Search
`
November 16, 2024

CAISO Proposal Would Permit ‘Economic’ Outages

By Robert Mullin

Power producers could temporarily suspend the operations of unprofitable generators not needed for system reliability under a CAISO plan released this week.

The Temporary Suspension of Resource Operations straw proposal, released Wednesday, would allow a plant owner to temporarily take a money-losing generator out of the market short of the “mothball” and retirement procedures already spelled out in the ISO’s Business Practice Manuals. (See CAISO Initiative Could Toss Lifeline to Struggling Generators.)

The proposal stipulates that a resource owner must manage a suspended resource in such a way that it can retain the same megawatt rating and ramping capability as before the shutdown. Any plants denied a request could become eligible for payment under CAISO’s capacity procurement mechanism (CPM), which currently compensates units for specific reliability needs.

While that move would fall far short of establishing a capacity market, it could provide needed financial support to gas-fired generators the ISO identifies as vital for future system needs, particularly in integrating increased amounts of renewable resources. CPM payments would be limited to four-month terms.

The proposal calls for owners to be permitted to shut down a resource for two to four months at a time, with the option to request a subsequent four-month suspension.

A unit approved for shutdown would not be required to respond to “exceptional” — or out-of-market — dispatches issued by the ISO, but it could be recalled for system emergencies, making it eligible for a CPM payment. A suspended unit would be ineligible to be counted in the ISO’s resource adequacy showing during its suspension.

The proposal would allow resources to apply for temporary shutdowns throughout the year, but they must provide notice 60 days in advance of the effective date of the suspension. CAISO, in turn, would be required to notify the resource of an approval or denial of the request eight days before the effective date.

“The ISO will assess requests on the first-come, first-served basis, and there will not be a window that resource owners would need to work around,” CAISO said.

A resource would be required to maintain all environmental operating permits while on shutdown, and it must be fully available for service on its return date, the proposal stipulates. To accommodate “unforeseen circumstances” — such as an expected loss of resources, transmission outages or extreme weather — suspended units must be prepared to return to service within 10 days of being notified by the ISO.

CAISO developed the temporary suspension proposal in response to stakeholder comments filed in a 2016 FERC proceeding over the ISO’s refusal to approve outage requests for three of four units at the 965-MW La Paloma combined cycle plant 140 miles north of Los Angeles (EL16-88).

CAISO economic outages
CAISO’s initiative stems from stakeholder concerns raised during a 2016 FERC proceeding related to the La Paloma generating plant, which filed for bankruptcy late last year after being refused permission to suspend its operations in the ISO market. | Kern County, California Public Health Services Department

FERC last October agreed with the ISO’s decision to reject the plant owners’ requests because they were made for economic — and not physical — reasons.

Because the request was economic, it “did not represent an appropriate use of the outage management system as allowed by the CAISO Tariff,” the ISO said.

CAISO also denied an additional request to compensate the units by designating them as reliability-must-run resources, contending that they were not needed for reliability purposes. At the time, 42 MW of La Paloma Unit 2 were under an RMR agreement.

La Paloma filed for bankruptcy late last year, citing $524 million in debt and an “inhospitable regulatory environment.”

Although stakeholders largely agreed with CAISO’s La Paloma response, some asked that FERC direct the grid operator to amend its Tariff to allow for outages based on economic considerations — a request that the commission rejected. The ISO nevertheless committed to establishing a stakeholder process to take up the issue this year.

“Through that process, the CAISO and stakeholders will have sufficient time to consider all pertinent issues, the conditions under which economic outages should be permitted, if at all, and how economic outages would interact with other requirements of the CAISO tariff and with CAISO grid and market operations,” the ISO said.

The ISO has scheduled a June 28 call to discuss the proposal and has asked stakeholders to submit comments by July 13.

House Panel OKs Bill Expanding FERC Hydro Authority

By Michael Kuser

A proposed law that would give FERC authority over the licensing of all hydropower projects has advanced to the House Energy and Commerce Committee along with four related bills — but only after a hearing that revealed a partisan divide on much of the legislation.

FERC hydropower
House Energy Subcommittee Meeting

The Energy Subcommittee on Thursday sent the Hydropower Policy Modernization Act of 2017 — and four other energy infrastructure-related bills dealing with natural gas pipelines, electric transmission and grid security — to the full committee despite complaints from Democrats about the Republican-controlled process for drafting the bills and on the substance of some clauses.

FERC hydropower
Upton

The hydropower legislation modifies the definition of renewable energy under the Energy Policy Act of 2005 to include hydropower and designates FERC as the lead agency for federal authorizations, granting the commission discretion to extend preliminary permits and the time limits for construction.

“As we always strive to do, these bills have been drafted with bipartisan input, and in large part we’re picking up where we left off with on last year’s energy bill conference,” subcommittee Chair Fred Upton (R-Mich.) said in his opening remarks.

Not a ‘Murmur’

FERC hydropower
Rush

Ranking member Bobby Rush (D-Ill.) disagreed with Upton’s take on the proceeding.

Rush said that despite coming to negotiate in good faith, two of the bills presented for the markup — the hydropower policy and the Promoting Interagency Coordination for Review of Natural Gas Pipelines Act (H.R. 2910) — “are vastly different from the discussion drafts that had been part of the staff negotiations.”

The two bills did not reflect any of the changes sought by Democrats, such as not allowing aerial surveillance to supplant on-the-ground inspection of proposed project sites. They “instead moved in the opposite direction and are even more problematic for our side to accept,” Rush said. He added that Upton had not responded to the Democrats’ request for a hearing on the hydropower policy legislation with officials from the departments of Interior, Commerce and Agriculture.

“This is yet another instance where once again, Mr. Chairman, our side is left to wonder whether we will ever hear directly from the administration on any bill or topic in our jurisdiction,” Rush said. “Where is the administrator of the EPA, and where is the Secretary of Energy? Six months into the Trump administration and we haven’t heard a murmur from the administrator or the secretary, and it’s high time that we hear from those in the administration who have responsibilities to this subcommittee and to the Congress.”

Minor Amendment

Pallone

The subcommittee also discussed drafts of the Enhancing State Energy Security Planning and Emergency Preparedness Act of 2017; an amendment to the Federal Power Act related to qualifying a conduit hydropower facility (H.R. 2786); and the Promoting Cross-Border Energy Infrastructure Act (H.R. 2883).

The subcommittee agreed to an amendment to H.R. 2786 — offered by the ranking member of the full committee, Rep. Frank Pallone (D-N.J.) — to reduce the public comment period on facilities from 45 days to 30, rather than the 15 days set out in the draft legislation, which Pallone thought insufficient. The proposed law also would lift the 5-MW cap on what constitutes a conduit hydro plant.

Other Democratic-sponsored amendments did not win acceptance, with the subcommittee dividing on party lines. Democrats voted to forward all the bills except for H.R. 2910.

Walden

Rep. Greg Walden (R-Ore.), chair of the full committee, said “We’ve learned that oftentimes dozens of agencies are involved in the permitting process, so it’s time that we address these issues head-on and improve the federal licensing procedures and processes to ensure that we get these projects to market sooner for consumers.”

Castor

The bill to streamline gas pipeline permitting substitutes “safety for expediency,” Rush said. Republican members voted down his proposal to cut a section of the bill, “so that states, tribes and local community stakeholders can continue to play an important role in the pipeline permitting process.”

Rep. Kathy Castor (D-Fla.) proposed another failed amendment that would have the Office of Management and Budget determine if the legislation would duplicate other federal efforts or result in wasteful government spending.

More Dissent

Pallone said he was “deeply concerned” over the process the subcommittee had used for the markup.

“The draft released on Tuesday night [June 20] not only failed to address any of the concerns we raised, but actually went so far as to add new sections taken directly from provisions of last year’s Senate energy bill that we had explicitly rejected,” Pallone said. “And this does not bode well for making this a bipartisan process.”

Pallone added that Upton had marked up changes on legislation on state energy security plans that Democratic members first saw Tuesday night and that was never the subject of a legislative hearing or member-level discussion. And the gas pipeline bill was a “completely new and different bill” from the one discussed in May, he said.

“I hope today’s issues represent an aberration and not a new and unfortunate way of doing business,” Pallone said.

Subcommittee Vice Chairman Pete Olson (R-Texas) mentioned that Tropical Storm Cindy the previous day had hit the nation’s first LNG export terminal, Sabine Pass on the Texas-Louisiana border, and led to the evacuation of several offshore rigs in the Gulf of Mexico.

“These threats are real, and as cyber threats evolve, let’s get this right,” Olson said. While Texas isn’t famous for hydropower, it is an important baseload power and should be developed without hindrance, he said. “Lastly, on pipelines, we need these reforms. We’ve seen time and time and time again that the process takes too long and is way too messy. The better we are at getting infrastructure built, the better our economy is.”

Cross-border or Borderline?

Mullin

Also drawing opposition from Democrats was H.R. 2883, the draft bill authored by Markwayne Mullin (R-Okla.) to “establish a predictable and transparent process to permit the construction of cross-border pipelines and electric transmission facilities.”

Pallone offered an amendment that would not restrict the purview of National Environmental Policy Act reviews to the border area, but have EPA look at environmental impacts across the whole length of such projects. The subcommittee divided 18-12 in rejecting the revision.

Green

Mullin and Rep. Gene Green (D-Texas) said the bill does not impinge on federal environmental reviews necessary under existing law, but heightens the focus on the border-crossing itself.

Rush also opposed H.R. 2883, saying the bill would shift the burden of proof to pipeline opponents to prove that a given project was not in the public interest.

The bill would “allow parties to push projects that are not necessarily in the public interest to move forward in the permitting process,” Rush said. “The new bill would make the process worse, less transparent, less inclusive and ultimately less effective … and lead to greater controversy, increased litigation and longer delays.”

Western Utilities Bought 3X Planned Wind, Study Says

By Jason Fordney

Western U.S. utilities procured three times more wind capacity in 2003-2014 than planned, showing there is a limited relationship between electricity resource planning and procurement, according to a new Department of Energy study.

department of energy wind capacity
Actual and planned nameplate capacity additions by resource and contract type for 12 load-serving entities in the West. | Lawrence Berkeley National Laboratory

Expansion of nameplate wind capacity by 2015 was expected to be about 15% but was actually about 50%, likely coming from power purchase agreements, the analysis of 12 Western load-serving entities showed. Changes in load growth, regulation and contracting led to adjustments in resource planning, and differences in resource mix came largely from renewable portfolio standards and demand-side management, as well as fuel price changes.

The study considered what types of economic and regulatory information is used in planning and procurement, and examined the value of the planning process in light of its relationship to actual practice. The analysis compared integrated resource plans filed in the early and mid-2000s to the actual procurement that followed.

Although IRPs are designed to ensure that utility investment decisions are as cost-effective as possible, there had been no previous “empirical assessment on the effectiveness of IRP implementation,” said the study, conducted by the Lawrence Berkeley National Laboratory.

“We find that most information produced in the planning phase is generally disconnected from the procurement phase,” the researchers said.

Western Wind Farm | SPP

After 2008, adoption of less efficient simple cycle combustion turbines correlated with dropping natural gas prices, which might also have been needed to provide balancing power because of higher usage of intermittent renewables. There was also less usage of coal-fired generation than planned, as difficulties in getting coal plants permitted were mentioned by several LSEs in their resource plans; natural gas was likely used as a baseload power substitute.

The researchers said only some of the forecasts, least-cost/risk portfolios and other information produced during the long-term planning processes were used during the procurement processes, and that procurement decisions relied “extensively on the most recent information available for decision making.”

“These findings suggest that states’ IRP rules and regulations mandating long-term planning horizons with the same analytical complexity throughout the planning period may not create useful information for the procurement process,” the study says.

The study found “in aggregate … a general alignment between planned and procured supply-side capacity. However, there are significant differences in the choice of supply-side resources and type of ownership for individual LSEs.”

Avista, Puget Sound Energy, Seattle City Light and Public Service Company of New Mexico procured less capacity than planned, possibly because of lower load growth, while Idaho Power, PacifiCorp and Portland General Electric procured more capacity than was planned. Idaho Power procured two to three times more wind capacity than planned. Although PacifiCorp had not planned for any wind in 2004, more than half of its procured nameplate capacity was wind.

For the Los Angeles Department of Water and Power, Sierra Pacific, Nevada Power and Public Service Company of Colorado, the largest difference between planning and procurement was substituting natural gas units for coal.

There is no formalization of how utilities should use inputs from their IRPs in their procurement, and there is little evidence regarding how sensitivity and risk analyses used in the IRPs are actually applied in procurement decisions, the study says.

It called for a “more careful” definition of the links between IRPs and procurement, calling it “an important problem as energy technologies, markets, and policy and regulatory goals evolve and become more complex.”

Consolidated EIM Proposal Effort Gets Underway

By Jason Fordney

CAISO is seeking comment from market participants on three proposed modifications to the Western Energy Imbalance Market (EIM).

The grid operator on Tuesday kicked off the stakeholder process for the proposals, which include allowing third-party transmission providers to receive congestion revenue when they make unused capacity available between EIM balancing authority areas (BAAs).

caiso eim congestion revenue
| CAISO

In response to questions during a call on the initiative, CAISO said transmission owners will not have to turn over control of their transmission facilities to participate and would receive payment only if there is congestion on the system.

CAISO says the measure would increase transfer capacity among members, which the ISO’s internal Market Monitor has pointed out reduces congestion and limits the ability of any single participant to wield market power within its BAA. (See Increased Transfer Capacity Reducing EIM Congestion.) EIM entities can currently collect congestion revenue through an offset, but that functionality is not extended to third parties.

CAISO has proposed allowing third-party transmission in the EIM | © RTO Insider

The ISO plans to use its existing functionality for transmission contributions, known as “energy transfer system resources” that are used to track, tag and settle EIM transfers. It will need to establish a pro forma agreement that enables scheduling coordinators to submit transmission contributions on behalf of a third party, and create a new make-whole mechanism that would guarantee a payment from congestion revenue. The ISO is seeking stakeholder input on what level of interval granularity those payments should be calculated and how their associated costs should be allocated.

CAISO also wants to correct an inequity that occurs when an EIM BAA wheels power between other BAAs. Wheel-through BAAs receive some revenue when congestion occurs but are not compensated if there is no congestion. In that circumstance, only the source and sink BAAs accrue benefits when a wheel-through transfer occurs.

“How should we quantify the benefits of providing EIM transfers through an EIM BAA?” CAISO asked in its meeting materials.

The ISO has also proposed a new policy for situations in which market participants change their bilateral schedules after submitting their hourly base schedules. Under current practice, changes made after submission are exposed to real-time imbalance settlement payments.

Settlement can result in either charges or payments, but there is no way for market participants to know the cost beforehand. Proposed changes would allow them to manage their exposure to imbalance settlement charges, CAISO said.

After the comment period ends June 30, CAISO will post a straw proposal on the initiative by July 27 and hold stakeholder meetings in August and September. The EIM Governing Body is set to review the proposals in October, ahead of a decision by the CAISO Board of Governors in November.

MISO: $130M Needed for New Market Platform

By Amanda Durish Cook

BRANSON, Mo. — MISO wants to spend $130 million over the next five years to construct a new market platform before its existing one becomes outdated, but its Board of Directors is insisting on a thorough stakeholder review of the project’s cost.

Jeff Bladen, MISO executive director of market design, said the upgrade would involve a “piece-by-piece replacement of components” resulting in a “far more modular platform” compared with the rigidity of the current system, which hinders market changes.

Swapping out market software incrementally instead of introducing a new platform all at once is the safer option, Bladen said.

“The risk of a misstep is far less using an incremental process,” he said during a rare June 20 joint meeting of the board’s Markets and Technology committees.

MISO’s current platform is “inflexible,” and even simple market changes require testing and retesting because of possible effects on other software, according to MISO Technology Executive Kevin Caringer. He likened the new design to Microsoft PowerPoint, which can recognize and accept fonts and graphics from other sources.

Looming Obsolescence

The RTO evaluated its market system last year and concluded it had five to seven years before evolving cybersecurity standards and increasing market complexity render the system — designed in the late 1990s — obsolete and no longer able to clear the day-ahead market. (See MISO Reaffirms 2023 End Date for Market Platform.)

“The time is now to begin long-term investment,” Bladen said. “Findings and conclusions drawn from the evaluation resulted in a clear call to immediately initiate a system upgrade.”

Caringer said MISO will spend about $3 million on cybersecurity to extend the life of the current platform for the five years needed for the switch to a new platform.

MISO is asking for an additional 25% contingency budget for unforeseen expenses in addition to the expected $130 million plan. Staff said it will present final cost estimates to the board in September. The board’s Audit and Finance Committee will decide whether to approve the spending in October, and a full board decision on the budget is set for December.

MISO staff predicts the project will yield a 4-to-1 return on investment, with $201 million in benefits, $254 million in cost avoidance and $111 million in risk mitigation.

Board Scrutiny

MISO board market platform
Baljit | © RTO Insider

Director Baljit Dail asked how MISO will prove the benefits and savings to its stakeholders.

Bladen said the RTO can share a recent benefits report once it removes nonpublic information from the document.

“I don’t want this to be jammed into December. At some point, I’m going to ask, has this report been scrubbed and has it been shared with stakeholders? I don’t want that to happen in December,” Dail warned.

Director Paul Bonavia wondered if MISO will give stakeholder groups a chance to collaborate to develop a process for responding to the benefits report.

Bladen responded that MISO expects to follow its normal annual budget process with stakeholder review occurring in the Finance Subcommittee.

“I appreciate that, but the budget process usually doesn’t have $130 million to $160 million in additional spending. One director’s strong counsel to you all is make sure the usual process can handle [this],” Dail said.

Other directors pointed out that the project’s benefits may play second fiddle to the market failure that looms if MISO does not implement a new market platform.

Curran | © RTO Insider

“I’m not too captivated by the benefits. We need to move,” Director Michael Curran said. “I’d love to see the benefits, but we have to spend the money. … It’s a burning platform; it’s a slow burn, but it’s coming.”

“My comment is, however you want to justify the benefit, it needs to be put before the stakeholders,” Dail replied. He suggested that MISO convene a special stakeholder committee to discuss the investment and consequences of not reconstructing the market platform.

“I’d like to see [the stakeholders’] fingerprints all over this,” Curran agreed.

Bladen said MISO could initiate stakeholder workshops to discuss building the platform.

In response to a question from Curran, Caringer said MISO could reach out to developers of its original market platform to help improve the transition. Some longtime MISO employees also have knowledge of the system, he said.

Curran said he wanted to require any potential project vendors to have contact with developers of the original system. CEO John Bear said the board would address that topic in a closed session that immediately followed the meeting.

DC Circuit Rejects Challenge to PJM CP Rules

By Rory D. Sweeney and Rich Heidorn Jr.

The D.C. Circuit Court of Appeals on Tuesday denied eight challenges to PJM’s controversial Capacity Performance market rules, potentially cementing fundamental changes to the RTO’s capacity market that critics believe were hastily enacted and unjustifiably increase costs (16-1234).

CP was implemented following a blackout scare in January 2014 when the polar vortex dipped unusually low across the northern U.S. and created record-low temperatures. As much as 22% of PJM’s fleet failed to operate when dispatched, despite being contracted through the capacity market.

The new rules introduced year-round performance requirements for capacity resources along with incentives to perform and steep penalties for failing to do so.

Critics of the new rules argued they would increase the cost to secure capacity by billions of dollars. After FERC approved the changes in June 2015, challengers petitioned the commission for a rehearing, which the commission denied.

Nine organizations challenged FERC’s denial in court. The ensemble is a somewhat unusual partnership of environmental groups (the Natural Resources Defense Council, Sierra Club and Union of Concerned Scientists), representatives of utilities (the American Public Power Association, the National Rural Electric Cooperative Association and the Public Power Association of New Jersey), the Advanced Energy Management Alliance, which represents demand response resources, American Municipal Power, which represents both utilities and resources, and the New Jersey Board of Public Utilities.

FERC’s Reasoning Upheld

The ruling by Judges A. Raymond Randolph, Janice Rogers Brown and David B. Sentelle was unanimous. The court ordered the clerk to withhold issuance of the mandate resulting from the ruling to give the plaintiffs time to file petitions for rehearing before the three-judge panel or the full court.

PJM DC circuit capacity performance rules
Left to right: Judges A. Raymond Randolph, Janice Rogers Brown, David B. Sentelle | U.S. Courts

The court’s decision points out that FERC acknowledged the increased capacity costs but cited a study that estimated the new rules would create an annual net savings of potentially billions of dollars starting in 2016. The fact that the study used a penalty that was higher than FERC approved was immaterial, the court found.

“The savings come from the penalty successfully increasing reliability,” the court said in its decision. “Even with a lower penalty, the net savings may be substantial.”

FERC “does not have to find net savings” to approve proposed changes, the court found, and higher costs can be warranted if they increase reliability. FERC said the revisions would do that and also help avoid energy price spikes.

Year-Round Resource Requirement

PJM’s requirement that all CP resources be year-round attracted opposition from numerous groups.

NRDC, Sierra Club and UCS said that the requirement discriminated against seasonal generation such as wind and solar — despite the RTO’s offer that winter-only resources could aggregate with summer resources — because aggregation imposed “transactional costs.”

PJM DC circuit capacity performance rules
Utility Scale Solar in Maryland | Constellation

AMP, meanwhile, said aggregation should also be open to traditional resources.

The judges said none of the challenges persuaded them to question the commission’s judgment. “The commission’s policy decision to assess reliability through a year-round capacity commitment is the type of policy judgment to which we afford deference, and that deference is justified by the record,” they said. “The law provides no basis to claim the commission cannot approve uniform performance requirements simply because those requirements will be easier to satisfy for some generators than for others.”

Demand Response

AEMA had problems with CP’s impact on DR, challenging PJM’s proposal to use separate formulas for calculating expected consumption during summer months and non-summer months.

The group said it supported the “peak load contribution” method for the summer, which is based on a DR customer’s contribution to the five hours of the previous year when systemwide demand peaked. It opposed the “customer baseline load” method for non-summer months, which is based on the customer’s contribution to the system’s load for the four days of peak systemwide load during the most recent 45 days.

“Because it was reasonable for the commission to accept PJM’s proposal to use the recent-peak method for non-summer months and any alleged departure from past practice was adequately explained, we defer to the commission’s determination on this issue,” the court said.

AEMA Executive Director Katherine Hamilton said the court rebuff means consumers will face reduced choices and higher prices because residential DR and renewable resources “could be forced out of the market altogether.”

“In the recent auction, the amount of demand resources — both offered and cleared — fell by thousands of megawatts compared with previous years. PJM has now effectively ceded jurisdiction for monetizing these competitive products in the capacity markets, and it will be up to state commissions located in PJM to determine how these products will be operated going forward,” she said in a statement. “As AEMA considers legal options moving forward, we will continue working within the PJM stakeholder process on wholesale competitive market issues and with state commissions on demand response solutions for consumers.”

Procedural Challenge

The court also rejected challenges by APPA, NRECA and PPANJ to PJM’s filing of proposed changes to the capacity market under Federal Power Act Section 205 and its simultaneous Section 206 complaint proposing replacements for energy market rules it said were no longer just and reasonable.

PJM could not file changes to the Operating Agreement under Section 205 because it did not seek stakeholder approval of the changes.

The public power groups argued that the commission could not accept PJM’s Section 205 filing as just and reasonable while simultaneously finding that the filing rendered the Operating Agreement unjust and unreasonable under Section 206. “In effect, FERC found that PJM had created the factual premise and legal basis for FERC to order a change in rates that PJM could not have unilaterally made,” the groups said. “This bootstrapping of results is impermissible.”

The court said the petitioners failed to “explain why PJM’s Section 205 filings regarding the capacity market necessarily must complement existing energy market agreements to be just and reasonable” and cited “no precedent for their theory that the commission was required to act ‘under Section 206 alone.’”

“We therefore see no reason why the commission was not entitled to approve changes under Section 206 in anticipation of the impacts of the Section 205 filing rather than wait for those impacts to be realized,” the court ruled.

Penalties Too Low

PPANJ and the New Jersey BPU contended the CP penalties for resources that fail to meet their capacity commitments during an emergency hour were too low to ensure performance.

The commission approved a penalty rate equal to one-thirtieth of the net cost of new entry per megawatt-hour of shortage. The petitioners said the 30-hour denominator — based on the number of emergency hours in 2013-2014 — was too high, resulting in a penalty that was too low.

“The commission had good reason to conclude that the formula results in a high enough penalty to encourage resources to meet their capacity commitments,” the judges said. “The commission decided the penalty was also low enough to avoid introducing ‘excessive risk’ into the capacity market. Too high a penalty could discourage even reliable resources from entering the market. We defer to the commission’s balancing of these competing concerns.”

Default Offer Cap

Also rejected was a complaint by the BPU and four organizations representing utilities that PJM’s default offer cap, meant to reflect the CP penalties and bonuses, is too high. PJM would only include an offer above the cap in the capacity auction if it determines it is cost-based.

The court rejected complaints the cap could increase capacity costs, saying “increased capacity prices are necessary” to encourage entry of new, reliable resources. “Resource owners need to be able to offer capacity at a higher price in order to recover the costs of improvements,” it said.

Unit-Specific Constraints

AMP challenged the imposition of penalties on CP resources that fail to perform because of unit-specific constraints, saying it was inconsistent with energy market rules, which require PJM to cover resources’ costs if it schedules the them to run outside of their parameter limits.

“Given the different purposes of the capacity market and the energy market, there is no inconsistency in treating the operating-parameter limitations differently in the two markets,” the court said.

DOE Approves Emergency Dispatch of Yorktown Units

By Rory D. Sweeney

PJM on Monday secured U.S. Department of Energy approval to dispatch Dominion Energy’s recently shuttered Yorktown coal-fired plant to address potential reliability issues on Virginia’s Middle Peninsula.

Dominion, which closed the plant in April to comply with an EPA mandate, said it anticipated the department’s order and is prepared to restart both units at the plant as necessary.

dominion doe yorktown units
Yorktown Generating Station | Dominion

Energy Secretary Rick Perry granted PJM’s request for a 90-day window to dispatch the units as necessary to “maintain grid reliability,” and the order can be renewed upon request indefinitely if the situation remains unchanged. PJM and Dominion are required to create a dispatch methodology and submit what dates the units are operated, along with estimated emissions and water usage, to the department.

“While this is not a long-term solution to the reliability issues, Dominion Energy supports PJM’s action and the DOE decision, and will work to ensure the units’ availability as required,” Dominion spokesperson Bonita Billingsley Harris said in an emailed statement.

Stalled Project

The order stems from Dominion’s difficulty in gaining approval for the proposed Surry-Skiffes Creek 500-kV transmission line across the James River, which has for years faced opposition from local and environmental activists. Approved by the PJM Board of Managers in 2012, the transmission project remains stalled pending permit approval from the Virginia Marine Resources Commission (VMRC) and a waiver from the state Department of Environmental Quality for water quality certification. The U.S. Army Corps of Engineers issued a conditional permit earlier this month that requires approval from both agencies.

dominion doe yorktown units
Map of transmission system at Virginia’s middle peninsula | PJM

The project will additionally require a special-use permit from the James City County Board of Supervisors. Members of the public will have the opportunity to weigh in during both the VMRC and county permit hearings, Harris said.

Dominion estimates the line would take at least 18 months to construct after all permits are approved. The company had hoped to complete the project prior to closing the Yorktown units, which are among the few generators able to serve load in the populous but isolated North Hampton region.

While Dominion sought to shutter Yorktown by 2014 to avoid expensive emissions upgrades required by EPA’s Mercury and Air Toxics Standards, PJM required the units to remain operational to maintain reliability on the peninsula in the absence of the proposed line. State and EPA approvals extended the shutdown deadline several years, but applicable extensions finally ran out on April 15 and Dominion closed the doors.

Dominion warned that failure to build the line before shutting down the units could result in blackouts, an assertion opponents dismissed as scare tactics. In February, the company provided PJM a regional remedial action scheme that calls for dropping service to approximately 150,000 customers in the event of an emergency in order to prevent potential voltage collapse from N-1-1 contingencies. (See Opposition to Va. Tx Line May Trigger Unintended Consequences.)

No Surprise

The order didn’t catch Dominion by surprise.

“When it became apparent we would not receive approvals in time to complete the new transmission line before the coal units had to be retired, we pursued an aggressive plan of equipment upgrades, enhanced inspections, maintenance scheduling and contingency preparations to protect energy reliability on the Virginia Peninsula until the permanent solution could be put in place,” Harris said.

While the company was prohibited from running the Yorktown units after April 15, its contingency plans included keeping them in operating condition in case of an emergency, she added.

Despite its potential open-ended approval to run the units, Dominion said it remains committed to shutting them down and building the transmission line.

“This law protects PJM and Dominion from civil or criminal liability or citizen suit, but it is our intention to continue moving forward as quickly as possible to build and energize the transmission project limiting the time these units will operate to ensure the best environmental outcome,” Harris said.

Comprehensive DER Oversight Best, NYDPS Hears

By Michael Kuser

ALBANY, N.Y. — Regulatory oversight of distributed energy resources is better fully mapped out at the beginning of the process rather than built piecemeal, more than a dozen industry stakeholders told staff of the New York State Department of Public Service on Monday at the second of two technical conferences on DER oversight.

distributed energy resources NYDPS
New York PSC Technical Conference on DER Oversight

The first conference was held June 12 to explore how the Public Service Commission can best regulate utilities and protect consumers through the application of uniform business practices and marketing standards in the new era of rooftop solar and residents becoming “virtual” DER providers through membership in community distributed generation programs.

“What we have done in other areas is we’ve erred on the side of being more generous in the initial phase, trying to support new markets, but then you go to try to introduce new rules [and] people go crazy,” said Erin Hogan, director of the state’s Utility Intervention Unit. “So in my mind, it almost seems better to start with a more comprehensive structure and take away, as opposed to trying to add when you’ve discovered a problem.”

The PSC in March adopted a new “value stack” pricing mechanism for solar and other DER, along with two other orders to transition utilities into “distributed system platforms” and align their incentives with DER providers. The Value of Distributed Energy Resources order approved March 9 (Case NYPSC Adopts ‘Value Stack’ Rate Structure for DER.)

Benefit of the Bargain

distributed energy resources NYDPS
Weiner

Scott Weiner, DPS deputy for markets and innovation, chaired the June 19 roundtable discussion and emphasized that “we’re dealing with not the purchase of bread or the repair of a car, which has its own protection, but with the provision of electricity and the opportunity of companies to enter into a marketplace, an expanded marketplace that has been created by the commission. The underlying question is, what responsibility does the commission have to make sure that end-use customers receive the benefit of the bargain that they’re agreeing to?”

“Oversight is important to build consumer confidence,” said Sara Margaret Geissler, manager of customer operations regulatory performance at Consolidated Edison. “We all want to create a market that they can have confidence in … and a core part of that is making sure, or having enough guidelines to ensure, that they understand what they’re signing and they know who to call if they have an issue.”

Geissler represented the joint utilities at the technical conference, which also include Central Hudson Gas & Electric, National Grid (which owns New York State Electric and Gas, and Rochester Gas and Electric), Orange and Rockland Utilities, and Rockland Electric.

Differentiate the Customers

distributed energy resources NYDPS
Strauss

Valerie Strauss, policy director at the Association for Energy Affordability, noted the importance of differentiating between residential and commercial customers — and between different levels of commercial customer.

“We need to look at this in terms of the risk to the consumer,” Strauss said. “The current proposal is a blanket [that] kind of covers everybody. … We would suggest that that be revisited and some changes made for the provisions to more reflective of the risk.”

Strauss suggested that commercial customers could be differentiated by the number of units they control: “Certainly a mom-and-pop owner who has five buildings with 10 units each is not a sophisticated [commercial and industrial] customer. A property manager who owns 100 buildings that have 100 units each probably is.”

Community DG is new in New York but not in other markets, according to Hannah Masterjohn, policy vice president at the Clean Energy Collective.

“We have pretty substantial markets in Massachusetts, in Colorado, where we’ve already got thousands of customers participating in projects,” Masterjohn said. “When we look at our experience … we find low complaints overall, and the vast majority are related to utility billing issues. When we’re talking about community solar, the customer’s paying a third-party provider, but what they’re paying for is bill credits on their utility bill, so that benefit that’s getting delivered to them, that’s where they have most challenges.”

David Sandbank, director of the New York Sun program at New York State Energy Research and Development Agency, has overseen 64,000 solar installations since 2012 and said that his program doesn’t have any oversight over community DG.

“Right now, our focus is really on system performance of the main system itself,” Sandbank said. “There’s no specific protections for community solar subscribers in New York. … We have provided a lot of customer education on our website and we’ve launched a very robust digital marketing campaign to educate potential solar customers.”

Zack Dufresne, communications director at the Alliance for Clean Energy New York, asked whether the state could afford to regulate heavily.

“These regulations will take significant resources on the part of the PSC,” he said, “and I’m wondering if starting off with this maximalist position, [will] the DPS staff have the resources in place for that?”

“Let’s not have the tail wag the dog,” Weiner said. “If we feel there are certain activities that commission staff should be engaged in, we’ll make sure we have the resources.”

Honorable: Leaving FERC, but not Sure When

By Tom Kleckner

CHICAGO — Colette Honorable continues to play it coy when discussing her future.

FERC Commissioner Colette Honorable | © RTO Insider

The FERC commissioner has said she would not seek a second term when her current one expires June 30. What she has not said is whether she will leave on that date or stay on until a replacement is nominated. (See No 2nd Term for FERC’s Colette Honorable.)

Honorable alluded to the uncertainty during a Monday luncheon address to fellow regulators, friends and attendees at the Mid-America Regulatory Conference. It was her only appearance during the conference, but it kept her long MARC attendance streak alive.

“I should have had a T-shirt made up: ‘I haven’t announced when I’m leaving, and I haven’t announced what I’m doing,’” she said.

One thing’s for sure: Honorable will spend at least the next two years in D.C. Call it returning the favor to her 16-year-old daughter, Sydney, who is still in high school.

“She loves it [in D.C.],” Honorable said. “I owe it to her. She was very good when I moved there.”

Honorable was nominated by President Barack Obama in August 2014 to fill the remainder of former Commissioner John Norris’ term. She was unanimously confirmed to the post by the Senate later in the year.

Honorable — who announced her departure in April — and acting Chairman Cheryl LaFleur have held down the fort at the quorum-less commission since February, when Chairman Norman Bay resigned.

Pennsylvania Public Utility Commissioner Robert Powelson and Neil Chatterjee, senior energy policy adviser to Senate Majority Leader Mitch McConnell (R-Ky.), were only recently nominated to fill two of the three vacancies. Both easily cleared the Senate’s Energy and Natural Resources Committee, but have yet to be confirmed by the full body. (See FERC Nominees Easily Advance to Full Senate.)

Powelson is president of the National Association of Regulatory Utility Commissioners, a post Honorable once held.

“I’m looking forward to when Rob joins us at FERC, or joins Cheryl,” Honorable said, a sly comment some in the audience missed.

An Arkansas native, Honorable was named to the state’s Public Service Commission in 2007. She chaired the PSC from January 2011 until January 2015, succeeding Paul Suskie, now SPP’s executive vice president of regulatory policy and general counsel, and one of her “work husbands.” (Her real husband died shortly before her FERC nomination.)

Acknowledging “uncertain times for regulators,” Honorable had some words of advice for those in her profession.

“We absolutely must protect our ability to work independently, no matter who is in office,” she said. “I want to urge you to stay true to that. I would have been shocked if the White House called and asked me to vote on something in a certain way. Keeping the lights on, reliably and safely, does not have a political or ideological bent.”

Honorable’s fellow regulators responded with a standing ovation, perhaps her last as a FERC commissioner.

She has no regrets about her decision.

“At the end of the day, I’m proud I kept the consumers first in my work,” she said. “It doesn’t mean I’ve been anti-business. In fact, I was shocked to read an article that described me as pro-business. It just shows I can work pragmatically by bringing together people from both sides of the aisle.”

Trump Brings Uncertainty to ISO-NE, Regulators

By Michael Kuser

MARLBOROUGH, Mass. — Environmental activists and state and RTO officials agreed Thursday that President Trump’s rollback of Obama administration energy and climate policies are causing uncertainty for New England officials even as some states attempt to fill the void.

Two panels at the Northeast Energy and Commerce Association Environmental Conference on June 15 discussed the implications of the Trump administration’s policies, including proposed EPA budget cuts and two executive orders to reduce regulations and prevent implementation of the Clean Power Plan.

Ad Hoc Decision Making

Former EPA Deputy General Counsel Ethan Shenkman said Trump’s May 28 order — which called for a sweeping re-examination of all U.S. energy and environmental policies to eliminate burdens on domestic energy resources — may result in ad hoc decision making (Executive Order 13783). (See Trump Order Begins Perilous Attempt to Undo Clean Power Plan.)

In addition to seeking to eliminate the Clean Power Plan, the order also directs the Council on Environmental Quality to rescind its guidance on how federal agencies should consider greenhouse gas emissions and the effects of climate change in National Environmental Policy Act (NEPA) reviews. CEQ coordinates federal environmental efforts and works with agencies and White House offices in the development of environmental policy. NEPA reviews are required for any “major” federal action.

Trump also ordered the elimination of the Interagency Working Group on Social Cost of Greenhouse Gases, created by the Council of Economic Advisers and the Office of Management and Budget in 2009, and dismissed the group’s work products as “no longer representative of governmental policy.” Instead, Trump ordered that “when monetizing the value of changes in greenhouse gas emissions resulting from regulations,” agencies rely on a 2003 Bush-era finding by OMB.

Withdrawing the guidance document means “you’re back to a situation of uncertainty and some ad hoc decision making as each agency in region by region decides how they’re going to address these issues going forward,” said Shenkman, a partner with law firm Arnold & Porter Kaye Scholer.

State Funding Worries

ISO-NE environmental and regulatory analyst Patricio Silva gave a presentation that highlighted Trump’s proposed 31% reduction in EPA’s budget for fiscal year 2018, to $5.7 billion from $8.2 billion this year. Silva said the cuts could impact New England states’ capacity to enforce environmental regulations. In 2016, Connecticut, Vermont, Massachusetts and Maine relied on EPA for 21 to 24% of their environmental agency budgets, while New Hampshire and Rhode Island saw the federal grants fund 35%.

Roger Reynolds, of Connecticut Fund for the Environment/Save the Sound, said the proposed 31% reduction would eliminate funding for estuaries and the Great Lakes. “And since we’re closely associated with Long Island Sound, that concerned us greatly,” he said. “Long Island Sound generates $18 billion annually for the regional economy, and that’s on the low end of the estimates.”

Noting that his group received $8 million in federal funding in 2017, twice its 2016 outlay, Reynolds said that “it’s not entirely clear — in fact, quite the opposite — that Congress is necessarily in lock-step [with Trump], especially on environmental funding.”

Silva also pointed out that presidents’ proposed cuts don’t always survive Congress. For example, President Ronald Reagan proposed 25% to be cut from the EPA budget over two years, and the budget for fiscal 1982 ended up being decreased by 7%, Silva said.

‘Rollback Rebound’

“There is a significant amount of uncertainty now facing all segments of the industry when it comes to determining what’s going to happen and what are the consequences of the regulatory agenda that the incoming administration has been outlining,” Silva said.

After Trump announced his decision to withdraw from the Paris Agreement on climate change June 1, several states, including most of New England, vowed to uphold U.S. commitments to reduce greenhouse gas emissions. Silva said this is evidence of the risk of a “rollback rebound” — a term he credited to D.C.-based consultants ClearView Energy Partners. If states rush to fill the vacuum left by the Trump administration, Silva said, they could create a patchwork of regulatory policies that further complicate business for energy developers. (See Trump Pulling U.S. Out of Paris Climate Accord.)

ISO-NE EPA trump

| ISO-NE

“We have no idea what’s going to happen with the high-priority infrastructure initiative that the administration’s put out,” said Silva. “Again, with the absence of any staff at CEQ to implement these programs and also … the withdrawal of policy guidance on how greenhouse gas is accounted for… we now run the risk that if a new transmission project is developed here in the region, it could be facing different greenhouse gas standard assessments by FERC, Fish and Wildlife [Service] and Army Corps of Engineers. And then CEQ would be stuck trying to reconcile all those different approaches.”

Lack of staff could jeopardize permitting and oversight not only for new transmission, but also for generators, pipelines, fuel storage and port projects, he said.

Silva repeated a comment by lobbyist and former Trump transition official Michael McKenna, president of MWR Strategies, who said “personnel is policy.”

“At 120 days in, we have any number of federal departments and other entities that affect energy policy across the country that have significant vacancies,” Silva said. “[At] EPA, only two out of 13 senior staff positions [have been] either nominated or confirmed.”

FERC’s loss of its quorum in February is “a source of particular anxiety, since they regulate us,” Silva said. “There are many ISO/RTOs that have more pressing matters that have been delayed by the lack of the quorum.” A Senate panel on June 6 cleared nominees Neil Chatterjee and Robert Powelson for a vote by the full Senate. (See LaFleur Ready to Welcome New Members as FERC Backlog Grows.)

FERC will be controlled 3-2 by Republicans once all the vacancies are filled, raising the chance of a change in ideology. For now, a lack of clear policy from the commission on the treatment of nuclear resources and integrating markets and public policy “could complicate a variety of both state initiatives, but more importantly from our perspective, it complicates and makes planning much more difficult,” Silva said.

Freeze on Rulemaking

Executive Order 13771, issued Jan. 30, calls for federal agencies to rescind two regulations for every one promulgated, making it perhaps the most significant of Trump’s orders, said Seth Jaffe of law firm Foley Hoag. “It’s not about regulatory budgeting or anything; it’s about a freeze on significant regulations,” said Jaffe, who moderated a panel on regulatory changes at the end of the day and also participated with his own presentation.

The March order also could be significant because it is not only about getting rid of the CPP, but also rescinding all the Obama administration executive orders and guidance on climate issues, Jaffe said. “Top to bottom, wipe the slate clean on everything Obama did on climate and federal [policy].”

Jaffe said Trump picked a good point of attack on the CPP, which some experts say may have exceeded EPA’s authority by seeking to impose regulations beyond generators’ “fence line.”

“The Trump administration [could] say ‘We’re not going to get rid of the endangerment finding. We’re still going to regulate greenhouse gases from power plants where we have jurisdiction, but what we’re going to do is just regulate greenhouse gases from those power plants, rather than somehow pretend that what we’re regulating is emissions from power plants when what we’re really doing is incentivizing renewable energy.’”

While that is a sound legal argument, Jaffe said, the Trump administration may risk losing the deference usually shown by the courts to the executive branch if it ignores climate science and fails to provide a rational basis for its reversal of Obama policies.