Search
`
November 17, 2024

MISO Board, Monitor Seek Response to PJM M2M Missteps

By Amanda Durish Cook

CARMEL, Ind. — The MISO Board of Directors last week learned about the recent discovery that PJM had been committing two market-to-market errors that have likely cost MISO millions of dollars over a period of years.

They also heard that MISO may have little recourse to recover those losses.

At issue was PJM’s longtime practice of overstating its own transmission loading relief (TLR) because of a calculation error and its failure to order mandated tests required to define M2M constraints between the two RTOs. (See MISO Monitor Blames PJM for Market-to-Market Errors.)

MISO board PJM market-to-market M2M
Patton | © RTO Insider

During a Dec. 5 meeting of the board’s Markets Committee, Independent Market Monitor David Patton said MISO has anted up millions in unnecessary congestion costs stemming from PJM’s mistakes.

The untested M2M constraints led to $84 million worth of congestion in 2016 and $187 million in 2017, Patton said, adding a disclaimer that his firm probably couldn’t perfectly duplicate the constraint test that the RTOs perform, and that they may show different congestion values. Delays in defining constraints resulted in $44 million worth of congestion last year and $25 million this year.

“If they don’t define the constraint, they basically get to a free pass to use the transmission system,” Patton told the board.

Patton said one flowgate that wasn’t tested or defined as M2M led to $43 million in congestion in September alone.

“A unit was running, overloading the constraint, and we did not tell PJM to back it down,” Patton said. “We need to be vigilant. … We don’t always ask our neighbors to test the constraints.”

Willful Neglect?

Patton said PJM’s failure to order these tests was deliberate: “In our mind, this is a pretty gross violation of the Tariff, particularly since they knew they weren’t doing the test.”

Director Baljit Dail asked how Patton could be sure PJM knowingly neglected the test.

MISO board PJM market-to-market M2M
Rainwater | © RTO Insider

Patton said at the beginning of the RTOs’ M2M process nearly a decade ago, PJM was aware it needed to devise a new constraint model that included an actual representation of MISO system outages with shift factors, but it failed to create such a model. “They never did it, and they knew they didn’t do it.” Patton said.

“I’ll hold the rest of my questions for closed session,” Dail replied, referring to a closed session on the matter following the board’s open meeting.

“What is it that we can do as a board?” Director Thomas Rainwater asked.

Patton said there weren’t many options available to the board. It could urge enforcement by FERC, “which to be honest, hasn’t been very active in enforcement on violations of RTOs.”

MISO board PJM market-to-market M2M
Doying (left) and MISO Executive Director of Strategy Shawn McFarlane | © RTO Insider

“I don’t think there’s a lot you can do other than telling PJM how serious you think this is,” Patton said. He also said MISO stakeholders could pursue resettlement of prices related to the TLR miscalculations, although no precedent exists for such resettlements. PJM has been overstating its TLR response since 2009, “inappropriately” raising the relief obligation of MISO and other balancing authorities, Patton said.

Patton said it’s up to stakeholders to decide whether to pursue TLR resettlement at FERC.

“We’ve certainly resettled for less,” Patton said.

“These are serious issues with big dollar amounts,” Director Barbara Krumsiek said.

MISO Executive Vice President of Operations Richard Doying said strategies for resettlement would “certainly be a closed discussion item.”

PJM Responds

PJM Chief Communications Officer Susan Buehler told RTO Insider that PJM acknowledges it had “an internal process issue regarding the flowgate tests as well as a calculation error with respect to relief obligations,” but it disagreed that the issues amounted to a Tariff violation. She also said the MISO Monitor is possibly overstating the monetary impacts.

“PJM has corrected both issues and is evaluating the potential impacts, but at this time we do not believe the impacts are what the MISO IMM has indicated,” Buehler said.

She also said the congestion impacts and monetary values the Monitor has disclosed are projections and not solely a consequence of PJM’s “internal process issues” and “potential M2M inefficiencies” with constraints. PJM cannot confirm Patton’s numbers, she said.

JOA with TVA

Patton also urged the board to consider entering a joint operating agreement with the Tennessee Valley Authority over the TLR issue. MISO discovered PJM’s incorrect TLR values while investigating a northeastern Tennessee constraint, and Patton said TVA often calls TLRs on its 500-kV Volunteer-Phipps Bend line, which leads to price increases in the Midwest and corresponding reductions in the South. The TLR constraint contributed to higher prices during a late September emergency event, Patton said.

He said MISO has incurred 100 dispatch violations of its own constraints in responding to the competing dispatch effects of the Volunteer-Phipps Bend constraint.

“We’ll violate our own constraints in order to provide TLR to TVA,” Patton said. He also said TVA’s generation is almost always more effective and economic for managing a TVA constraint than MISO’s.

Patton originally complained about the excessive amount of relief MISO is asked to provide the Volunteer-Phipps Bend more than two years ago. (See External Constraint Vexing MISO, Market Monitor Says.) Now he thinks the RTO could lower its transmission constraint demand curve for TLR requests to avoid incurring costs to provide “very small amounts of relief.” He said MISO should instead pay TVA for economic relief on constraints pursuant to a JOA.

Doying said MISO is not in 100% agreement with the Monitor’s suggestions. “We value the reliability of our neighbor’s systems as much as we value the reliability of our own,” Doying said.

However, Doying said MISO is currently drafting a narrow JOA with TVA that would govern certain flowgates. He said MISO has had similar agreement with TVA in the past.

Patton also noted that TVA at times orders TLRs on Volunteer-Phipps Bend as a proxy to obtain relief on a nearby 161-kV constraint, and he questioned the efficiency of TVA’s process.

Director Paul Bonavia asked MISO executives if it was appropriate under NERC rules to use the 500-kV line as a proxy for a 161-kV line. Doying said the practice doesn’t violate NERC policies.

MISO General Counsel Andre Porter then reminded the board that further discussion was best left for a closed session.

“We’re not going to solve all of this today, but we’ll grapple with it, get it on the table,” Bonavia said. “How do we approach the resettlement issue. … How do we help our neighbors without being overzealous?”

“I do think we have a lot of issues to untangle with PJM and TVA,” Doying said.

MISO Board Promotes Moeller, OKs 2018 Budget

By Amanda Durish Cook

CARMEL, Ind. —The MISO Board of Directors last week stepped in to order a plan of succession for the RTO’s executive leadership, while also approving its requested 2018 budget.

As part of the plan, the board immediately promoted Executive Vice President of Operations Clair Moeller to president, a permanent appointment. In the event of unforeseen circumstances related to CEO John Bear, Moeller would act as CEO, the board decided.

MISO Board of Directors REV budget PJM Insider
MISO CEO John Bear (left) and Board Chairman Michael Curran | © RTO Insider

The RTO’s board usually takes a “nose in, fingers out” approach except when it comes to matters of personnel succession and strategic planning, Chair Michael Curran explained during a Dec. 7 meeting. He said the appointment will ensure that MISO is spared uncertainty in the event that Bear leaves his post.

For example, Curran joked, “if John gets hit by a truck, wins the lottery [or] beamed up by a spaceship.”

The board also approved a $321.7 million total operating budget and $29.6 million in capital spending for 2018.

As part of the budget, MISO will spend $21.7 million to begin replacing its aging market platform with a more adaptable modular market platform, a project it expects to complete by 2024. (See Winter Launch for MISO Website, Market System Project.) The RTO’s existing market platform relies on technology from the late 1990s, while its day-ahead and real-time market systems were added around 2005. The age of the system is limiting the new market products MISO can pursue.

“It’s approaching its teen years — God help us all,” Dynegy’s Mark Volpe joked during a Dec. 6 Advisory Committee meeting.

Alliant Energy’s Mitch Myhre, chair of the MISO Finance Subcommittee, said his group will track spending on the project.

“This is a big deal. $130 million is half of MISO’s annual budget,” Volpe said.

To date, MISO is under its 2017 base operating budget by about $1.8 million and predicts it will end the year having spent $240.8 million instead of the budgeted $241.7 million.

Chief Financial Officer Melissa Brown said the savings will result from not implementing a previously planned forward capacity market for the RTO’s deregulated areas, as well as lower-then-expected spending on building maintenance and employee travel.

MISO Board of Directors REV budget PJM Insider
Bonavia (center) leads his last Markets Committee meeting | © RTO Insider

MISO is $500,000 overbudget on this year’s capital spending but is poised to shrink the overage to $200,000 by year-end. The increase was mainly driven by the RTO’s effort to replace its market settlements software.

Last week also marked Director Paul Bonavia’s final meeting on the board, with his term expiring Dec. 31. In parting remarks, Bonavia called MISO a “civics lesson” and said the RTO was proof that decorum and cooperation could exist in an industry with several competing interests. “It’s positively breathtaking, with how you come together representing different interests but still have goodwill and move billions of dollars in investment,” he said.

Former Delta Air Lines Chief Information Officer Theresa Wise will replace Bonavia beginning Jan. 1. (See New Director to Join MISO Board, 2 Keep Seats.)

Photos Show Murray’s Role in Perry Coal NOPR

Newly revealed photographs show Energy Secretary Rick Perry and Murray Energy CEO Robert Murray meeting in late March to discuss the coal mining company’s “action plan” — the apparent basis for Perry’s controversial call for price supports for coal generating plants.

The photos, obtained by magazine In These Times and The Washington Post, appear to contradict Murray’s statement to Greenwire in November that “I had nothing to do with” the DOE Notice of Proposed Rulemaking.

One photo shows the action plan’s cover letter, printed on Murray Energy letterhead. Another shows Perry embracing Murray.

Rick Perry NOPR Murray Energy
Cover letter of Murray Energy’s “action plan” | Photograph obtained by In These Times

In These Times reporter Kate Aronoff said a confidential source provided the magazine with the photos, as well as additional, unpublished photos showing pages in the document, which propose, among other things, cutting EPA’s staff by half and replacing members of FERC, the Tennessee Valley Authority’s Board of Directors and the National Labor Relations Board.

Rick Perry NOPR Murray Energy
Murray and Perry embrace. | Photograph obtained by In These Times

Aronoff said her magazine had only obtained photographs of the meeting and of the document, not the document itself.

The action plan contains language regarding the need for “immediate action” to support struggling coal plants like that in the DOE NOPR issued to FERC on Sept. 28 (RM18-1).

One section of the plan calls for “immediate action … to require organized power markets to value fuel security, fuel diversity and ancillary services that only baseload generating assets, especially coal plants, can provide,” according to In These Times.

The DOE NOPR says “immediate action is necessary to ensure fair compensation in order to stop the imminent loss of generators with on-site fuel supplies, and thereby preserve the benefits of generation diversity.”

Murray had referenced the document in an Oct. 11 episode of PBS’s “Frontline,” “War on the EPA.”

“I gave Mr. Trump what I called an ‘action plan’ very early,” said Murray, whose company’s political action committee donated $100,000 to President Trump’s campaign last year, according to the Federal Election Commission. “It’s about three-and-a-half pages … of what he needed to do in his administration. He’s wiped out page 1,” which apparently included repealing the Clean Power Plan.

Several other officials are portrayed in the photos: Perry’s chief of staff, former Edison Electric Institute Vice President for External Affairs Brian McCormack, is pictured shaking hands with Murray. Also seen is Andrew Wheeler, at the time a registered lobbyist for Murray Energy, now Trump’s nominee for EPA deputy administrator.

Rick Perry NOPR Murray Energy
Murray Energy CEO Robert Murray (right) shakes hands with DOE Chief of Staff Brian McCormack (left) as Energy Secretary Rick Perry (center) looks on. | Photograph obtained by In These Times

At his confirmation hearing in early November, Wheeler testified to the Senate Environment and Public Works Committee that he had only briefly seen the document. Sen. Sheldon Whitehouse (D-R.I.) has called for its release. Wheeler has cleared the committee, and his nomination is pending a vote by the full Senate.

DOE did not dispute the authenticity of the photos. “Industry stakeholders visit the Department of Energy on a daily basis,” a department spokeswoman told Politico.

The March 29 meeting at DOE headquarters occurred just weeks after Perry was sworn in as secretary, and weeks before he would order a study on the effect of federal policies on the reliability of the grid.

Later in July, according to a letter from Murray to Trump obtained by the Associated Press, Murray met with the president and Perry in Youngstown, Ohio, where he asked that the secretary declare an emergency on the grid under Section 202(c) of the Federal Power Act in order to protect coal-fired plants owned by FirstEnergy, Murray’s biggest customer.

FERC NOPR Rick Perry James A. FitzPatrick nuclear plant
Andrew Wheeler, President Trump’s nominee for EPA deputy administrator, is seen on the far right, as Murray speaks with Perry. | Photograph obtained by In These Times

Trump was receptive to the proposal and, according to Murray, told Perry three times that “I want this done.” On Aug. 3, Murray again met with the president, along with FirstEnergy CEO Charles Jones, in Huntington, W.Va., where Trump told personal aide John D. McEntee III to tell Gary Cohn, director of the White House’s National Economic Council, “to do whatever these two want him to do.”

Perry, however, rejected the emergency order, the AP reported on Aug. 22. The next day, the department released its grid study. And a month later, Perry issued his NOPR, ordering FERC to consider fully compensating plants with a 90-day supply of on-site fuel their operating costs. (See Perry Orders FERC Rescue of Nukes, Coal.)

On Friday, Perry reluctantly agreed to FERC Chairman Kevin McIntyre’s request to delay action on the NOPR for 30 days. (See McIntyre Takes FERC Chair; Wins Delay on NOPR.)

— Michael Brooks

New Wave of PJM Transmission Upgrades Rankles AMP

By Rory D. Sweeney

The PJM Board of Managers last week authorized $348 million in transmission projects. Coming two months after it greenlit $1 billion in projects, the approvals irked American Municipal Power, the RTO’s biggest critic when it comes to its Regional Transmission Expansion Plan.

PJM Transmission Upgrades PJM Board of Managers AMP
Tatum | © RTO Insider

“There was another $186 million of supplemental projects that will move forward in the PJM process. In other words, over a third of the transmission projects reviewed in this time frame were not approved by the PJM board,” American Municipal Power’s Ed Tatum said in an email. “These projects were not subjected to the same level of rigorous review afforded baseline projects, yet the cost of these facilities will ultimately be borne by the consumers in the constructing transmission owners’ zone.”

Tatum was referring to the separation within PJM’s RTEP between different types of projects: baseline projects requested to address reliability issues that receive significant RTO scrutiny; and “supplemental” projects proposed by TOs to address their own internal criteria that aren’t subject to the same level of analysis.

PJM must make recommendations and receive board authorization before assigning baseline projects, but TOs do not need RTO approval for supplementals.

“Another half-billion dollars of more supplemental projects are waiting in the wings. The sheer volume of projects moving forward absent adequate review for need and alternatives should be a grave concern to the PJM board,” Tatum said.

Last week’s decision by the board authorized 26 projects, most of which were reliability upgrades or replacements. There were three market efficiency proposals PJM staff recommended for authorization, though they accounted for less than $10 million. Twelve of them are in the Mid-Atlantic region of PJM’s footprint; 10 are in the Western area and four are in the Southern area.

The board also approved PJM’s installed reserve margin (IRM) of 15.8% for 2021/22. The IRM dropped from 16.6% thanks to an anticipated fleet-wide equivalent forced outage rate (EFORd) reduction from 6.59% to 5.89%. (See “IRM Results Approved,” PJM Planning/TEAC Briefs Oct. 12, 2017.) An IRM study earlier this year also created updated margins for other delivery years, which the board also approved: 16.1% for 2018/19 and 15.9% for 2019/20 and 2020/21.

The board also approved five targeted market efficiency projects (TMEPs) in conjunction with MISO that traverse the grid operators’ borders. The smaller, congestion-relieving interregional projects were also approved last week by MISO’s board. (See related story, MISO Board Approves $2.6B Transmission Spending Package.)

The portfolio of system upgrades has a combined cost of $20 million. On average, project costs will be allocated 69% to PJM and 31% to MISO, based on projected benefits, which are expected to reach $100 million.

FERC OKs Changes to MISO Competitive Tx Process

By Michael Brooks

FERC last week approved several changes to MISO’s competitive transmission developer selection process under Order 1000, which the RTO says will greatly improve its efficiency.

The most substantial of these changes eliminates MISO’s facility-by-facility evaluation when considering a developer’s bid, allowing the RTO to evaluate the project as a whole (ER18-44). Previously, the RTO had to individually assess a project’s facilities, such as lines and substations, even if they were all part of the same project. MISO called this approach both “inefficient” and “analytically flawed.”

miso ferc order 1000 selection process
| © RTO Insider

MISO will now evaluate mixed-facility projects (those consisting of both competitive lines and substations) using the following weights:

  • 35% for cost and facility design quality;
  • 30% for project implementation capabilities;
  • 30% for operations, maintenance, repair and replacement capabilities; and
  • 5% for MISO transmission planning process participation.

Previously, the RTO used separate weighting for lines and substations.

Developers Midcontinent MCN and LS Power protested the new weighting. Both said the cost and description criterion, though increased by 5% for both types of facilities, should have significantly greater weight.

FERC rejected this, saying it agreed with MISO “that providing greater weight (35%) for cost and reasonably descriptive facility design quality appropriately accounts for the evaluation criterion that MISO anticipates will result in the greatest challenges for these types of projects, which include different types of facilities.”

“Indeed, MISO’s proposal to provide greater weight for the cost and reasonably descriptive facility design quality evaluation criterion for mixed-facility projects is consistent with LS Power’s and Midcontinent MCN’s general view that this evaluation criteria should play a greater role in the competitive developer selection process,” the commission said.

Additionally, FERC accepted other noncontroversial changes to the selection process. One of these allows MISO to stagger its requests for proposals for competitive projects. The RTO had explained that, as its Board of Directors approves projects for bidding in packages, drafting RFPs for the projects at the same time created significant staffing crunches (ER18-41).

The commission also approved several revisions to MISO’s governing documents to update terms and definitions related to the competitive process, as well as to improve their clarity, grammar and formatting (ER18-39).

Opponents Assemble as PSEG Seeks NJ Nuke Subsidy

By Rory D. Sweeney

Public Service Enterprise Group CEO Ralph Izzo last week asked New Jersey legislators to approve subsidies for the company’s three in-state nuclear facilities, warning they may otherwise be shuttered.

PSEG FERC state subsidies CEO Bill Magness
Izzo | © RTO Insider

Testifying at a joint session of the General Assembly’s Telecommunications and Utilities Committee and the Senate Environment and Energy Committee on Dec. 4, Izzo said PSEG’s three nuclear units at the Salem and Hope Creek facilities remain profitable but are threatened by low natural gas prices and could become uneconomic within two years. He said the plants’ finances have been propped up by hedging over the past three years, but most of those contracts are set to expire by the end of next year.

“Unless market prices change, we will no longer be covering our costs within the next two years. Without intervention — without a thoughtful economic safety net — PSEG will be forced to close its New Jersey nuclear plants,” he said. “It would be an extraordinarily painful decision because of how much we value the importance to New Jersey, but it is a cut-and-dry decision.”

A Brattle Group study produced for PSEG and Exelon found that allowing the facilities to close would increase New Jersey power bills by $400 million annually over the next decade while reducing state tax receipts by $37 million, eliminating 1,400 jobs and increasing carbon dioxide emissions by 13.8 million metric tons annually.

Izzo requested state subsidies like the zero-emission credits approved in Illinois and New York for units owned by Exelon, which also owns 43% of the two Salem units.

Opposition Coalescing

Opponents questioned Izzo’s prediction that the plants will become unprofitable.

“It is not enough to simply accept PSEG’s assertions regarding the plants’ profitability, and that even if the plants are shown to be at risk of losing money in the future, the solutions must be found within the federally administered markets and not through out-of-market payments for plants that are already profitable,” said Stefanie Brand, the director of New Jersey’s Division of Rate Counsel. “Just because nuclear plants in other parts of the country are not profitable, doesn’t mean that plants in New Jersey — the state with the highest prices in PJM — are also unprofitable.”

PSEG’s units benefit from constraints in New Jersey’s EMAAC locational deliverability area (LDA) that traditionally put its clearing prices near the top in PJM. Capacity prices for delivery year 2020/21 during May’s Base Residual Auction fell to $76.53/MW-day in most of the RTO, while EMAAC jumped to $187.87 from less than $120 for 2019/20. (See Analysts See End to New Builds in PJM Capacity Results.)

Brand urged legislators to wait for FERC to act on the U.S. Department of Energy’s proposed price supports for nuclear and coal plants. (See related story, PJM Markets and Reliability/Members Committees Briefs: Dec. 7, 2017.)

PJM sent identical letters to Sen. Bob Smith, chair of the Senate committee, and Wayne DeAngelo, chairman of the Assembly committee, urging lawmakers to consider a regional approach rather than having the state act on its own. “As a state within PJM, New Jersey need not address these challenges alone or in a vacuum. Being located within PJM — a regional organization with a multistate market — allows for solutions and alternatives that can augment, enhance and amplify the means by which you meet your state policy priorities.”

“There is no evidence that PSEG’s nuclear plants are uneconomic and facing a retirement signal from the PJM markets,” said Joe Bowring, PJM’s Independent Market Monitor. “Neither plant is defined as at risk according to the criteria that the IMM applies to all units in the IMM’s annual PJM State of the Market Report.”

He argued that subsidizing the units would also deter investment in newer technology.

“Subsidies suppress energy and capacity market prices and therefore suppress … investment incentives for innovation in the next generation of energy supply technologies and energy efficiency technologies. These impacts are large and long lasting,” he said. “If subsidies are provided to one generating plant, this will suppress prices for all generating plants and create a need for additional subsidies for the remaining units. Competition in the markets will be replaced by competition to receive subsidies.”

Other Opponents

Also opposing PSEG’s proposal are AARP, which launched an anti-subsidy ad campaign, and the New Jersey Coalition for Fair Energy — whose members include Calpine, Dynegy, NRG Energy and the Electric Power Supply Association — which released a TV spot.

The New Jersey Coalition Against Nuclear Taxes includes AARP, environmental groups, the New Jersey Petroleum Council and other groups. Over the summer, one of its members — Dennis Hart, executive director of the Chemistry Council of New Jersey — criticized PSEG for “trying to build support in the New Jersey Legislature for another government handout that may cost all New Jersey ratepayers about $350 million annually over a 10-year period, or $3.5 billion.”

In a press release announcing its formation about a week before last Monday’s hearing, the Coalition for Fair Energy upped that estimate to “the range of $475 million a year or more, or in excess of $4 billion total” based on analysis of the New York and Illinois initiatives.

“There is no need for the Legislature to rush to pass a bill of such magnitude in a lame duck session without a full and thoughtful examination of a subsidy and its implications on the cost of electricity and its impact on a fair, level and competitive electric marketplace,” coalition spokesman Matt Fossen said in the release. “The public deserves complete transparency and a review of PSEG’s finances to see if there is any basis for a ratepayer-financed subsidy.” In his testimony, Izzo promised to open his company’s financial books for an independent examination.

After the Dec. 4 hearing, Smith said that legislation supporting the plants could be enacted during the lame-duck session, which ends early in January. “I learned enough today to begin the discussion,” he told NJ Spotlight.

Outgoing Gov. Chris Christie said he would sign a bill to save the nuclear plants, but only if it does not include incentives sought by environmentalists.

On Remand, FERC Rejects PJM MOPR Compromise

By Rich Heidorn Jr. and Rory D. Sweeney

FERC last week again rejected PJM’s 2012 compromise on the minimum offer price rule (MOPR), saying that eliminating unit-specific exemptions and subjecting generators to the offer floor for three years is unreasonable (ER13-535-004).

The commission originally rejected PJM’s proposal in 2013, saying it discouraged new entry because the exemptions were too narrow and the mitigation period was too long. However, it indicated it would accept the proposal if the unit-specific review were retained and the mitigation period remained unchanged. PJM agreed in a compliance filing adopting FERC’s changes, but a handful of stakeholders petitioned the D.C. Circuit Court of Appeals to review the order.

PJM MOPR
PSEG’s Sewaren 7 natural gas generator is expected to go into operation in summer 2018. | PSEG

In July, the D.C. Circuit said the commission had overstepped its authority in undoing the compromise. The court determined that FERC exceeded its “passive and reactive role” under Section 205 of the Federal Power Act, which requires it to accept proposed rate changes if they are just and reasonable and suggest only “minor” changes. (See PJM MOPR Order Reversed; FERC Overstepped, Court Says.)

PJM’s proposal would have replaced the unit-specific MOPR exemption with two new categorical exemptions and extended the mitigation period from one to three years before a unit could bid below the price floor. The change was prompted by generators’ concerns that the unit-specific review, which allowed units to prove confidentially to PJM that its costs were below the required minimum offer, lacked transparency and allowed below-cost bids.

In exchange for eliminating the exemption, load-serving entities won an agreement for two new exemptions: a competitive-entry exemption for units that are unsubsidized or subsidized through a nondiscriminatory, state-sponsored procurement process; and a self-supply exemption for units intended to meet a portion of an LSE’s needs.

The compromise proposal was widely supported by PJM stakeholders — the first time that a significant MOPR revision had won a two-thirds sector-weighted vote, the court noted.

Following the court ruling, the RTO asked FERC in October to “simply accept PJM’s original Section 205 proposal, unchanged, as just and reasonable.” (See PJM Stakeholders Split on Request to OK MOPR Compromise.)

Although the commission’s membership has changed since 2012, its opinion of the PJM proposal did not.

“We continue to find that PJM has failed to show that its proposed categorical exemptions, standing alone, are just and reasonable … because there would be no means for nonexempted resources with lower costs than the MOPR offer floor to have a competitive bid considered in the auction,” Commissioners Cheryl LaFleur, Neil Chatterjee and Richard Glick wrote in the 3-0 order. “We also continue to find that PJM failed to show that extending the mitigation period from one year to three years is just and reasonable. … Accordingly, we reject PJM’s December 2012 filing in its entirety and reinstate its previously approved market design, i.e., a MOPR without categorical exemptions but with a unit-specific review process and a one-year MOPR mitigation period.”

Chairman Kevin McIntyre and Commissioner Robert Powelson did not participate in the ruling.

The commission said a unit-specific exemption was necessary because “the benchmark price that is used to set the MOPR is an estimate of the net [cost of new entry]. This derived price may exceed the actual costs of individual generators and such generators should have an opportunity to demonstrate as much.”

The fact that unit-specific reviews are more complicated than categorical exemptions did not justify their elimination, the commission said. “We concur with the [Independent Market Monitor], and we disagree with the notion that the unit-specific review is an unworkable method to prevent buyer-side market power, as evidenced by its effective use in ISO-New England Inc. and NYISO.”

It said the three-year mitigation period was improper because it would prevent resources from bidding based on their going-forward costs.

“Before a resource is built, its incremental cost would reflect the unit-specific net CONE, but once the resource has cleared in one auction, its developer would need to begin construction to meet its obligation three years later in the delivery year. At that point, the construction costs incurred prior to subsequent auctions become sunk costs, and they are not part of the resource’s incremental costs going forward,” the commissioners said. “But under a three-year mitigation period, developers whose offers are mitigated and clear in the auction would be prevented from offering at their going-forward costs for at least two years beyond the first auction in which they clear and would instead have to offer at … an artificially inflated price.”

The commission said, however, that it would not order PJM to rerun its capacity auctions under the rules in effect before the 2012 filing, saying it “would cause significant disruption and burdens that are not warranted.”

The situation may soon become moot as PJM completes its yearlong examination of its capacity construct. A proposal from the Monitor to extend the current MOPR process — the only plan to receive endorsement by the task force investigating the issue — is set for a vote at the Dec. 21 meeting of the Markets and Reliability Committee.

The proposal would expand the MOPR to all units indefinitely but would include exemptions for self supply, competitive entry, public power and state renewable portfolio standards programs.

The Monitor is holding a question-and-answer session following Tuesday’s Operating Committee meeting to address stakeholder questions ahead of the vote.

PJM has not confirmed it would file the proposal for FERC approval should it win endorsement, but Monitor Joe Bowring confirmed he would file it himself if the RTO refuses. (See related story “Stakeholders Have Questions Before Approving MOPR-Ex,” Markets and Reliability/Members Committees Briefs: Dec. 7, 2017.)

PJM Unit to Help Develop Western Markets

By Rory D. Sweeney, Jason Fordney and Rich Heidorn Jr.

PHILADELPHIA — PJM and reliability coordinator Peak Reliability announced Thursday they will explore the development of markets and other services in the West, creating a potential competitor to the expansion ambitions of CAISO and SPP.

Peak Reliability, the NERC-designated reliability coordinator for most of the Western Interconnection, announced the agreement to “explore reliability services and markets in the West” with PJM Connext, a non-regulated subsidiary of PJM Interconnection LLC, operator of the world’s largest wholesale electricity market and North America’s largest grid.

“Peak and PJM Connext will begin review of potential reliability services, market design, governance, product suites, rules, technology and organization,” they said in a press release, promising to report on their finding by the end of March 2018. “We believe that our partnership will lead to a viable and credible alternative structure in the West,” the release quoted PJM CEO Andy Ott.

“I think it’s a good fit,” Ott said in an interview after a meeting of the PJM Members Committee Thursday.

Ott said the initiative resulted from requests Peak had received about whether it could provide more services.  “They’re geared toward reliability services. We could provide the market-oriented and operational services,” he said.

“At this point, it’s exploratory,” Ott added. “The notion of having this separate company allows us to do that and keep risk off of PJM members.”

“PJM has an established track record as an innovative and cost-effective provider of system operations and market services,” Peak CEO Marie Jordan said in a statement. “Our partnership seeks to leverage Peak’s West-wide system model, PJM’s markets expertise, and our combined processes, people and tools. Both Peak and PJM share a strong commitment to developing solutions, tailored to the Western Interconnection.”

The two said their research will include an “outreach program” to Western Interconnection “industry leaders and stakeholders.”

pjm peak reliability western electric markets
| NERC

The announcement led Montana regulator Travis Kavulla to tweet Thursday afternoon that PJM and Peak “just sent a letter to regulators announcing they’re exploring how to form a new RTO in the West.”

“Big stakes here,” added Kavulla, a member of the Montana Public Service Commission and former chair of the National Association of Regulatory Utility Commissioners. “If Peak against the odds pulled this off, it’d be a huge coup. But Peak’s funders (including those championing rival RTO efforts) probably aren’t going to be very warm on this.”

Kavulla told RTO Insider: “I took the liberty of describing it as an RTO because I figured they are using a euphemism to avoid that description.”

Asked about Kavulla’s interpretation, PJM spokeswoman Susan Buehler said “The agreement allows PJM and Peak to explore opportunities in the West. We are looking at market services but it’s too early to predict anything else.”

Later, Kavulla tweeted a quote from Gary Ackerman, executive director of the Western Power Trading Forum, who weighed in with a report in the Friday Burrito, his weekly newsletter.

Ackerman said he spoke with Jordan and asked her “if the new venture was contemplating a full market including day-ahead, real-time energy and ancillary services? She assured me it was.

“She also said although no anchor balancing authorities have yet come forward, she has been in discussions with many … and there is widespread interest,” Ackerman wrote, according to Kavulla.

Kavulla also shared a portion of the letter to regulators, in which Peak called the announcement “an exciting opportunity to address challenges facing the West and the issues we have been hearing about as we’ve met with many of our stakeholders. We believe that Peak and PJM’s complementary strengths can lead to a viable and credible alternative option at the time when the West is looking at markets to reduce costs.”

RTO Requirements

Any effort to create a full-fledged RTO would require PJM and Peak to meet the requirements of FERC Order 2000. The order sets four minimum requirements for an RTO: “independence from market participants; appropriate scope and regional configuration; possession of operational authority for all transmission facilities under the RTO’s control; and exclusive authority to maintain short-term reliability.”

Headquartered in Vancouver, Wash., Peak runs reliability coordination offices there and in Loveland, Colo., which provide situational awareness and real-time monitoring of all or parts of 14 western states, the Canadian province of British Columbia and a small, northern portion of Baja California, Mexico. Its region totals 1.6 million square miles and includes 110,129 miles of transmission and a population of 74 million.

The venture is the latest development to indicate the West is warming to the notion of organized markets.

Eight members of Mountain West, including Xcel Energy’s Public Service Company of Colorado, are considering joining SPP. (See Col. Regulators Talk Governance with SPP, Mountain West.) Peak Reliability is Mountain West’s current reliability coordinator.

SPP Chief Operating Officer Carl Monroe did not seem concerned about the prospect of competition. “We’re supportive of markets and collaboration between reliability coordinators in the West and welcome the opportunity to work with PJM and Peak Reliability to bring reliability and economic benefits to ratepayers in the west, just as we have been successfully doing in the east for many years,” he told RTO Insider.

California enacted a law in 2015 that requires CAISO and state energy agencies to explore expanding the ISO to help the state meet its 50% renewable energy mandate. CAISO’s Western Energy Imbalance Market (EIM), which includes PacifiCorp, Arizona Public Service, Puget Sound Energy and NV Energy, has produced more than $213 million in gross benefits since commencing operation in November 2014.

But governance concerns have hampered efforts to build the EIM into a full-fledged RTO. One contentious issue for coal-burning states is California’s requirement that its utilities track carbon emissions from generation serving their loads to ensure compliance with emissions caps. (See CAISO Expansion in Question as EIM Grows.)

The Western Electricity Coordinating Council (WECC) said it had no comment on Peak’s plans. CAISO did not immediately respond to a request for comment.

Peak Reliability was formed in 2014 when WECC bifurcated, with it becoming a NERC Regional Entity and Peak Reliability becoming the reliability coordinator.  FERC approved the bifurcation in February 2014, making Peak independent of WECC. WECC was formed in April 2002 from the merger of the Western Systems Coordinating Council, and two regional transmission associations.

NERC regional entities are responsible for reliability compliance monitoring and enforcement activities, while reliability coordinators maintain reliability in real-time, coordinating or directing actions to mitigate system issues.

WECC is in the midst of a separate rebranding and restructuring to focus more on its core reliability mission.

Evolution of PJM Technologies

PJM Connext, formerly known as PJM Technologies, was formed in 2000 under PJM’s “other activities protocol,” Ott said.

“We were one of the first RTOs, so some of the concept back then was if we were to monetize any of that intellectual property or groundbreaking ideas, then that feeds back to the membership. That would lower the stated rate,” Ott said.

PJM Technologies includes PJM EIS (Environmental Information Services), which operates the Generation Attribute Tracking System for tracking renewable energy credits. PJM is also looking to license its Dispatcher Interactive Map Application (DIMA) to transmission owners. (See “TOs Must Approve PJM Licensing of DIMA,” PJM Operating Committee Briefs: Nov. 7, 2017.)

In October, PJM announced the unit had signed a contract to help the Chinese province of Zhejiang develop a real-time energy market. That effort will involve three to four full-time equivalent PJM staffers for 18 months. The province, south of Shanghai, has a load equal to almost half of PJM’s.

PJM is consulting with the Chinese on market design, whereas the deal with Peak is for market operation, Ott said.

“There’s more opportunities presenting themselves” now, Ott said “In this case, we see several popping up at once. Just so happens there are more of them, and we’re being more transparent” about announcing the work, he added. “It’s an opportunity for us to further the advance of competitive markets around the world.”

Tom Kleckner contributed to this article.

Pruitt Confirms EPA Working on CPP Replacement

By Michael Brooks

WASHINGTON — EPA Administrator Scott Pruitt on Thursday confirmed that the agency is working on a replacement to the Obama administration’s Clean Power Plan.

EPA Scott Pruitt Clean Power Plan
Pruitt | © RTO Insider

The revelation came in response to a question from Rep. Raul Ruiz (D-Calif.) at a House Environment Subcommittee hearing on the agency’s activities. Pruitt had previously only committed to considering a replacement plan.

Ruiz had asked whether EPA had relied on any new peer-reviewed studies on pollution to support the proposed repeal of the CPP, criticizing Pruitt for reversing the agency’s stance on climate pollution.

Pruitt denied that he had. “Moreover, we are going to be introducing a replacement rule too,” he said.

His statement came at the very end of an hourlong session of the subcommittee in which he answered questions from six members before he left to attend a meeting with President Trump.

Pruitt would return three hours later to resume the hearing, but no subcommittee members followed up on his statement regarding replacement of the CPP or pressed for details about a new plan. Instead, the members’ questions covered a wide array of topics, including Superfund sites, pesticides, water quality, vehicle emissions and fuel standards, hurricane recovery and Pruitt’s frequent travel to his home state of Oklahoma. Pruitt declined to take questions from reporters after the hearing.

He also gave no indication of plans to overturn the agency’s endangerment finding on carbon dioxide.

Earlier in the morning session, Rep. Joe Barton (R-Texas) encouraged Pruitt to revisit the finding, which both agreed EPA had rushed to put out in 2009 in the wake of Massachusetts v. EPA, the Supreme Court decision confirming the agency’s authority to regulate carbon dioxide as a pollutant.

EPA REV Scott Pruitt Clean Power Plan
Pruitt testifying before the House Environment Subcommittee | © RTO Insider

Pruitt also said that he is still working on a “red team/blue team” debate regarding the science of climate change and hoped to announce it at the beginning of next year “at the latest.”

“I think one of the most important things we can do for the American people is provide that type of discussion, because it hasn’t happened at the agency,” Pruitt told Barton. “We need to ensure that type of discussion occurs, and it occurs in a way that the American people know that an objective, transparent review has taken place.”

Thursday’s hearing was predictably partisan in nature. Pruitt received a warm welcome and pats on the back from Republicans, who praised his work at the agency and his so-called “back to basics” approach. Democrats, on the other hand, lambasted him for his rollback of numerous Obama-era regulations, including the CPP.

Many of Pruitt’s answers mirrored those he gave at his Senate confirmation hearing in January. He talked about the importance of the “rule of law” and process, saying EPA had overstepped its bounds under President Barack Obama. (See Dems Unmoved by EPA Pick’s Charm Offensive.)

On Wednesday, EPA announced that it would hold three additional hearings on the CPP after what Pruitt called “the overwhelming response” to the agency’s hearing in Charlestown, W.Va. (See No Unanimity in ‘Coal Country’ Hearing on CPP Repeal.) The agency said the hearings will be in San Francisco, Kansas City, Mo., and Gillette, Wyo., though it did not provide specific dates or venue locations.

UPDATED: McIntyre Takes FERC Chair; Wins Delay on NOPR

By Rich Heidorn Jr., Amanda Durish Cook and Michael Kuser

Kevin McIntyre, sworn in as FERC chairman Thursday, will have a month to build support for his response to the Department of Energy’s controversial proposal for coal and nuclear price supports.

On Friday, Energy Secretary Rick Perry granted a 30-day delay from the Dec. 11 deadline set in Perry’s Notice of Proposed Rulemaking. Saying they were needed for grid resiliency, Perry called for compensating coal and nuclear plants in regions with competitive capacity markets that maintain 90 days of fuel on site.

 

FERC NOPR Kevin McIntyre Kevin
FERC Chief Administrative Law Judge Carmen A. Citron swears in Kevin McIntyre as his wife, Jennifer Brosnahan McIntyre, holds a Bible. | FERC

In a letter to Perry, McIntyre said the delay was “critical to afford adequate time” for him and Democrat Richard Glick, who was sworn in Nov. 29, to review the more than 1,500 comments filed in the docket (RM18-1) “and engage fully in deliberations.”

Perry agreed to the request Friday, setting a new deadline of Jan. 10. “The commission is nevertheless authorized to act at any time prior to this deadline and I urge the commission to act expeditiously,” Perry wrote. “… I continue to believe that urgent action must be taken to ensure the resilience and security of the electric grid, which is so vitally important to the economic and national security of the United States.”

New commissioners often choose not to vote on issues subject to deliberations before their arrival. Glick, for example, did not participate in a Dec. 1 order on a state-federal jurisdictional dispute over energy efficiency. (See FERC Claims Jurisdiction on EE, OKs Ky. Opt-Out.)

FERC NOPR Kevin McIntyre Kevin
Glick (left) and McIntyre | FERC

Although McIntyre and Glick have had access to the comments in the docket, McIntyre has not had time to build a consensus around his own response.

What McIntyre may have in mind is not apparent. His only prior public comments on the NOPR came at his confirmation hearing in September. (See McIntyre to Senate: ‘FERC does not Pick Fuels’.)

A Republican, McIntyre joins FERC after 22 years at Jones Day, where he was coleader of the law firm’s global energy practice. His former Jones Day colleague Don McGahn is President Trump’s White House counsel.

Perry acted within his legal authority in ordering FERC to consider his NOPR. But he has no power to make FERC provide the relief he is seeking, legal experts say. (See FERC’s Independence to be Tested by DOE NOPR.)

McIntyre did not appear to have signaled his plans to fellow commissioners Cheryl LaFleur or Rob Powelson, who indicated in public appearances Wednesday and Thursday that they expected to rule on Monday, as promised by interim Chairman Neil Chatterjee. DOE Under Secretary Mark Menezes said Wednesday that the ruling was likely to be pushed back one day to Dec. 12. (See DOE: German Energy Struggles Sparked NOPR.)

FERC’s website was briefly overwhelmed by traffic after the agency tweeted out a link to McIntyre’s letter at 6:35 p.m. Thursday.

Analysts at ClearView Energy Partners had said before news of the letter that the commission appeared to lack a consensus for responding to the NOPR. “Over the course of this week, Commissioner Neil Chatterjee conceded that he has not successful in persuading his other colleagues to support the interim solution he prefers,” the analysts wrote in an email to the firm’s clients Friday morning. “Last night’s action indicates to us that the new chairman may not be persuaded that closing the docket and issuing a Notice of Inquiry to the FERC-jurisdictional regional transmission organizations — the option purportedly preferred by Commissioners Cheryl LaFleur and Rob Powelson — is necessarily a course of action he prefers.”

LaFleur told MISO’s Board of Directors meeting in Carmel, Ind., on Thursday that the commissioners were “busily scurrying to get something out on Monday.”

“I’m actually to the point where I’m relieved [the deadline] is Monday because if it was March 11, we’d talk about it until March 11,” she said.

Republicans Chatterjee and Powelson have indicated support for Perry’s proposal. On Wednesday, Powelson told the PJM General Session that the commission would craft a “defensible” response to the NOPR that does not upend competitive markets.

LaFleur Previews Ruling

LaFleur, a Democrat, has been noncommittal in her public statements. (See DOE, Pugliese Press ‘Baseload’ Rescue at NARUC.) She told MISO’s board meeting Thursday that if customers are made to pay for generation attributes, it should be done based on data through a transparent market process.

She also said considerations of resilience should include severe weather, cyber threats and transmission. “It probably shouldn’t be confined to the areas with mandatory capacity auctions because their resilience isn’t more important,” she added.

LaFleur said the commission has reached a saturation point on dissecting the resiliency rule. “Finally, last week, even I had too much, and I said, ‘That’s it; pencils down.’”

She said the NOPR interrupted commission work on the backlog of filings that built up during the six months the commission was without a quorum after the resignation of former Chairman Norman Bay. “It’s as if we had all of our jets lined up for takeoff and someone took the airspace,” she said.

Chatterjee, speaking to a meeting of ISO-NE’s Consumer Liaison Group in Boston on Thursday, reiterated his call for providing “interim” relief to at-risk generators while FERC considers the NOPR. (See Chatterjee: ‘We’ve Moved Past’ DOE NOPR.) Chatterjee also sought to calm those who fear the new commission, now dominated 3-2 by Republicans, will be more partisan and less independent than in the past.

Advice for McIntyre

Among those offering McIntyre congratulations was interim NERC CEO Charles Berardesco. “We have a long and productive relationship with FERC,” he said in a statement. “NERC looks forward to continuing work on the key priorities impacting grid reliability, including the changing resource mix, essential reliability services and security challenges.”

Some of those issuing statements welcoming McIntyre also gave advice on how he should rule on the NOPR and other issues.

The Affordable Energy Coalition, an ad hoc group that includes industrial customers and the American Wind Energy Association, urged McIntyre to reject the NOPR. “Chairman McIntyre joins the commission at a critical moment in the agency’s history,” the group said, adding that the ruling on the DOE proposal “will determine the affordability of electricity for tens of millions of American consumers.”

John Moore, director of the Natural Resource Defense Council’s Sustainable FERC Project said the commission “is at a crossroads.”

“As an independent commission, FERC has largely avoided pressure from the White House and Congress in recent years, and hewed mostly to a nonpartisan (if not always harmonious) path,” Moore wrote in a blog post. “In the last several months, however, FERC has faced unprecedented pressure from the Trump administration to subsidize coal plants and nuclear for their claimed ‘resilience’ attributes. McIntyre’s leadership will be a test of the extent to which he can withstand pressure from the White House to bend to its political ends.”

Clients, Contributions

FERC NOPR Kevin McIntyre
McIntyre | © RTO Insider

McIntyre replaces Chatterjee, a former aide to Senate Majority Leader Mitch McConnell (R-Ky.), whose nearly four months as interim chair have been marked by his advocacy for the coal industry and sparring on social media with actor James Cromwell.

It is the first time FERC has had a full complement of five members since October 2015, when Republican Philip Moeller left the commission. The panel faces decisions on ways to harmonize RTO markets with state subsidies for nuclear plants, rulemakings on energy efficiency and distributed energy resources, and pipeline licensing.

During his two decades at Jones Day, McIntyre represented clients in administrative and appellate litigation, compliance and enforcement matters, and corporate transactions. According to his Jones Day biography, McIntyre’s clients have included American Electric Power (negotiations to settle claims in connection with the California energy crisis); SCANA (settlement of Calpine bankruptcy claims); South Carolina Electric & Gas (FERC-jurisdictional rates for electric transmission service); Public Service Company of North Carolina (litigation before FERC concerning the Atlantic Coast Pipeline); and E.ON AG ($1.9 billion acquisition of the North American operations of Irish wind farm operator Airtricity).

McIntyre has been a regular contributor to Republican candidates. In the 2016 presidential primaries, he initially backed both Wisconsin Gov. Scott Walker and Sen. Marco Rubio (R-Fla.), giving each $1,000 in July 2015. He gave Rubio another $1,700 in February 2016. He also has contributed to the Republican National Committee, Sens. Tom Cotton (R-Ark.), Pat Toomey (R-Pa.) and Rob Portman (R-Ohio), and Republican presidential nominees Mitt Romney and John McCain.

McIntyre is a graduate of San Diego State University (A.B., political science) and Georgetown Law. His wife, Jennifer Brosnahan McIntyre, a former deputy general counsel for the U.S. Department of Transportation and associate counsel to President George W. Bush, became chief counsel of Boeing’s Washington Operations in 2010. Married in 2008, the couple have three children.

Cook reported from Carmel, Ind. Kuser reported from Boston.