertainty surrounding EPSA.”

Clark also said he agreed with PJM’s call for caution in the handling of DR because of the legal uncertainty.

“Rather than proclaiming, ‘damn the torpedoes, full speed ahead!’ I would prefer a modest approach whereby we avoid buying ourselves more potential trouble and refrain from actively adding more demand response megawatts into PJM’s capacity construct while it faces an uncertain future and possible disorderly ‘unwinding.’ While the pendency of Order No. 745 is not alone dispositive, it should cause us to proceed more cautiously than we are doing here.”

FERC Seeks Supply Chain Protection Against Cyber Threats

By Michael Brooks

Two malware campaigns against vendors of industrial control systems have prompted the Federal Energy Regulatory Commission to propose the development of a new reliability standard.

FERC issued a notice of proposed rulemaking last week that directs the North American Electric Reliability Corp. to develop critical infrastructure protection (CIP) rules for supply chain management to respond to risks to communication networks and related Bulk Electric System (BES) assets (RM15-14).

supply chain“This new type of malware campaign is based on the injection of malware while a product or service remains in the control of the hardware or software vendor, prior to delivery to the customer,” FERC said. The supply chain rules would be part of a revised standard, CIP-006-6 (Physical Security of BES Cyber Systems).

The NOPR seeks comment on that and six other updated CIP standards.

Trojan Horse Viruses

The two malware threats that prompted FERC’s concern are Trojan horse viruses planted in industrial control systems, such as supervisory control and data acquisition (SCADA) and programmable logic controllers (PLCs). One, called Havex, was identified in June by cybersecurity firm F-Secure and was used to conduct espionage against several industrial companies in Europe.

Last fall, the Department of Homeland Security’s Industrial Control Systems Cyber Emergency Response Team (ICS-CERT) issued a warning that a Trojan horse virus dubbed BlackEnergy had been found on Internet-connected human-machine interfaces (HMIs) from vendors including GE Cimplicity, Advantech/Broadwin WebAccess and Siemens WinCC. ICS-CERT also cited public reports of a BlackEnergy campaign against overseas targets that took advantage of vulnerabilities affecting Microsoft Windows and Windows Server 2008 and 2012.

The virus is believed to have been planted as early as 2011 but only activated recently by government-backed hackers in Russia.

Third Time

Highlighting the seriousness of FERC’s concern, Commissioner Cheryl LaFleur noted that the NOPR represented only the third time the commission has ordered NERC to initiate a standard. FERC previously ordered standards addressing geomagnetic disturbances and physical security.

“The work that NERC, the industry and the commission do on cybersecurity must obviously continually evolve to meet the changing nature of the cybersecurity threat, which we all see in the news practically daily,” LaFleur said in a statement. “Understanding the evolving threats and how best to respond to them is of critical importance.”

The NOPR only gave NERC general directions as to what the new standard should include. The commission suggested it could be based on the National Institute of Standards and Technology’s supply chain risk management controls (SP 800-161). The Department of Energy also has offered guidance on cybersecurity procurement for energy delivery systems.

“It’s too early in the process to say what a standard might say or what the terms of it might be,” FERC Chairman Norman Bay said.

The order is intended to protect against malware and other supply chain risks including counterfeits and tampering or theft of data.

The new standard would only apply to registered entities subject to NERC jurisdiction, not vendors supplying them. “At this time we aren’t seeking some sort of broader statutory authority,” Bay said.

“While the commission’s CIP standards don’t specifically cover … supply chain vendors, there is undoubtedly a gap and vulnerability there that’s been identified now for some period of time that I think all of us take very, very seriously,” Commissioner Tony Clark said. “I suppose the main idea is that we’re trying to ensure that security becomes effectively baked into the cake, as it were, from the ground up in the systems that the electric utilities use.”

The commission asked for comment on the proposed standard, including what would be “a reasonable time frame” for its completion. Comments are due in 60 days from publication of the NOPR in the Federal Register.

Transient Devices

While FERC accepted most of the CIP standards as proposed, the commission ordered NERC to provide additional justification for its rules regarding risks posed by “transient” electronic devices such as USB flash drives and laptops.

The commission said it was concerned about NERC’s decision not to include rules regarding use of transient devices on “low-impact” cyber systems, including low-impact control centers.

“Malware inserted via a USB flash drive at a single low-impact substation could propagate through a network of many substations without encountering a single security control under NERC’s proposal,” FERC said. “In addition, we note that low-impact security controls do not provide for the use of mandatory anti-malware/antivirus protections within the low-impact facilities, heightening the risk that malware or malicious code could propagate through these systems without being detected.”

Nonprogrammable Components

The commission also said it was concerned that NERC’s standards provided limited protection for nonprogrammable components of communication systems, such as cabling.

NERC has proposed physical access restrictions and encryption as protections against physical attacks on nonprogrammable equipment, session hijacking attacks within a BES control center and man-in-the-middle attacks — in which an attacker intercepts and may alter data between two parties who believe they are directly communicating with each other.

But it “does not extend protections to real-time data passing between control centers outside of a facility,” FERC said.

The commission ordered NERC to modify CIP-006-6 to require protection of all communication links and sensitive data communicated between all BES control centers.

Other Standards

The other standards tentatively approved by FERC were: CIP-003-6 (Security Management Controls); CIP-004-6 (Personnel and Training); CIP-007-6 (Systems Security Management); CIP-009-6 (Recovery Plans for BES Cyber Systems); CIP-010-2 (Configuration Change Management and Vulnerability Assessments); and CIP-011-2 (Information Protection).

DTE Electric Wins OK to Acquire Gas Peaker

By Chris O’Malley

DTE Electric has won federal approval to acquire a 320-MW natural gas-fired peaking plant from its parent company to help it meet MISO Zone 7 resource adequacy requirements.

The East China peaking station is an indirect, wholly owned subsidiary of DTE Energy, the parent of DTE Electric.

The Federal Energy Regulatory Commission last week asserted that the deal won’t have an adverse effect on competition, saying it amounts to a transfer of generating assets between affiliated entities (EC15-138).

The East China facility was the only resource to respond to DTE Electric’s requests for proposals for simple-cycle generating facilities to meet its reliability requirements.

FERC said the RFP satisfied any concerns over cross-subsidization. “In the context of an acquisition of affiliated generation, a competitive solicitation is the most direct and reliable way to ensure no affiliate preference,” FERC said.

DTE Electric owns and controls about 13,479 MW of generating capacity, plus 4,000 miles of distribution lines. It is the provider of last resort for customer load in its territory.

The East China plant is authorized to make wholesale sales of energy and capacity at market-based rates.

Financial details of the acquisition were not specified.

Last fall, DTE Energy and Consumers Energy warned of a shortage of generation reserves starting next year, noting nine coal-fired plants in Michigan are set for retirement ahead of tighter air pollution regulations.

Consumer groups have accused the utilities of fear-mongering, saying further deregulation of Michigan’s electric market would help ensure the flow of additional power from elsewhere.

PJM Markets and Reliability Commitee Preview

Below is a summary of the issues scheduled to be brought to a vote at the Markets and Reliability Committee on Thursday. Each item is listed by agenda number, description and projected time of discussion, followed by a summary of the issue and links to prior coverage in RTO Insider.

RTO Insider will be in Wilmington covering the discussions and votes. See next Tuesday’s newsletter for a full report.

Markets and Reliability Committee

2. PJM Manuals (9:40-9:55)

Members will be asked to endorse the following manual changes:

A. Manual 01: Control Center and Data Exchange Requirements — Major update and reorganization to Section 5 introducing definitions of two major data types: System Control and Monitoring (Instantaneous) and Billing (Accumulated). Also updates references to OASIS and adds requirements regarding synchrophasor data exchange.

B. Manual 13: Emergency Operations — Includes administrative changes, clarifications and updates. Adds reference to Manual 12 for member actions when PJM loads 100% synchronized reserves and a reference to the instantaneous reserve check process.

3. CAPACITY PERFORMANCE (9:55-10:45)

A. Manual 18: PJM Capacity MarketUpdates the manual to incorporate Capacity Performance. Includes clarifications on non-performance assessments, acceptable replacement resources for CP and Base Capacity commitments, the CP effective date for Fixed Revenue Resource entities and the physical option for non-performance for FRR entities. (See PJM Delays Vote on Capacity Performance Rules.) Members endorsed an update to Section 4.8 of the manual regarding credit requirements at a special MRC meeting July 15. Relevant forms have been posted for member use.

B. Manual 20: PJM Resource Adequacy Analysis — Changes related to the determination of limited-availability resource constraints under Capacity Performance. Because Capacity Performance rules allow participation of limited availability resources for the 2018/19 and 2019/20 delivery years, constraints must be established on Base Capacity DR and Base Capacity generation to ensure reliability. Details of the constraint computation methodology were added as Section 6.

4. FERC Order 1000 Proposal Fee Update (10:45-10:55)

Members will be asked to approve a two-tiered fee schedule for proposed transmission projects. For greenfield projects or upgrades between $20 million and $100 million, PJM will assess $5,000 to cover its study expenses. Projects costing at least $100 million will be charged $30,000. Previously, a $30,000 fee for all projects greater than $20 million had been approved, but planners later realized they likely wouldn’t need to collect that much. (See PJM Lowers Proposed Tx Project Study Fee.)

5. MERCHANT NETWORK UPGRADE (10:55-11:10)

New tariff language is being proposed to more accurately reflect how PJM processes requests for merchant network upgrades. The changes address definitions, queue entry, agreements and the capacity market.

6. TIMING OF REPLACEMENT CAPACITY TRANSACTIONS (11:10-11:25)

Manual changes would allow market participants to enter replacement capacity transactions earlier than Nov. 30 prior to the start of the delivery year if the need is linked to a physical reason that would prevent a participant from meeting its commitment. The changes prohibit generation that is replaced early from being recommitted for the delivery year. (See Earlier Replacement Capacity Transactions Approved.)

7. MARKET DATA CONFIDENTIALITY CLARIFICATIONS (11:25-11:40)

Members will be asked to approve a problem statement and issue charge designed to relax confidentiality rules regarding uplift payments and generator outages. Stakeholders have requested more granular data, especially following severe weather events. Current rules allow the release of aggregate market data only if it includes information about at least three market participants and it is no more specific than a PJM transmission zone. PJM also is prohibited from releasing data that already has been made public elsewhere. As a result, it’s unable to be more specific about such issues as conditions surrounding weather events, closed-loop interfaces and transmission planning. PJM also is offering a proposed solution. (See PJM Considering Release of Uplift, Outage Data.)

8. REGULATION MARKET ISSUES (11:40-12:00)

The Independent Market Monitor will seek approval of a problem statement and issue charge on concerns that PJM is buying too much fast-responding RegD resources in the regulation market. The initiative also will consider changes to the marginal benefit factor that defines that substitutability between RegA and RegD megawatts, which the Monitor says is faulty. (See PJM Market Monitor: Faulty Marginal Benefit Factor Harming Regulation.)

9. MARKETS RELATED GOVERNING DOCUMENTS UPDATE (12:45-1:00)

The PJM Law Department is proposing an initiative to clean up language in the RTO’s governing documents that is “ambiguous, incorrect or requires clarification.” PJM’s proposed problem statement and issue charge would assign the task to the Market Implementation Committee, separating it from an effort already underway involving the Tariff Harmonization Senior Task Force. (See PJM Law Proposes Cleaning up Language in Governing Documents.)

10. FTR/ARR TASK FORCE (1:00-1:15)

Old Dominion Electric Cooperative will seek approval for a proposal that combines recommendations from PJM and the Independent Market Monitor in redesigning the financial transmission rights and auction revenue rights process. (See ODEC Seeks Last-Ditch Vote on Deadlocked FTR/ARR Issue.)

11. TARIFF HARMONIZATION SENIOR TASK FORCE (1:15-1:30)

Members will be asked to approve seven revised definitions, the first batch of changes from the task force. (See Task Force Proposed to Resolve Inconsistencies in PJM Governing Documents.)

— Suzanne Herel

FERC Eliminates Form 566 for Most Filers. So Why Does it Still Exist at All?

By Rich Heidorn Jr.

RTOs, ISOs and exempt wholesale generators will no longer have to file Form 566 (Annual Report of a Utility’s 20 Largest Customers), a minor but annoying requirement.

fercThe Federal Energy Regulatory Commission eliminated the requirement for 82% of the current 1,082 filers in an order last week (RM15-3).

The commission noted that the report is intended to capture sales to end-use customers as opposed to those purchasing for resale. As a result, RTOs and ISOs have had to report only that they had no applicable sales. The same goes for exempt wholesale generators, which by definition cannot make retail sales.

FERC’s order computes down to the dollar the impact of the changes. Eliminating the requirement to provide the name and address of any residential customers will save 29 utilities 15 minutes each a year. In total, the rule change will save $390,312, FERC estimates.

But why did this rule exist in the first place? And what purpose does it serve today? Those answers are nowhere to be found in the 25-page order, which notes only that the form is the result of Section 305(c) of the Federal Power Act, dating to 1935.

FERC’s Frequently Asked Questions provides limited guidance, saying that the commission uses the form along with Form 561 (Annual Report of Interlocking Positions) to “determine whether public or private interests will be adversely affected by the holding of officer or director positions of both a public utility and its customers.”

Have the two forms ever uncovered any problems or resulted in enforcement actions? A FERC spokeswoman couldn’t say Monday.

FERC’s action exempts all but 196 of current filers, who are expected to spend a total of 1,071 hours annually on the paperwork at a cost of $77,094 (assuming an hourly cost of $72/hour).

FERC rejected the Edison Electric Institute’s request to extend the exemption to qualifying facilities or utilities participating in RTO and ISO markets. The commission said utilities participating in organized markets “may well also make sales ‘for purposes other than for resale.’”

“Adopting EEI’s suggestion would virtually eliminate the filing requirement, contrary to the statute,” FERC said.

The commission also declined to exempt transmission-only companies, but it said they may escape filing requirements because the commission is eliminating the reporting obligation for public utilities that make no reportable sales for the preceding three years.

It did, however, adopt EEI’s suggestion that it eliminate the requirement that utilities notify the 20 largest purchasers that their names are being reported.

Federal Briefs

Department of the Interior sealThe Obama administration on Thursday toughened rules to protect waterways from coal mining by requiring mining activity to take place at least 100 feet from streams.

The administration said the updated regulations, which clarify earlier rules, require mines to monitor streams near their operations and call for companies to restore areas impacted by earlier operations. The Interior Department estimates that the rules will safeguard 6,500 miles of streams in the next 20 years.

Industry supporters denounced the new mandate. “It’s no secret that this overreaching rule is designed to help put the coal country out of business,” said Sen. John Barrasso (R-Wyo.). He called the regulation “job-crushing” and “anti-coal.”

More: National Journal

EPA Watchdog Says Agency Should Track Fracking Chemicals

epaThe Environmental Protection Agency’s Office of Inspector General recommended the agency improve oversight of chemicals used in hydraulic fracturing. The OIG said the agency needed to crack down on the unlicensed use of diesel fuel in fracking and figure out whether to mandate public disclosure of fracking chemicals.

Although EPA’s oversight on fracking is limited by a 2005 law, it does have control over the use of fuels and chemicals that could affect the quality of drinking water. The agency has approved the use of diesel fuel in some fracking operations, but the OIG said there are instances where “EPA and primacy states have not been fully successful in their efforts to effectively control the use of diesel fuels for well stimulation.”

The OIG also said the agency should also address calls for the mandatory disclosure of chemicals used in fracking. “To date, however, the agency has not addressed the comments or developed a plan of action for the next steps,” the report said, adding that EPA “needs to develop an action plan with a timeline to address the public comments and determine whether to propose a rule to obtain information on chemical substances and mixtures used in hydraulic fracking.”

More: The Hill

Former DOE Official Tapped for NRC by Obama Admin

Roberson
Roberson

The Obama administration nominated a former Bush administration official to fill an empty seat on the five-member Nuclear Regulatory Commission.

If confirmed by the Senate, Jessie Hill Roberson, who served in the George W. Bush administration as an assistant secretary for environmental management, would be the third new commissioner on the NRC since September.

Roberson has been vice chairwoman and a member of the Defense Nuclear Facilities Safety Board for the last five years. She has held positions with several utilities, including nuclear-power giant Exelon.

More: Washington Examiner; Nuclear Energy Institute

NOAA, Others Say Oceans Hot and Getting Hotter

An annual report by the National Oceanic and Atmospheric Administration and the American Meteorological Society said the world’s oceans are warm and getting warmer.

According to the report, the ocean surface temperatures are the warmest in the 135 years that records have been kept. One reason: About 93% of the heat from burning fossil fuels goes into the oceans, which serve as giant heat sinks. The seas are holding record levels of thermal energy as deep as 2,300 feet below the surface.

The trapped heat in the oceans provides energy that feeds into tropical cyclones, according to NOAA oceanographer Greg Johnson. The report was compiled by more than 400 scientists.

More: Associated Press

Federal Judge Dismisses Oklahoma’s Second Lawsuit Against Clean Power Plan

Egan
Egan

A federal judge on Friday dismissed Oklahoma’s second attempt to block the Obama administration’s climate rule for power plants, saying the state cannot challenge the Environmental Protection Agency’s regulation until it becomes final.

“The court finds no exceptional circumstances that would warrant judicial intervention at this time, and plaintiff’s claims should be dismissed for lack of subject matter jurisdiction,” ruled U.S. District Court Judge Claire Egan of the Northern District of Oklahoma.

It is the second time in two months a federal judge has dismissed an Oklahoma challenge to the Clean Power Plan, both for similar reasons. EPA is expected to issue its final rule next month.

More: The Hill

SPP Strategic Planning Committee Briefs

KANSAS CITY — SPP’s Strategic Planning Committee on Thursday endorsed a plan to make incumbent transmission owners responsible for providing cost estimates for non-competitive projects.

spp

The plan recommended by the Competitive Transmission Process Task Force — Solution 2A — easily cleared the Markets and Operations Policy Committee earlier last week. It adds additional cost analysis of competitive-projects by transmission owners. SPP and third-party vendors would still evaluate competitive projects subject to Federal Energy Regulatory Commission Order 1000.

Although the overall timeline remains the same, Solution 2A adds three and a half weeks of study development, allowing for a better cost analysis, said Xcel Energy’s Bill Grant, the task force’s chair.

“For the projects that have been identified as non-competitive, we will receive the estimate from the transmission owner instead of the third-party vendor,” Grant said. “At this point in time, the project has already been selected. We’re just proving the estimate is non-competitive.”

Carl Monroe, SPP’s executive vice president and COO, said the additional screening “improves the estimating process, so we can give the [SPP] board better information” for selecting projects to build.

Because the process change could require revisions to the Tariff and governing documents, FERC approval will likely be required, along with the normal SPP approval process.

Load Responsibility White Paper

Golden Spread Electric Cooperative’s Mike Wise updated the SPC on the Capacity Margin Task Force’s Load Response Entity (LRE) white paper, which cleared the MOPC earlier in the week. The document is intended to ensure all load served by SPP’s balancing authority has sufficient capacity.

“If an entity is not responsible for a load forecast or contract,” Grant asked during the MOPC discussion, “should the customer be an LRE?”

“The first and most critical step is to make everyone adhere to the policy,” said Richard Ross of American Electric Power. “Secondly, we need to transfer the responsibility obligation to those with wholesale contracts. … It’s not my responsibility as a legacy BA.”

Developing a policy to enforce the requirement will take additional time, Wise said.

The task force asked that its charter be extended for an additional year to July 2016, a request approved by the MOPC and endorsed by the SPC.

Wise told the SPC that SPP staff is developing a deliverability study process that will allow for non-firm transmission service for planning reserves. The study will analyze all generators registered in the Integrated Marketplace and determine whether they are deliverable to all loads within the SPP balancing authority.

Engaging Prospective Members

The SPC also reviewed the final report from its Task Force on New Members and approved a recommendation to improve the process of engaging prospective transmission-owning and load-serving members.

The task force was commissioned in 2014 to develop formal processes to be followed during negotiations with prospective members.

Michael Desselle, SPP’s Chief Compliance and Chief Administrative Officer, said much of the task force’s work centered on how to involve the regulators on SPP’s Regional State Committee during the negotiation period. The task force tried to balance transparency with the need for confidential negotiations.

The report notes that SPP staff “remains solely responsible for the direct negotiations with the prospective member,” while stakeholders provide input on policy and changes to the governing documents.

The SPC discussed the legal costs for smaller entities and the threshold for “triggering events” when a prospective new transmission-owning member formally requests changes to SPP’s Tariff and governing documents or RSC bylaws.

The committee also considered the report’s definition of stakeholders: “Stakeholders include existing transmission owner members, transmission-using members and RSC members and their staffs.”

“Stakeholder means anybody and everybody in the world who feels affected in some way,” said SPP board member Phyllis Bernard, urging “SPP” be used as a modifier for “stakeholder” across all governing documents.

The task force will make several language modifications to the report before sending it to the SPP Board of Directors for its approval.

Behind-the-Meter Generation

Wise teed up a discussion on behind-the-meter generation by noting that the amount of such unaccounted-for energy is growing. “I know some market participants are not adding [behind-the-meter generation] back in[to the pool],” Wise said, “and it’s not fair.”

The Regional Tariff Working Group will take up the issue for further discussion during its Thursday meeting.

Integrated System

Monroe told the committee that SPP is continuing to incorporate members of the Integrated System and their facilities under the RTO’s Tariff. He said the majority of the IS load that would be placed under the Tariff has already been accounted for.

Monroe said that while the Northwest Power Pool has suspended its solicitation for bids to manage its energy imbalance service market, SPP continues to consult with the pool on EIS markets.

— Tom Kleckner

Plant Owner Responsible for Uncorrected ISO-NE Error, FERC Says

By William Opalka

The Federal Energy Regulatory Commission ruled Thursday that a power plant owner must pay unnecessary capacity charges because it failed to correct ISO-NE records before a deadline set by the RTO’s Tariff (EL15-57).

GenOn Energy Management, a unit of NRG Energy, asked FERC in April to excuse it from buying replacement capacity to meet an obligation it was capable of fulfilling with its own resources.

GenOn said ISO-NE credited its Canal 2 generator in Sandwich, Mass., with capacity of only 303 MW — rather than the plant’s actual 556.5-MW output — in the March Annual Reconfiguration Auction for the 2015-2016 capacity commitment period that began June 1. (See ISO-NE Error Could Cost GenOn Millions.)

ISO-NE said, and FERC agreed, that the Tariff requires participants to file restoration plans for any capacity shortfall within 10 business days after notification of the ARA results. “The provision also makes clear that after they receive notification of their qualified capacity from ISO-NE, the onus is on resources to provide a restoration plan, as necessary, and if they do not do so, ISO-NE will procure capacity on their behalf and charge them for it,” the commission wrote.

ISO-NE also said it wasn’t obligated to find out why no restoration plan was filed. (See ISO-NE: Plant Owner’s Responsibility to Flag Capacity Error.) FERC concurred. “We agree with ISO-NE that it is not ISO-NE’s responsibility to second-guess the market participant’s failure to submit a restoration plan after being notified of its qualified capacity,” it wrote.

The commission said reopening the auction as an alternative remedy would create market uncertainty.

In order to administer the capacity market, “ISO-NE must ensure that the auction results are final, and that, once the auction is concluded, market participants are able to take actions and enter into transactions immediately, based on those auction results,” it concluded.

State Briefs

Personal finance website WalletHub has released a study that ranks the states and D.C. based on the average monthly cost of energy, with breakdowns by electricity, natural gas, vehicle fuel and home heating oil.

D.C. ranked lowest overall, followed by Colorado and Washington state. Connecticut, Wyoming and Massachusetts had the highest overall bills. D.C. residents also pay the least for electricity, followed by Illinois and New Mexico. Electricity costs are highest in Hawaii, South Carolina and Alabama.

Lower prices don’t always equate to lower bills, the study shows. Its authors used the states’ average monthly energy consumption in each category and multiplied it by the average price, adding each category to find the total cost. In Southern Louisiana, for example, where the summers are hot but the electricity is cheap, residents will pay more than in Northern California, where customers consume less because the weather is temperate.

DELAWARE

State Offers Rebates to Spur Electric Car Sales

The state has earmarked $2.7 million to fund the new Delaware Clean Transportation Incentive Program, which aims to encourage residents to buy electric, propane and natural gas vehicles.

The initiative will provide three rebate programs for consumers and two grants for the development of infrastructure to support alternative fueling. Rebates will run up to $20,000, and developers may qualify for grants up to $500,000.

More: NewsWorks

DISTRICT OF COLUMBIA

District to Buy Output of Pa. Wind Farm in Record Deal

RTO-IberdrolaThe district plans to purchase the entire output of Iberdrola Renewable’s 46-MW South Chestnut wind farm in Pennsylvania, which will provide 35% of the municipal government’s renewable power portfolio.

The 20-year power purchase agreement is the largest of its kind to be entered into by a U.S. city and is expected to save taxpayers $45 million over the next two decades. The district has a goal to meet half its government’s demand by 2032 with renewable energy.

The wind farm contains 23 turbines on private property in three townships in southwestern Pennsylvania.

More: Executive Office of the Mayor

ILLINOIS

State Sets Public Forums for Power Line Project

Grain BeltExpressSourceGrainBeltThe Commerce Commission is planning three public forums this month about the proposed Grain Belt Express direct-current transmission line. The line would run through the Illinois counties of Pike, Scott, Greene, Macoupin, Montgomery, Christian, Shelby, Cumberland and Clark.

Clean Line Energy seeks a certificate of public convenience and necessity for the 780-mile-long project, which would deliver wind power from Kansas to Indiana. Hearings are set for July 28-29 at various sites.

More: Illinois Commerce Commission

INDIANA

State Claims Global Domination in Airport Solar Generation

INdianapolisAirportSourceIndianapolisAirportIndianapolis International Airport says it now operates the world’s largest airport solar farm.

Contractors recently completed a second phase of the airport’s solar farm, bringing total output to 17.5 MW, or enough to power 3,200 houses. Indianapolis Power & Light is buying the power from what now looks like a sea of blue-colored solar panels near the end of runways on the southwest corner of the airport.

The 161-acre site is to expand farther this year, with an additional 22 acres designated for solar generation. When all three phases are completed, the solar farm will consist of 87,000 panels.

More: Solar Power World

IOWA

Wind Could Meet 40% of State’s Energy Needs by 2020

AmericanWindSourceAWEAAn American Wind Energy Association report said the state could produce enough wind energy to meet 40% of its power needs by 2020 and all of its electricity demand by 2030.

The report acknowledges that a fuel mix will always be necessary, but it said wind, solar and energy-storage technologies are improving at a rapid rate. “Iowa is already a leader in wind energy, but this report shows the Hawkeye State has just scratched the surface of wind power’s benefit to the state,” said Tom Kiernan, AWEA’s CEO.

The report said the wind energy industry employs 7,000 in Iowa at 13 factories and assembly plants. Lease payments to landowners by wind energy companies could increase from the $17.1 million a year now to $55 million by 2030.

More: Des Moines Register; AWEA

KENTUCKY

Report: State’s CO2 Emissions Highest in the Country

Big Rivers Electric Corp Logonew report looking at air pollution from the country’s power plants found that the company that emits the most carbon dioxide per megawatt-hour is Big Rivers Electric. Also in the top 10: East Kentucky Power Cooperative.

The study considered how much electricity the plants generate along with sulfur dioxide, nitrogen dioxide, carbon dioxide and mercury. Seven of the 10 companies with the highest emissions per megawatt-hour were energy cooperatives.

Kentucky’s ranking is largely due to the portion of coal in its energy portfolio, said Dan Bakal of Ceres, a sustainability advocacy group.

More: WFPL

MAINE

Study: Supply Boost to Cost More than it Saves

An initiative to boost the region’s natural gas supply would cost consumers more than it would save them, according to a study commissioned by the state Public Utilities Commission.

A cost-benefit analysis of the Maine Energy Cost Reduction Act, which was approved by the Legislature in 2013, shows the act may be counterproductive. Boston-based consultant London Economics International said the state’s plan to augment natural gas supply would be costly. “Maine simply does not use large amounts of gas and electricity,” it said.

The 2013 law is designed to lower energy costs for consumers by having the state enter into contracts to purchase up to 200 million cubic feet per day of natural gas at a cost not to exceed $75 million annually. Ratepayers in the state would foot the bill.

More: Portland Press Herald

Power Marketer Draws Complaints

ClearviewEnergySourceClearviewTexas-based Clearview Energy is attracting complaints for alleged aggressive sales tactics by its door-to-door teams in Central Maine Power’s service area. CMP and the Maine Public Utilities Commission say customers have complained that Clearview’s salespeople sometimes ask customers to show them their monthly bills.

The company says it’s doing nothing wrong and last week responded to a PUC request for information with details about its training and sales protocols. The company also blames CMP for stirring up trouble, charging that the utility’s staff is anti-competition.

The PUC, which licenses electricity suppliers, said it is evaluating the information submitted by Clearview and deciding what, if any, steps to take. It said that Clearview appears to be the first electricity provider using door-to-door sales in Maine, and it’s the first time the PUC has received complaints about the practice.

More: Portland Press Herald

MARYLAND

Pepco, SMECO Pair with Energesco in Efficiency Program

EnergescoSourceEnergescoPepco and Southern Maryland Electric Cooperative are partnering with Energesco Solutions to provide energy and water efficiency for multifamily buildings in the state under a new rebate initiative, the Commercial Multifamily Program.

Multifamily properties within Pepco’s 566 square miles of service area can apply for rebates for energy efficiency projects like LED lighting upgrades and HVAC enhancements.

Energy costs in such communities represent 25 to 35% of expenses and are highly controllable. Previously, multifamily owners and operators were restricted to rebates for upgrades in common areas.

More: EnergyEfficiencyMarkets.com

MASSACHUSETTS

Online Marketplace Would Allow Comparison Shopping for Rates

MassDPUSourceGovThe state is planning to build an online marketplace where consumers can shop for competitive suppliers.

The Department of Public Utilities soon will begin soliciting ideas to build the website. Under the DPU proposal, companies initially would be allowed to offer only fixed-rate plans so consumers would be shielded from hidden charges and confusing contracts.

Several other states, including OhioTexasConnecticut and Pennsylvania operate similar marketplaces. The state experienced a growth in customers shopping for suppliers after last year’s bone-chilling winter sent electricity prices soaring.

More: Boston Globe

MICHIGAN

Legislators Eye Energy Market Regulation

The Senate has begun hearings on a comprehensive energy plan governing how utilities and alternative suppliers may operate in the state and how renewable power and energy efficiency programs will figure into the equation.

Among other things, the Senate’s plan would offer incentives for utilities that already have met a renewable energy mandate to increase their energy efficiency programs.

The most controversial aspect of the plan would make it more difficult for electricity customers to opt in or out of the competitive retail supply market.

More: Detroit Free Press

Straits of Mackinac Pipeline Report Shows ‘Gaps’ in Enbridge Info

StraitsofMackinacSourceNatWildlifeFedA state report on the twin pipelines running under the Straits of Mackinac said operator Enbridge’s assurances that the pipelines are safe and don’t need replacement were unsupported by data.

The report said the yearlong inquiry by the state Department of Environmental Quality and the Attorney General’s Office was hampered by “gaps” in information provided by Enbridge. Dan Wyant, DEQ director, said Enbridge failed to provide comprehensive information in many areas, including inspections and the nature and result of heavy mussel encrustations that could be hiding significant corrosion.

“Substantial questions remain and can only be resolved by full disclosure of additional information and rigorous, independent review by qualified experts,” the report concludes. The report was spurred in part by the rupture of another Enbridge pipeline in 2010 that spilled oil into the Kalamazoo River.

More: MLive

MONTANA

Renewable Advocates Say Utility Blocking Small-Scale Solar, Wind

MontanaDakotaUtilitiesSourceMDUMontana-Dakota Utilities wants to assess customers with wind and solar generators a demand charge, but renewable advocates say the utility is using the fee to block small-scale generation.

MDU built the fee into a 21% rate increase it has proposed for about 26,000 customers in the state. The company said it needs the $1.50/kW demand charge to cover the cost of providing power to wind and solar customers when their self-generation isn’t sufficient to meet their needs. The fee would also pay for the costs of installing emissions controls at plants in Montana and South Dakota.

A Public Service Commission spokesman says it was the first time a utility has asked for a special fee for net-metering customers. The Montana Renewable Energy Association said the utility ignores the assertion that customers who generate their own power allow the utility to reduce transmission and distribution costs across the system as a whole.

More: The News Tribune

NEW HAMPSHIRE

Kinder Morgan Starts Promotional Website

Kinder MorganKinder Morgan has launched a website aimed at New Hampshire residents along the 80-mile proposed route of the Northeast Energy Direct natural gas pipeline.

The pipeline would deliver natural gas from the shale formations of Pennsylvania through New York and into New England to ease supply shortages. The new website is part of a public outreach campaign by Kinder Morgan to communicate the need for the project.

EnergymattersNH.com includes videos on the project, an up-to-date project blog, as well as a running list of upcoming project-related meetings.

More: New Hampshire Union Leader

Another Electricity Supplier Pulls Out

Gulf, which entered the competitive electricity market with much fanfare in 2013, has quietly pulled out, the latest departure from a business sector that one competitive supplier says is on life support.

Competitive suppliers are having a hard time beating the utility prices for residential power supply. Bart Fromuth, a Republican state representative from Bedford and head of Resident Power, one of the earliest brokers to enter the residential space in 2012, said the pullback mostly affects the retail residential market.

“Commercial competition remains at healthy levels,” said Fromuth. “The regulatory environment for residential is absolutely suffocating. In the interests of beefing up consumer protection, the legislature and the PUC are quickly cementing New Hampshire’s position as the most unattractive place to do residential supply in all of New England.”

More: New Hampshire Union Leader

NEW YORK

Transmission Policy Requirement Adopted

nyisoThe Public Service Commission has adopted a public policy requirement related to the potential need for additional transmission capability in Western New York. The decision stems from a proceeding the commission initiated last year to establish procedures that it would use to identify any transmission needs driven by public policy requirements that would be referred to NYISO. The Federal Energy Regulatory Commission’s Order 1000 requires public policy be considered in system planning.

The commission determined transmission projects in Western New York that fulfill such public policy requirements will now become eligible for cost recovery through NYISO’s Tariff if they are selected by the RTO as the most efficient or cost-effective solution. Designating Western New York congestion relief as a public policy requirement will enable NYISO to solicit potential project solutions and undertake an initial analysis of the project’s viability. The PSC did not adopt other proposed public policy requirements for other regions.

More: NYPSC

NORTH CAROLINA

Amazon to Build Major Wind Farm

Online retail giant Amazon plans to power its cloud-computing division with the $400 million Amazon Wind Farm US East, set to be built on 34 square miles in the eastern counties of Perquimans and Pasquotank.

The project will start with 104 turbines and will be built by Spanish wind farm developer Iberdrola Renewables. It is expected to begin generating power for Amazon’s data centers late next year.

The project has sidestepped obstacles that have felled such proposals in the past. The 208-MW farm is sited in isolated scrubland locally knows as The Desert where there are no homes, minimizing its impact on tourist areas, military flight paths and bird migration routes.

More: News and Observer

OHIO

Study Shows Utica Oil and Gas Play Much Larger than Thought

A study by West Virginia University shows that the amount of recoverable oil and natural gas in the Utica Shale formation is much larger than first thought. The geologic formation, which includes parts of Pennsylvania, West Virginia, Kentucky, New York and Ohio, has about 782 trillion cubic feet of natural gas and about 2 billion barrels of oil, about 20 times the U.S. Geological Survey’s estimate from three years ago.

“This is a landmark study that demonstrates the vast potential of the Utica as a resource to complement — and go beyond — what the Marcellus has already proven to be,” said Brian Anderson, director of WVU’s Energy Institute. The study leans heavily on research conducted by the Appalachian Oil and Natural Gas Consortium.

“The revised resource numbers are impressive, comparable to the numbers for the more established Marcellus Shale play, and a little surprising based on our Utica estimates of just a year ago,” said Douglas Patchen, director of the consortium. The announcement came as low oil and natural gas prices continue to curtail new production.

More: Columbus Business First; National Research Center for Coal and Energy

WISCONSIN

Enbridge Pulls Its Appeal of Pipeline Insurance Regulation After State Legislative Action

EnbridgeSourceEnbridgeLawmakers amended the state budget to prohibit local governments from imposing higher insurance demands on pipeline operators, a move that handcuffs Dane County, which had demanded Enbridge boost its liability coverage. Enbridge immediately dropped an appeal of the local mandate.

Dane County officials were irked. “Enbridge filed an appeal properly, and we were set to hear that appeal and make a decision,” said Dane County Board Chairwoman Sharon Corrigan. “That’s how it’s supposed to work. But apparently Enbridge sent some lobbyists to make a different kind of appeal to the Legislature and the governor, and got some special treatment slipped into the budget.”

More: Wisconsin State Journal

FERC Rejects Claims that MISO Snubs Generation Alternatives

By Chris O’Malley

The Federal Energy Regulatory Commission last week declined to rehear DTE Electric’s contention that MISO rules put generation developers at a disadvantage in the competition for reliability projects.

misoDTE had sought review of FERC’s September 2014 ruling approving MISO’s requirement that a proposed generator must have filed an interconnection agreement to be considered as an alternative to a transmission solution. The agreement is due before the date MISO must initiate the transmission project to meet its required in-service date.

Comparable Treatment

The commission agreed with MISO that the requirement is comparable to those required for transmission solutions in its Transmission Expansion Plan process (MTEP). FERC also accepted MISO’s compliance filing in response to the commission’s Order 809 transmission planning requirements (OA08-53-005, ER15-133).

To allow generator proposals to progress through the interconnection process, DTE said more time is needed between when MISO identifies a system need and when it approves a transmission facility to meet the need. The time it takes MISO to complete interconnection studies “makes it more likely than not that a generation project could never even be considered by MISO as an alternative to a transmission project,” DTE said.

The company said generation developers won’t have the information they need regarding potential system needs until Sept. 15, when transmission owners must identify and submit new transmission projects within the MTEP process.

FERC said that developers should be able to identify system needs based on power flow models available in June. But DTE countered, “It is far-fetched to believe that a proponent of a generation solution would be able to use that data to determine that a transmission problem existed or even if it could, offer a generation solution to that problem in the allowed timeframe.”

The commission was not persuaded. DTE “does not explain why a generation developer must wait until a transmission facility is proposed before it can identify potential generation solutions to the needs the transmission facility is meant to address,” FERC said. “Just as the proponent of a transmission solution considers system needs to identify potential transmission facilities to meet those needs, so too can the proponent of a generation solution.”

Catch 22?

Developers have until April to submit generation projects — including executed interconnection agreements —  as alternatives to transmission projects that were proposed the preceding September.

DTE disputed the commission’s finding that a generator that may mitigate a particular transmission need is likely being evaluated in the interconnection process long before the April deadline.

The company noted that generators in the interconnection process are considered operational. As a result, it said, any transmission projects identified in the MTEP process will be those needed in addition to generation in the interconnection process, and any new generation alternatives would be precluded from ever being evaluated against the newly identified transmission need.

FERC saw it differently. “If a generation solution that goes through the interconnection process and has an interconnection agreement filed with the commission does in fact address the need, MISO will not identify a transmission facility to meet the need and the generator alternative will have successfully replaced a transmission facility,” the commission said.

Not Viable

FERC agreed with DTE that MISO is unlikely to replace an approved transmission facility with a generation solution if the transmission developer has already begun right-of-way acquisition, completed design and engineering, ordered material and obtained permits.

“That means only that the generation solution did not have the necessary contractual commitments for MISO to consider it a viable alternative to the transmission solution before the transmission solution had to begin being developed,” FERC said.