Search
`
November 14, 2024

FERC Approves Cost Recovery for Exelon’s Mystic Plant

FERC on Wednesday approved Exelon’s request for recovery of more than $1.5 million in fuel costs for its natural gas-fired Mystic Generation Station in Everett, Mass. (ER17-933).

The commission order granted Exelon $1,554,854 for Mystic Units 8 and 9 fuel costs that were not recovered because of market power mitigation measures applied last October and November.

ISO-NE’s Internal Market Monitor challenged Exelon’s request for cost recovery for mitigated hours on three days in October 2016, arguing that the company did not adequately provide data in its initial request, and that further supplemental information was submitted past the due date under the RTO’s Tariff.

ferc exelon mystic generating station
Mystic Generation Station

“We disagree with the IMM’s position that Exelon’s alleged failure to timely submit information to the IMM for operating days Oct. 1, 3 and 4, 2016, precludes Exelon from seeking additional cost recovery for those days,” the commission said in response. “We do not find that failure to meet that deadline alone necessarily operates as a procedural bar to submitting a [Federal Power Act] Section 205 filing for additional cost recovery or renders such a filing unjust and unreasonable.” It noted that Exelon’s initial filing was submitted on time and that the Monitor did not dispute that certain required information was unavailable to the company at the time.

Exelon also asked to recover nearly $57,000 in regulatory costs in connection with its filing, as well as additional regulatory costs it might incur in connection with the proceeding after the date of its filing. The commission granted this request subject to a compliance filing due in 60 days that details the total regulatory costs.

— Michael Kuser

CAISO Board Approves RAS Modeling Proposal

By Jason Fordney

CAISO’s Board of Governors on Tuesday unanimously approved rule changes that would allow market participants to partake in a program that models generator outages and the impact of remedial action schemes (RAS) on market operations.

caiso ras generator contingencies
Cook | © RTO Insider

During a presentation to the board, CAISO Director of Market and Infrastructure Policy Greg Cook said “stakeholders are generally supportive of the proposal” — but some still worry about unintended consequences.

The board’s vote greenlights modeling of generator contingencies and RAS in the day-ahead and real-time markets, as well as the congestion revenue rights allocation process, but the package still requires approval by FERC.

CAISO’s current modeling only addresses situations in which a transmission line goes down, potentially causing overflow on other lines. The new generator modeling reflects how the system will react to the loss of generation and is meant to ensure that transmission lines are not overwhelmed as the system picks up to address the unexpected shutdown of a generator.

RAS are protective processes that automatically disconnect generators or load to prevent transmission line overload in the event that another line goes out. The new method will update the ISO’s security constrained economic dispatch by modeling the loss of generation within the dispatch, as well as modeling the loss of transmission and generation because of RAS operations. The ISO currently uses manual, out-of-market dispatches to manage generator contingencies.

The changes will alter the congestion component of LMPs so that they consider the cost of positioning the system to account for generator contingencies and RAS operations. A RAS-connected generator does not increase congestion and will potentially receive higher energy prices than other generators at the same bus.

The Western Energy Imbalance Market (EIM) Governing Body on Sept. 6 approved the rule changes for generators that are within the EIM but outside the ISO. (See EIM Body Approves Generator Loss Modeling Plan.) Body Chairman Doug Howe on Tuesday urged the CAISO board to carefully implement the proposal.

caiso ras generator contingencies
The CAISO Board of Governors Met in Folsom on Tuesday | © RTO Insider

Howe said the change will increase the efficiency of the real-time market across the EIM, improve dispatch and lead to more accurate market prices. But he also urged the ISO to ensure the new rule doesn’t create market abuse or too much complexity.

Southern California Edison raised concerns that the program would create a new value stream that could incentivize participants to pursue RAS rather than building new transmission. A company representative questioned whether generators on RAS should be rewarded with higher locational prices.

Trying to value RAS resources “gives us pause,” and the implementation should be carefully monitored, said SCE Director of State Legislative Policy Catherine Hackney. SCE has thousands of megawatts of generation under RAS.

“We need to be vigilant about watching and being wary and being able to respond if things don’t go exactly how we like,” Hackney said.

When it unveiled the proposal in May 2016, CAISO said it had more than 20 RAS modeled within its own system, with more throughout the Western Interconnection. (See Stakeholders Wary of CAISO Contingency Modeling.) The ISO currently factors RAS into its market operations through adjustments to its market software but views that approach as inadequate.

FERC Upholds PGE ISO Incentive Adder, Rebuffs CPUC

By Robert Mullin

FERC on Wednesday rejected an argument by the California Public Utilities Commission that it erred last year in allowing Pacific Gas and Electric to include a 50-basis-point ISO participation adder in the utility’s 2017 transmission rates proposal.

The PUC filed its protest last November after FERC conditionally accepted PG&E’s proposed rate increase while at the same time denying the PUC’s request to throw out the adder, calling it a $30 million “unjustified windfall” at the expense of California ratepayers. (See CPUC Contest ISO Incentive for PG&E.) The Sacramento Municipal Utility District joined the protest.

The PUC at the time contended that the ruling ignored “the need to demonstrate that an incentive must be ‘justified’ pursuant to [FERC] Order 679,” which allows transmission owners to collect the adder as motivation to join an RTO or ISO. Because the PUC requires California’s investor-owned utilities to be members of CAISO, PG&E did not warrant incentive treatment, the PUC said.

The commission’s Sept. 20 order rebuffed that argument, saying that the PUC had raised the same argument more than 10 years ago in its rehearing request of Order 679, which was rejected in a follow-up order (ER16-2320).

ferc pacific gas & electric cpuc pg&e
Pacific Gas and Electric transmission lines | PGE

“If the CPUC disagreed with the commission’s determination in Order No. 679-A, the appropriate course of action was to seek judicial review of Order Nos. 679 and 679-A under Section 313 of the” Federal Power Act, FERC said. “The commission has also already held that arguments opposing the granting of an incentive adder for RTO membership to existing RTO members constitute a collateral attack on Order No. 679-A, and we find that the CPUC’s assertion here is in the same vein and warrants the same response.”

The commission also rejected the PUC’s contention that FERC erred by granting the 50-basis-point adder without weighing the specific facts of the case and considering whether a different incentive might be more appropriate. The PUC noted that FERC’s September 2016 order had subjected PG&E’s final return on equity to a hearing by a settlement judge. (See FERC Sets PG&E Rate Increase Proposal for Talks.)

FERC said it approved the adder subject to it being it being applied to a base ROE that left the full ROE within the “zone of reasonableness” determined by the settlement judge.

“Thus, the commission’s duty to ensure just and reasonable rates for consumers will be fulfilled via the trial-type evidentiary hearing process we have ordered, which will result in an ROE, including the proposed adder, that must fall within the zone of reasonableness, and that trial-type evidentiary hearing process is one in which the CPUC may participate,” FERC said.

FERC also said it was “not persuaded” by the PUC’s contention that PG&E’s continued membership in CAISO is not voluntary. It noted that FERC Order 2000 spelled out that voluntary membership was the “most appropriate” approach for creating and expanding RTOs and ISOs.

“This longstanding commission policy of voluntary RTO/ISO formation and membership remains unchanged,” FERC said. “This longstanding commission policy is also reflected in CAISO’s currently effective Transmission Control Agreement, which is on file with the commission.”

GE Power Pitches its Global Perspective to IPPNY

By Michael Kuser

SARATOGA SPRINGS, N.Y. — Refurbishing an existing combined-cycle plant can squeeze an extra 12 to 15 MW of generating capacity from each gas turbine — and the compelling economics of equipment upgrades provide New York generators a choice beyond building new plants.

GE Power IPPNY
Bob Prantil, executive director of sales and strategic accounts, GE Power North America | © RTO Insider

That was the view of Bob Prantil, executive director of sales and strategic accounts for GE Power North America, who spoke Sept. 14 at the fall conference of the Independent Power Producers of New York.

“After all the debates and discussions, eventually electrons need to be placed on a grid at the lowest LCOE [levelized cost of electricity] to make sure that whoever is providing those electrons can break even,” Prantil said. “We recently combined our power business with our grid business because that’s what the market wanted. When you’re going to speak to a utility, it’s not just necessarily about generation. You have to figure out how to get those electrons around.”

Existing Versus New Generation

While New York has a goal of getting 50% of its electricity from renewable resources by 2030, Prantil pointed out that other states are looking at more. Iowa, for example, aims to reach 100% renewable energy over the next five years.

“You all know the complexity of new generation from the standpoint of permitting and do people want it in their backyards — and the construction, where it makes sense,” Prantil said. “I would just challenge you to understand the existing generation that you have in-state already and what [original equipment manufacturers] can do to reduce overall CO2 emissions, gain more efficiency and get more output from those plants at a quarter of the price of a new plant being built.”

Energy conferences these days focus more on renewables and efficiency than on gas, which strikes Prantil as odd.

“Especially in the northeast United States, if you see what’s going on in PJM, there has been an uptick in the installation of combined cycle plants,” he said. “If you think about the sizes of gas turbines now and the efficiencies of those turbines compared to just 10 years ago, it makes the decision to go with gas, as some people call it, a bridge fuel before 100% renewables, a very smart decision.”

ge power ippny
GE Power’s 9HA.01 gas turbine helped the company earn a Guinness World Records™ title for powering the world’s most efficient combined-cycle power plant in Bouchain, France. |  GE Power

GE Power just set a world record with the company’s first plant in France. Prantil said the combined cycle unit is 99.95% available and achieved a record-setting 62.6% thermal efficiency, 5 percentage points higher than the best combined cycle plants could have achieved just five years ago.

“If you take that efficiency over the life cycle of a plant and then you look at the LCOE for that, and you think about the saved BTUs and CO2, it’s a pretty compelling story,” Prantil said.

Energy Storage and Hybrids

GE built one of the first battery plants in the U.S. in Schenectady, N.Y. “So we know how to do all this,” Prantil said. “We believe that energy storage prices are going to come down.”

He said California has been doing generation-storage hybrids longer than New York, but instead of trying to figure out how to create new markets — which is what New York is doing — GE is looking at how to take an existing market and apply battery technology to it. He cited a case in California where GE applied storage technology to the famed “duck curve.”

“That power needs to be instantaneous, almost like spinning reserve,” Prantil said. “So if you take a 50-MW gas turbine that takes eight or nine minutes to ramp up to speed … you put in a four-hour battery that’s being charged by the grid. We can have the battery take over for the seven minutes of ramping.”

GE sees energy storage as a very cost-effective way to meet some of the ancillary requirements of RTOs and ISOs — and there has to be an ancillary service for any developer to do it and get paid.

GE Power IPPNY
GE workers with GE 9HA.01 gas turbine at factory in Belfort, France | GE Power

“We always want to get the EEI [Edison Electric Institute] award for a 1,200-MW combined cycle plant or some offshore wind farm, but we got the EEI award for a 15-MW battery hybrid system,” Prantil said.

Energy efficiency is also driving changes to the dispatch stack, which will also occur in NYISO, he said.

“A developer will look at what zone they’re in, and if there’s a combined cycle plant in that zone, they want to know the efficiency of that plant. And if a generator can build a more efficient plant in that zone, or increase the efficiency of an existing plant, their capacity is more likely to get dispatched.”

New York Native

A native New Yorker schooled in Brooklyn, Queens and the Bronx, Prantil said GE is also a native of the state.

“The headquarters of our GE Power business from the very beginning, from the Thomas Edison years, is located 20 miles from here in Schenectady,” he said.

Prantil noted that GE technology has outfitted about half the state’s nuclear fleet and wind farms, as well as providing 152 gas turbine units and 116 steam and hydro turbine units.

“We like to say that New York is powered by GE, as 60% of the megawatts generated in New York comes from GE equipment,” Prantil said. “We have 152 gas turbine units, we have 116 turbine units, half of the nuclear fleet is with GE technology and about 50% of the installed blades in wind is with GE technology.”

If New York decides to go heavily into offshore wind, GE’s not going to debate if that’s right or wrong, he said, but will instead figure out how to develop the resources at the lowest cost.

Environmentalists Denounce FERC Millennium Pipeline Ruling

By Michael Kuser

Environmental advocates criticized FERC for ruling last week that New York state failed to act in a timely manner on water quality permits sought by Millennium Pipeline.

FERC EPA Millennium Pipeline natural gas pipelines
New York State Department of Environmental Conservation Headquarters

In its Sept. 15 order, the commission ruled that the New York State Department of Environmental Conservation (DEC) had waived its authority to issue or deny a water quality certification for the project by failing to act within the one-year time frame required by the Clean Water Act (CP16-17).

In a statement, the department said it is reviewing FERC’s decision and would “consider all legal options to protect public health and the environment.” It would have to file any appeal with the D.C. Circuit Court of Appeals.

But opponents of the natural gas pipeline extension — the 7.8-mile Valley Lateral spur to the Valley Energy Center in Wawayanda, N.Y. — were not as circumspect.

“This is just another warping of the law by FERC,” Maya van Rossum, director of the Delaware Riverkeeper Network, told RTO Insider. “It’s not the first time, and it probably won’t be the last, that FERC acts only to help its friends in the pipeline industry.”

Sierra Club Atlantic Chapter Director Roger Downs said in a statement that “nowhere is FERC granted the right to override” a state’s authority to regulate its water quality.

Timeliness of the Essence

Millennium Pipeline in July filed with the commission a request for notice to proceed with construction, asserting that the DEC had failed to act before the statutorily imposed deadline. The department responded days later that it had not waived its authority, which it exercised on Aug. 30 when it denied Millennium’s application for certification.

FERC EPA Millennium Pipeline natural gas pipelines
| Millenium Pipeline

Millennium and the department differed on when the one-year review process began, with the company contending that the clock started ticking when it submitted its application to DEC in November 2015. The DEC countered that the one-year period did not begin until it received a “complete” application on Aug. 31, 2016. (See Pipeline Sues to Force NY to Issue Permit for CPV Plant.)

FERC said in its order that the “starting point for interpreting a statute is the language of the statute itself,” and that “Section 401 [of the Clean Water Act] provides that water quality certification is waived when the certifying agency ‘fails or refuses to act on a request for certification, within a reasonable period of time (which shall not exceed one year) after receipt of such request.’ Thus the term ‘receipt’ specifies the triggering event.”

The commission ruled that “giving effect to the plain text of a statute, the one-year review period began November 23, 2015” — when the DEC received the application.

New Pattern

Gavin Donahue, CEO of the Independent Power Producers of New York, last week told participants at the group’s fall conference that “the siting of natural gas pipelines is FERC’s jurisdiction, but the DEC has developed a pattern of denying water quality certificates for projects, most recently evidenced by the decision on the Millennium Pipeline.” (See NYPSC Chair Promises ‘Continuity’ on State Energy Policies.)

New York environmentalists might have thought they were succeeding in stopping pipelines after the 2nd U.S. Circuit Court of Appeals last month ruled that the department acted within its authority to deny water quality permits sought by Williams Co. for its Constitution Pipeline.

Now the natural gas industry sees hope. Following the Millennium order, Reuters reported that Williams now plans to seek a similar permit ruling from FERC.

Federal Officials Side with Utilities on Tree-Clearing Bills

By Rich Heidorn Jr.

The Trump administration sided with utility witnesses Tuesday on legislation to streamline approvals for managing vegetation near power lines on federal land, an effort to reduce wildfire risks.

Witnesses from the Bureau of Land Management, the National Forest Service and two utilities endorsed separate House and Senate bills to amend the Federal Land Policy and Management Act (FLPMA) and provide authority to exempt existing rights of way (ROWs) from reviews under the National Environmental Policy Act (NEPA).

The Wilderness Society, however, said it opposed the House bill, the Electricity Reliability and Forest Protection Act (H.R. 1873), because it would impose “counterproductive limitations and obligations on both utilities and federal land managers, inappropriately shift costs from utilities to taxpayers and agencies, and undermine the public interest in the management of their public lands.”

FERC vegetation management federal land
Witnesses from the Bureau of Land Management, the National Forest Service and two utilities endorsed separate House and Senate bills to streamline approvals for managing vegetation near power lines on federal land. Left to right, Glenn Casamassa, National Forest System; John Ruhs, Bureau of Land Management; Mark Hayden, Missoula Electric Cooperative; Scott Miller, The Wilderness Society, and Andrew Rable, Arizona Public Service. Miller said he supports a Senate bill but not the House legislation.

The group told a Senate Energy and Natural Resources Committee hearing Tuesday that it prefers Section 2310 of the Energy and Natural Resources Act of 2017 (S. 1460), a comprehensive energy bill cosponsored by committee Chair Lisa Murkowski (R-Alaska) and ranking member Maria Cantwell (D-Wash.).

Blackout Prompted Standards

It was the August 2003 Northeast blackout — triggered by contact between a power line and a tree — that led Congress to enact mandatory reliability standards as part of the 2005 Energy Policy Act. FERC, which deputized NERC to develop the standards, approved the corporation’s vegetation standards in 2013.

Both bills pending before Congress would provide authority to exempt existing ROWs from reviews under NEPA. They also would allow utilities to trim vegetation within ROWs or “hazard” trees adjacent to ROWs that have contacted or are in imminent danger of contacting transmission lines as long as they notify the appropriate agency within 24 hours, according to summary attached to BLM’s testimony.

FERC vegetation management federal land
Rable

Testifying for the Edison Electric Institute, Andrew Rable, manager of forestry and special programs for Arizona Public Service, laid out utilities’ difficulties in employing integrated vegetation management (IVM), which combines the planting of low-growth vegetation in ROWs with pruning and use of herbicides to ensure sufficient distance between plants and electric facilities.

“Transmission line ROWs crossing federal lands face multiple layers of jurisdiction and decision-making, which can hamper electric companies’ ability to manage vegetation and reduce wildfire risk in a timely manner,” he said.

Rable said that although the two bills are largely similar, the House’s is preferable because it sets shorter deadline for approval of vegetation management plans (90 days versus 180 days) and provides “more flexible and less burdensome” rules.

The two bills both provide limited liability protections. According to the BLM summary, the House version protects a utility from wildfire liability to the U.S. when federal agencies blocks it from addressing hazard trees or vegetation in imminent danger of contact with power facilities. The Senate’s would protect utilities from strict liability following a land agency’s “unreasonable delay or failure to approve or adhere to a vegetation management plan or an MOU,” BLM said.

FERC vegetation management federal land
Hayden

Mark Hayden, general manager of the Missoula Electric Cooperative, which has about 15,000 customers in western Montana and eastern Idaho and 300 miles of distribution lines crossing federal land, told the committee the 2017 wildfire season has devastated his region’s economy.

“I fully recognize that the fires burning in Montana today were all lightning sparked. But for me, these fires serve as a vivid reminder and warning of what could occur as a result of long delays in permit approvals and inconsistent application of policies by federal land managers,” said Hayden, who said the ability of utilities to develop relationships with federal officials is hampered by frequent turnover at Forest Service district offices.

Examples Cited

Hayden cited a New Mexico cooperative that received a $38.2 million bill from the Forest Service — almost twice the co-op’s $20 million in liability insurance — for the costs of fighting a 152,000-acre fire caused when a tree fell onto a power line.

The Benton Rural Electric Association in Prosser, Wash., applied to renew its ROW permit in August 2015, four months before it was due to expire. “After waiting 15 months, Forest Service officials have now proposed nothing short of a full blown environmental assessment for which costs could exceed $100,000 for facilities that have been in place for more than 70 years,” Hayden said.

In 2009, when the Missoula co-op felled trees killed and weakened by an insect infestation, the Forest Service required it to remove the timber “using an expensive, labor-intensive method to minimize impact to ‘flora and fauna’ from mechanical equipment,” Hayden said. “Ironically, the Forest Service conducted a timber sale on the same tract later in the year using the exact mechanical forestry techniques that we were prohibited from employing. In essence, we were held to a higher standard than they held themselves.”

When the co-op requested permission to bury about 6 miles of overhead lines on Forest Service land, approval took 18 months — granted just days before Hayden was to testify before Congress regarding the delay.

BLM Committed to Streamlining Process

FERC vegetation management federal land
Ruhs

John Ruhs, acting deputy director of operations for BLM, said his agency supports both bills and “is committed to improving and streamlining its permitting processes.”

The agency, which administers almost 16,000 authorizations for electricity transmission and distribution facilities, allows utilities to conduct “minor trimming, pruning and weed management” after notifying the agency, Ruhs explained. Trees that present an imminent hazard can be removed without BLM pre-approval. “For actions that fall outside the scope of the ROW grant and do not present an imminent threat, BLM approval is needed, and additional analysis may be required.”

Ruhs said the legislation “would expand the BLM’s toolbox to help reduce the threat of catastrophic wildfires like those we are currently experiencing.”

FERC vegetation management federal land
Casamassa

Glenn Casamassa, associate deputy chief of the Department of Agriculture’s National Forest System, said his agency supports most of the language of both bills. But Casamassa said some provisions duplicate existing requirements in Forest Service policies.

“USDA is aware of the frustrations some utilities experience as a result of delayed responses for maintenance approvals and inconsistency across agency field offices and has been actively taking steps to address these concerns under existing authorities,” he said. The Forest Service has 2,700 authorizations for 18,000 linear miles of power lines.

Climate Change Impact

FERC vegetation management federal land
Miller

Scott Miller, senior director for The Wilderness Society’s Southwest region, said utility vegetation management (UVM) practices have improved substantially since 2005. “At the same time, the importance of strong UVM practices continues to grow as climate change is causing longer wildfire seasons, larger and more severe wildfires, longer growing seasons, changing plant species distributions, increased insect and disease activity, and more intense, more frequent and longer-lasting drought, wetness and weather events,” he said.

Miller said the society, which claims more than 1 million members, opposes H.R. 1873 because it “fails to appropriately recognize the federal land management agencies’ obligations or the public’s interest in federal land management and because it fails to provide for the necessary cooperation that will improve effective and sustainable UVM on federal lands.”

The Senate bill, in contrast, provides “a thoughtful framework for legislation to advance UVM on public lands” and “corrects the many flaws” of the House bill.

“H.R. 1873 would prevent utilities and land managers from including activities in vegetation management plans that would require anything beyond annual notice, description and certification by the utility for its planned activities. It also would give utilities (including those without approved plans) blanket approval to conduct vegetation management activities to meet clearance requirements, leaving the agencies with no authority but to allow such activities, and leaving the utilities with little incentive to cooperate or even prepare a vegetation management plan.”

Granting a blanket exemption for vegetation management from NEPA “would undermine sound stewardship of our public lands,” he continued. “We note that both the Forest Service and BLM have already established a number of categorical exclusions that apply to many routine UVM activities, and those authorities are routinely utilized by the agencies in the context of UVM.”

The Senate bill, in contrast, would encourage cooperation between utilities and federal land managers, he said.

The group said the House bill’s provisions on liability are “overbroad and unclear.”

“Nothing in the bill states that the release of liability is limited to situations where the secretaries’ decisions are an actual and proximate cause of the damages, potentially leaving the agencies (and ultimately, taxpayers) to cover the damages caused by the utilities’ negligence (or even gross negligence).”

MISO to Address FERC Query on Constrained Areas

CARMEL, Ind. — MISO will file a response to FERC’s recent deficiency letter on the RTO’s new constrained area category after an internal review, stakeholders learned on Thursday.

FERC issued the letter Sept. 6 (ER17-2097), inquiring about:

  • What past outage information or expected future congestion estimates MISO plans to use to impose a dynamic narrowly constrained area designation;
  • What conduct and impact thresholds MISO plans to use for mitigation;
  • Whether dynamic narrowly constrained areas could also be simultaneously designated as simple narrowly constrained areas;
  • Whether MISO’s existing binding reserve zone constraints would be used to apply mitigation measures

MISO Director of Market Evaluation and Design Dhiman Chatterjee said the RTO is working with its Independent Market Monitor to respond to the deficiency letter.

MISO FERC narrowly constrained area
Indiana transmission line | © RTO Insider

“We believe those are more clarifications [than changes] that they’re asking for. It’s a matter of providing more information, is our initial take on it,” Chatterjee said during a Sept. 14 Market Subcommittee meeting.

Under MISO’s proposal, filed July 14, dynamic narrowly constrained areas would address intense, short-lived congestion by allowing the Monitor to apply mitigation if the constraint has bound in 15% or more hours over at least five consecutive days. The definition would differ from FERC-defined narrowly constrained areas, which must bind for more than 500 hours annually. (See MISO Embraces Monitor’s New Constrained Area Category.)

The new category also would require the Monitor to have identified economic or physical withholding, or uneconomic production in the area. MISO proposed a $25/MWh “conduct threshold” for such determinations, meaning the behavior must have impacted LMPs or market clearing prices by at least that amount.

— Amanda Durish Cook

PJM Market Implementation Committee Briefs: Sept. 13, 2017

VALLEY FORGE, Pa. — Stakeholders at last week’s Market Implementation Committee meeting endorsed the first phase of what amounts to a two-phase implementation of Manual 11 revisions to facilitate intra-day generation offers.

PJM was requesting endorsement of manual revisions needed to implement intra-day offers on Nov. 1 as planned. The proposal received 72% approval but not before a lengthy discussion about how frequently generators can elect to opt in or out of making changes to offers in real-time auctions.

PJM and its Independent Market Monitor have differed on the issue, but the two sides came to an agreement that market participants must specify in their annually approved fuel-cost policies (FCPs) the conditions under which they will opt in. This came as a surprise to several generation representatives, including Gary Greiner of Public Service Electric and Gas. He believed the language previously had read that generators would be able to make that election monthly.

PJM intra-day generation
Morelli | © RTO Insider

PJM’s Lisa Morelli had called the change “minor,” but Greiner took issue with that characterization.

“What I’m hearing now is we have to build it into the fuel-cost policy so we no longer have that monthly option; that’s gone. It’s a once-a-year, permanent thing, unless we want to create a new fuel-cost policy that says we’d want to opt in and [include] everything around all of the mechanics of what we’re going to do intra-day. [Then] we have to stay with an opt-out decision for one year. Is that a minor change?” he asked. “That’s a massive change.”

“So, I should not have used the word ‘minor,’” Morelli acknowledged but pointed out that the language had been the same at the August Markets and Reliability Committee meeting. (See “Division Remains on Oversight of Intraday Offers,” PJM Markets and Reliability Committee Briefs: Aug. 24, 2017.)

PJM’s Jeff Schmitt said such flexibility could be worked into a generator’s FCP.

“As long as we have an approved fuel cost policy … we’d work with you to get there,” he said. “It’s certainly workable from my perspective.”

“I’m uncomfortable with having a predefined trigger that determines when I’m opting in or opting out,” Greiner said.

NRG’s Neal Fitch asked several questions to clarify whether he was correct in assuming that the new rules provided leeway for opting in and out more frequently than just annually.

“To the extent that there is a change in desire down the road, you’re not limited to once per year,” Fitch said.

PJM and the IMM remain at odds about whether market participants must specify in their FCPs the frequency with which they can update price-based offers.

“PJM isn’t necessarily opposed to having that level of detail, but we don’t think that it’s required,” Morelli said.

She also laid out the second phase of revisions, which will be presented for endorsement next month. They would change how offers are capped and how often the three-pivotal supplier (TPS) test is run.

PJM and the IMM mutually proposed re-evaluating which schedule, either the cost- or price-based, is cheapest and reapplying the offer cap when offers are updated. The current rules do not allow for such re-evaluation, which wouldn’t allow market power mitigation to keep up with intraday updates. Since units can self-schedule with 20 minutes of notice, PJM and the IMM proposed running the TPS test on such units every hour following the first hour of operation.

Stakeholders also endorsed related revisions to Manual 28 by acclamation with no objections or abstentions.

MTSL Revisions Kaput

Stakeholders rejected a joint PJM-IMM proposal to revise how black start units are compensated for fuel storage, with some generators complaining that the issue is not significant relative to other issues the membership is addressing.

The measure, which would have paid units based on the portion of fuel they need for black start rather than how much is stored, received 48% approval. The proposal, which was based on the minimum tank-suction level (MTSL) for the fuel-storage tanks, would have saved customers about $210,000 annually. (See “PJM Indifferent on Black Start Fuel Compensation,” PJM MIC Briefs: July 12, 2017.)

NRG’s Fitch said the way the proposal was presented seemed “inappropriate” and “flawed.”

PJM intra-day generation offers
Horstmann | © RTO Insider

“I hope we do a better job in the future deciding when and where we need to work on the small stuff,” he said.

John Horstmann of Dayton Power and Light called the proposal “shortsighted” because the value of having fuel when needed during a system emergency far exceeds the “minuscule” savings from proportional compensation.

“You can’t even measure these savings on a customer’s bill,” he said.

Others, however, said the principle was the point.

“The status quo is not defensible. There are units being paid more than it takes to provide black start service,” the IMM’s Catherine Tyler said.

PJM intra-day generation offers
Tyler | © RTO Insider

“I realize that these are not major dollars, but dollars are dollars, and customers have to pay those dollars,” said John Farber with the Delaware Public Service Commission.

The Monitor noted that the final proposal was a compromise between it and PJM. The RTO estimated the pro rata calculation would have reduced payments by about 95%, so it included a $12,000 “dual-fuel unit adder” that only cut payments in half.

“We do feel that the dual-fuel adder is somewhat arbitrary,” Tyler said, adding that it would need to be justified or eliminated in the future.

FTR Forfeiture Rebilling to Start

PJM’s Brian Chmielewski announced that, barring any further action from FERC, implementation of PJM’s revised financial transmission right (FTR) forfeiture rule will begin with September billing statements and rebill back to the Jan. 19 effective date of the related FERC order. Manual revisions to address the changes ordered by FERC received 82% approval in an endorsement vote.

FERC’s order on the issue (EL14-37) required PJM to evaluate the net effect of a market participant’s entire virtual portfolio of up-to-congestion trades (UTCs), incremental bids (INCs) and decremental offers (DECs) on congestion constraints. A forfeiture is triggered if at least 75% of the energy flowing between the bus where a virtual transaction is made and the worst-case bus — the location at which the transaction has the biggest impact on congestion — is reflected in the constraint. (See FERC Orders Portfolio Approach for PJM FTR Forfeiture Rule.)

Following PJM’s request in 2013 to define UTCs as virtual transactions, FERC initiated an investigation to examine how PJM planned to apply its FTR forfeiture rule to UTCs. PJM had implemented the rule in 2000 to prevent market participants from using virtual transactions to create congestion that benefits their FTR positions but hadn’t included UTCs.

“We just rewrote the entire section because it’s essentially an entirely different, new rule,” Chmielewski said of the manual revisions. “We are on the same page with the IMM. Our numbers are very close to matching.”

He acknowledged that the calculations under the revised forfeiture logic were higher, but “I wouldn’t say they are significantly more in all cases.”

“I think relative to total target credits, the percentage is still very low, but relative to the previous rule, they’re higher,” Chmielewski said.

Several stakeholders noted the existence of protests in the FERC docket, but Chmielewski said that wouldn’t impact the effective date.

Now is the Winter of Our Discontent (with DR Rules)

East Kentucky Power Cooperative’s (EKPC’s) Chuck Dugan proposed a problem statement and issue charge to investigate the impact of winter demand response (DR) not performing on an assessment day due to a maintenance outage. Such nonperformance on a winter peak day reduces a market participant’s winter peak load (WPL), which reduces the participant’s winter DR capacity nomination. An unexpectedly low nomination can result in needing to secure replacement capacity to fulfill a commitment and avoid a daily deficiency penalty, which happened to an EKPC customer, Dugan said.

“We’re paying the resources to be available all year,” said Tyler, adding that the Monitor opposes the proposal.

“They’re already doing what you paid them to do, which is be off,” Dugan countered.

Stakeholders will vote on the proposal at next month’s meeting.

EE Waiver for Kentucky?

Chris O’Hara, PJM’s deputy general counsel, said the RTO plans to submit a Section 205 filing with FERC asking for a prospective waiver of its Tariff to bar Kentucky participants from its energy efficiency resources (EERs) market. The waiver would be limited to Kentucky and only after FERC makes a ruling on the issue.

The request evolved from a Kentucky Public Service Commission staff finding in February that EERs are a retail product under its regulatory oversight that, like other Kentucky retail customers, aren’t eligible to participate in wholesale markets such as PJM. PSC commissioners issued a declaratory order to that effect on June 6. Four days earlier, Advanced Energy Economy requested that FERC declare whether it has sole jurisdiction over EERs.

“To the extent that’s a change to what we’ve said, it is a change,” O’Hara said in response to questions about whether PJM had revised its position on the issue. PJM received stakeholder endorsement to examine how it allows EER aggregations to participate in its wholesale markets. The initiative also was to investigate the potential for creating an “opt-out” mechanism for regulators like what PJM developed for demand response in response to Order 719. (See States, Enviros Differ on Jurisdiction over Energy Efficiency.)

EKPC’s Dugan supported the waiver request, sympathizing with PJM’s position “between a rock and [a] hard place” jurisdictionally. Tom Rutigliano, a consultant who represents EER clients, sought — and received — assurances that the waiver would not extend past Kentucky.

Tyler voiced concerns that PJM is requesting permission to discriminate among market participants “especially in a way that limits competition.”

Rory D. Sweeney

NOVEC Offers 10th Capacity Proposal

By Rory D. Sweeney

VALLEY FORGE, Pa. — The Northern Virginia Electric Cooperative (NOVEC) last week added to the pile of proposals to reform PJM’s capacity construct, but the details were familiar for anyone who’s been following the Capacity Construct/Public Policy Senior Task Force (CCPPSTF).

PJM NOVEC capacity construct
Johnson | © RTO Insider

Customized Energy Solutions’ Carl Johnson, representing NOVEC as a member of the PJM Public Power Coalition, acknowledged that the Manassas-based cooperative usually doesn’t take an active role in PJM’s stakeholder process. But Johnson said it felt the need to get involved based on concerns that the existing proposals relied too much on logic and theory and failed to account for sometimes-illogical human behavior.

“Newton, if he’d lived long enough, might have come up with a fourth law: power plants that are in service tend to stay in service,” Johnson said.

NOVEC argued that some of the proposals encourage generators to seek a subsidy designation rather than remove the influence of out-of-market payments from competitive bidding. It’s equally concerned with proposals that would suppress auction prices in a “race to the bottom” and ones that would result in high prices, Johnson said.

“We’re concerned about other proposals making the market considerably more vulnerable,” he said.

NOVEC’s offering proposes revisions that evolved from recommendations previously advanced by James Wilson of Wilson Energy Economics, which consults for consumer advocates in New Jersey, Pennsylvania, Maryland, Delaware and D.C. Wilson argued at the Sept. 11 meeting of the CCPPSTF that “if a state follows a deliberate process and provides the market substantial advance notice of its actions, it should be assumed the market has fully absorbed the resulting resources and there is minimal, if any, impact on the auction prices.”

“We propose a solution … that simply requires that the appropriate information about those resources be published along with the planning parameters for each auction, such that other market participants can set their bids in accord with their expectations of the bidding of those resources,” NOVEC’s proposal explained. “The subsidies would then be added to the resources’ competitive offers, and the resource stack would clear as usual.”

The remaining nine proposals have all added responses to a list of stakeholder questions, including how they would handle subsidized resources and impact other PJM processes.

PJM ZECs NOVEC
Lieberman | © RTO Insider

American Municipal Power’s Steve Lieberman provided additional details on AMP’s proposal that encourage bilateral contracts. It would require that load and capacity resources with bilateral contracts or self-supply notify PJM and the Independent Market Monitor of the arrangement. The contract price would be reported — with the participants’ names masked — by PJM and the IMM after the annual capacity auction.

The proposal is a response to the “mismatch of expectations between the buyers and the sellers,” said AMP’s Ed Tatum. “A better [way] to think about one of our objectives here [is] to make bilaterals more balanced.”

EnerNOC’s Katie Guerry expressed concern that requiring companies like hers to negotiate contracts with every load-serving entity would increase administrative costs greatly and potentially increase prices for customers. Tatum disagreed with Guerry’s assessment but did not elaborate.

PJM ZECs NOVEC
Hoatson | © RTO Insider

LS Power’s Tom Hoatson clarified his company’s perspective on the definition of a subsidy.

“Our view is if [a subsidy is] available to everyone, we probably would not treat it as a subsidy. But we’re open to discussion,” Hoatson said.

Exelon’s Jason Barker asked where the Illinois zero-emission credit program (ZECs) fit because it appears to conform with LS’s definition of being available to all units in the technology class. Hoatson pledged that the company will review the language, saying its intent is to include ZECs.

“Is the purpose just to capture ZECs?” Barker asked, noting that the proposal doesn’t backdate to subsidies prior to 2017.

“No,” Hoatson said, “but they seem to be the new subsidy du jour, so we wanted to capture them.”

PJM ZECs NOVEC
Ford | © RTO Insider

Adrien Ford of Old Dominion Electric Cooperative said its proposal was meant to make PJM’s two-stage repricing model “less worse.” PJM’s proposal would remove subsidized units to maintain a competitive clearing price at the expense of so-called “in-between” offers that would clear in the repriced second stage but didn’t in the first stage. ODEC’s proposal was designed to fully synthesize an auction as if subsidized units never existed and competitive units covered the entire demand.

“We think that is a problem with all two-stage approaches, including ours,” she said.

Exelon’s Sharon Midgley said her company would rather not change a thing, even though it offered a proposal.

“Our firm really believes that reforms are not necessary at this time,” she said. “Really, there is no reliability problem here, so we do strongly prefer the status quo.”

NRG Energy’s Neal Fitch called PJM’s proposal “a good working model to start with, with some necessary adjustments.” NRG’s proposal would lower capacity commitments for bids that cleared in the first stage to address “in-between” units with commitments for all resources proportionally reduced below their offer amounts.

Wilson suggested adding a mechanism that would allow units to drop their commitments, arguing that a few units likely would, allowing the remaining units to be committed closer to their full offer. Fitch said the idea was “probably a next-level step” if the proposal is implemented.

PJM ZECs NOVEC
Price | © RTO Insider

Ruth Ann Price, of the Delaware Division of the Public Advocate, asked proposers to analyze how their proposals would impact state renewable portfolio standards, renewable energy credits, ZECs and the Regional Greenhouse Gas Initiative.

PJM plans to conduct a stakeholder poll on the 10 proposals before the task force’s next meeting on Sept. 26. After that, another round of proposal explanations and revisions is likely to follow. The task force hopes to recommend one of them for stakeholder endorsement by the end of the year.

PJM Operating Committee Briefs: Sept. 12, 2017

VALLEY FORGE, Pa. — The difference between the reserve measurements in PJM’s real-time security-constrained economic dispatch (SCED) engine and its emergency management system (EMS) has been shrinking since PJM implemented calculation changes. (See “Reserve Differences Explained,” PJM OC Briefs: Aug. 8, 2017.)

PJM’s Joe Ciabattoni presented a graph that measured the absolute error as a percentage as part of his executive operations report presented at a Sept. 12 Operating Committee meeting. Prior to July 11, when PJM removed a 2% “back off” in the EMS that assumes resources will achieve only 98% of their stated capability; the error was relatively flat at just over 9%. Since then, the difference has declined by about half a percentage point.

pjm
Graph indicates that the difference between the reserve measurements in PJM’s real-time security-constrained economic dispatch engine and its emergency management system has been shrinking since the RTO implemented calculation changes. | PJM

Stakeholders have expressed concern that SCED was not pricing shortages accurately because publicly available reserve data didn’t match LMP changes. PJM explained previously that the publicly available data is from the EMS, while the actual shortage pricing comes through SCED, which is confidential. The measurement differences, PJM argued, created the appearance that there were more shortages than actually existed.

With the small sample size, Ciabattoni hesitated to suggest the issue has been resolved.

“Even though these numbers have appeared to improve slightly, I think we need more time,” he said.

TOs to Receive Confidential Generation Data for System Restoration

PJM operating committee EMS SCED
Schweizer | © RTO Insider

PJM’s Dave Schweizer presented proposed Operating Agreement changes that would provide transmission owners with confidential data about generators that are part of the TOs’ system-failure restoration plan.

PJM currently provides such information when a unit is providing black start service or is modeled in the TO’s EMS plan. The information includes real-time unit status, real and reactive power, outage data and reactive capability. PJM proposes adding “system-restoration planning data,” such as unit start times, ramp rates, start-up loads and low-load operating capabilities.

The requested changes are in preparation for PJM’s request for proposals (RFP) on black start units coming in January. (See “Black Start RFP Process Offers Opportunity to Re-examine System Setup,” PJM OC Briefs.) GT Power Group’s Dave Pratzon asked if PJM would be able to identify where black start proposals would be “useful rather than just a shot in the dark,” citing costs of developing proposals for multiple potential sites as a deterrent for developing proposals that aren’t likely to be approved.

Schweizer said the RFP is for the entire RTO, so “we wouldn’t be able to reach out … and say, ‘you could put black start there’ because it’s an open process.”

He acknowledged staff continues to look for ways to make the process “less onerous.”

Gas-Pipeline Coordination Largely Confidential

PJM operating committee EMS SCED
Seiler | © RTO Insider

PJM’s Ken Seiler said staff have been working with gas-pipeline operators for at least a year to increase gas-electric coordination, the results of which are expected to be rolled out over the next three years. Details are coming, he said, but specifics — such as which gas-fired units that are dual-fuel are connected to more than one pipeline — aren’t.

“There’s going to be a lot of things that we can share … in terms of megawatts and what pipelines they’re associated with that may be impacted, but we’re not going to get into specifics because we don’t want to identify any potential sensitivities that we have within the system,” he said.

The discussion came as part of PJM’s ongoing focus on system hardening and resilience.

“I think it will be great for people to get a feel for the extent of the types of research and operations improvement you make,” said Pratzon, who had made the initial inquiry.

Staff are currently reviewing a list of about 50 extreme event contingencies and expect to have the gas-related ones complete prior to the winter.

Synchrophasors Backup

PJM operating committee EMS SCED
Nice | © RTO Insider

PJM’s Ryan Nice provided an update on staff efforts to roll out synchrophasor technology, which takes high-speed, time-stamped measurements of phase angles, voltage and frequency. PJM is using the more precise information for advanced energy-management applications. (See “PJM Seeks to Tap Synchrophasors’ Potential,” PJM Operating Committee Briefs.)

Nice said he is particularly excited about system-wide heat maps for measurements such as voltage magnitude, voltage angle and frequency.

“A human being understands nothing more rapidly and more intuitively than a colored map,” he said. “It makes us more responsive to the state of the grid.”

Staff have had to address how the sheer volume of data that PJM needs to handle has overwhelmed software that has performed well for other grid operators. PJM is the “abnormally big kid in the daycare center, and we break all the toys,” he said.

PJM has begun a demonstration project that will run a linear state estimator using only synchrophasor data. The project will run into 2018, at which point PJM will have to decide whether to purchase the system.

PJM operating committee EMS SCED
PJM phasor measurement unit locations | PJM

If successful, the system could be an equivalent replacement for the current EMS state estimator without relying on the same systems and software.

“It’s a miniature EMS system. It can do a lot of the same things, maybe a little bit more [rudimentarily],” he said. “A vulnerability that would work on the EMS system would not work on the synchrophasor network.”

Eclipse Analysis

The August solar eclipse resulted in less reduction in solar output and more load reduction than expected. PJM planned for a loss of up to 2,500 MW in solar generation, but an analysis found it dropped by about 2,220 MW between 2 p.m. and 4 p.m. on Aug. 21.

Also unexpected was a 5,000 MW load decrease during that period. Staff believe that might have in part stemmed from a corresponding temperature drop of about 3 degrees Fahrenheit, but PJM’s hourly data is inconclusive. Staff also are investigating whether customer behavioral changes played a role, noting that the residential control-automation system Nest announced it received positive feedback when it solicited approval from customers to reduce air-conditioning demand during the eclipse. (See “Eclipse Hot Takes,” PJM Markets and Reliability Committee Briefs: Aug. 24, 2017.)

PJM’s Joe Mulhern acknowledged that PJM’s calculations for behind-the-meter solar arrays are estimates. Staff believe they have the information about 90% triangulated from a database that oversees solar renewable energy credits (SRECs), time and location estimates and other publicly available data.

The analysis will provide a historical basis to plan for the 2024 eclipse, which will likely have a greater impact on the RTO “based on the amount of solar in the queue,” Mulhern said.

Rory D. Sweeney