Search
`
October 10, 2024

FERC Approves Transfer of New Jersey Plants

FERC on Thursday gave energy investment firm Ares EIF Management the go-ahead to transfer its ownership in two New Jersey cogeneration facilities to Excalibur Power (ER16-2217, ER17-2515).

Ares EIF Management Excalibur Power
Logan Cogeneration Plant | Google Maps

Ares owns a 242-MW facility in Logan Township and has a 60% stake in the 285-MW Chambers cogeneration facility in Carneys Point. Atlantic Power owns the other 40% of the latter plant. Both plants have FERC-approved rate schedules to provide reactive power to PJM.

Ares EIF Management Excalibur Power
Carney’s Point Cogeneration Plant | Google Maps

The commission also granted a request to waive the 90-day notice period for transferring the plants, although Ares and Excalibur had sought to obtain the waiver by Dec. 15.

— Rory D. Sweeney

Report: Fuel Security Key Risk for New England Grid

By Michael Kuser

A new ISO-NE report finds that New England’s grid is vulnerable to a season-long outage of any of several major energy facilities, such as the 688-MW Pilgrim nuclear plant in Plymouth, Mass., which went offline during a recent cold snap after the loss of a power line leading to the plant.

That incident resulted in no reliability issues for the RTO.

ISO-NE LNG electricity imports natural gas
Pilgrim Nuclear Station Control Room | Entergy

“Maintaining reliability is likely to become more challenging, especially if current power system trends continue,” the RTO’s Operational Fuel-Security Analysis report said.

The most concerning trend: the increasing reliance on natural gas for power generation, which has led to supply constraints during times of peak load. Under normal conditions, New England relies on natural gas for about half its electric power generation, up from 15% in 2000.

The grid operator began the study in late 2016 to quantify the region’s future fuel security risk. It planned to issue the report last fall but delayed publication until the furor died down over Energy Secretary Rick Perry’s proposed rulemaking to financially support coal and nuclear generators (RM18-1). (See DOE NOPR Rejected, ‘Resilience’ Debate Turns to RTOs, States.)

“The goal was to understand the future implications of several significant trends already affecting grid operations,” ISO-NE CEO Gordon van Welie said. “The results aren’t a prediction, but they do shine a light on the potential reliability consequences of retirements of generators with stored fuels and the significance of liquefied natural gas, imports, renewables and oil inventories at dual-fuel power plants.”

ISO-NE LNG electricity imports natural Gas
| ISO-NE

The study grew out of the RTO’s experiences operating the system through challenging winter conditions and was undertaken to ensure that power plants have, or are able to procure, the fuel they need to meet demand and maintain power system reliability.

Scenarios and Risks

The study created 23 scenarios and focused on five key variables: retirements of coal- and oil-fired power plants; availability of LNG; oil tank inventories at dual-fuel generators; electricity imports from neighboring power systems; and the addition of renewable resources.

ISO-NE LNG
| ISO-NE

The report highlighted the concern that New England’s system reliability is heavily dependent on LNG and electricity imports. While dual-fuel capability for plants can provide a key contribution to reliability, permitting for construction and emissions is difficult. All but four scenarios resulted in fuel shortages requiring rolling blackouts, indicating the trends affecting the system may intensify the region’s fuel security risk.

RTO planners concluded that developing renewable resources could help reduce the fuel security risk but will also likely drive more coal- and oil-fired generators into retirement, requiring increased LNG imports to counteract the loss of stored fuels. At the same time, higher levels of LNG, electricity imports and renewables can minimize system stress and maintain reliability. But delivery assurances for LNG and electricity imports, and transmission expansion, will be needed to attain those levels, the report said.

Recent and impending retirements of oil, coal and nuclear power plants will translate into 4,600 MW of retirements by June 2021, representing more than 10% of the region’s total installed capacity, the report said.

The RTO noted that about 13,500 MW of new generation was in its interconnection queue as of Dec. 1.

“Proposed wind farms make up just over half the proposals, or about 7,300 MW,” the report said. “The queue also includes 1,000 MW of proposed solar (8% of the total) and 400 MW of battery storage (3% of the total). Not all these projects will be constructed; historically, about 68% of the megawatts proposed are never built.”

Massachusetts Sierra Club Director Emily Norton took issue with those numbers.

The report “inexplicably underestimates the amount of renewable energy — i.e. solar and wind — that we know will be coming online in coming years,” Norton said in a statement.” Yet even a report rigged against clean energy shows that New England can affordably and reliably replace most of its old, dirty, dangerous and uneconomic power plants without spending billions of dollars on unnecessary gas pipelines.”

ISO-NE plans to discuss the results of the analysis with stakeholders, regulators and policymakers throughout 2018 to determine the level of fuel security risk they are willing to tolerate.

MISO Readies Retirement Change

By Amanda Durish Cook

CARMEL, Ind. — MISO is close to completing a plan that would give generators three years to submit a decision to retire after signaling their intention, but some stakeholders think the changes could allow unit owners to “game the system” for allocating transmission costs.

MISO FERC generator retirements
Joe Reddoch | © RTO Insider

Joe Reddoch of MISO’s retirement planning group said the proposal — slated for a March filing with FERC — will close out a longtime recommendation from the Independent Market Monitor to allow generators to time their retirements according to Planning Resource Auction timelines.

Under the proposal, generation owners considering or planning a shutdown will still submit an Attachment Y notice to MISO, but the RTO will now treat all such notices as a request for suspension. Owners would no longer have to decide between a permanent retirement and a temporary shutdown with an estimated return-to-service date.

Instead, they would have three full planning years to prepare a return to service or decide to make the suspension permanent, providing additional time to decide whether to participate in the capacity auction. Suspended generators would lose interconnection service after three planning years if they don’t resume operations.

“By removing the return date [requirement], we can actually consider them in our planning processes,” Reddoch said during a Jan. 17 Planning Advisory Committee meeting.

Reddoch said MISO plans to continue its practice of passing pro rata transmission upgrade costs needed to maintain baseline reliability to unit owners who rescind their decision to retire.

Wind on the Wires’ Natalie McIntire pointed out that unit owners cause unnecessary costs for new interconnection customers by deciding to suspend and then come back online after an interconnection customer has shouldered the entire cost of interconnecting to make up for the lost generation.

“We have concerns about this,” McIntire said. “This treatment sort of creates an opportunity to game the system.”

“They could play games right now, but they don’t. They’re simply looking at the viability of their assets,” Reddoch said. “Right now, we create a false sense of security by modeling their return date when most of them never return.”

Reddoch said the proposal will not require changes to the planning process, as planning models already assume all retiring and formerly suspended units will be offline within 36 months. MISO last year deferred the proposal while it looked into possible modeling implications stemming from the change. (See MISO Defers Retirement Process Changes.)

MISO Director of Planning Jeff Webb said the plan improves the auction because owners uncertain about retiring a generator can still choose to participate in auctions, but the RTO’s Interconnection Planning Task Force could still explore the possibility that interconnection customers could be left holding the tab on an ultimately ineffectual network upgrade.

Other stakeholders said generation owners could potentially game the system by vacillating in and out of three-year suspensions. Reddoch pointed out that MISO’s Tariff limits total suspension times to three years in a five-year period.

FERC Rejects Challenge to PJM CP Rules on Coal Plants

By Rich Heidorn Jr.

FERC on Thursday rejected an Illinois Municipal Electric Agency challenge to PJM’s Capacity Performance rules for coal plants, saying it had dealt with IMEA’s concerns in its June 2015 order approving the program (ER15-623-010, et al.).

IMEA asked for rehearing on two aspects of the commission’s May 2016 follow-up CP order on compliance, arguing that the order will “unduly disadvantage coal-fired generation owners like IMEA who separately bid in their minimal level of output and megawatts,” according to FERC’s summary.

PJM Capacity Performance CP IMEA
IMEA owns 12% of LG&E and KU’s Trimble County 1, a 514-MW coal-fired unit between Louisville and Cincinnati. | LG&E-KU

Created in 1984, IMEA comprises 32 municipal electric systems and one cooperative in Illinois. It owns a 15% stake in two 800-MW supercritical units at the Prairie State Generating Co. in Southern Illinois, and 12% of Trimble County 1 (a 514-MW coal-fired unit) and Trimble County 2 (a 750-MW super-critical, pulverized coal-fired unit) located between Louisville and Cincinnati.

Nonperformance Charge Exemption

IMEA said FERC should have approved PJM’s compliance filing — a response to the June 2015 order — proposing to exempt generators from nonperformance charges “if the relevant resource is not scheduled by PJM, or is online but scheduled down, subject to a determination by PJM that such an action is appropriate” under its economic dispatch.

The agency said the May 2016 order was thus inconsistent with commission precedent recognizing the longer ramp-time needs of coal units.

But FERC ruled that “IMEA effectively seeks rehearing of the initial June 2015 order, not the May 2016 order.”

“Having failed to seek rehearing of the June 2015 order on this issue, IMEA may not raise these issues on rehearing of the May 2016 order addressing PJM’s compliance filing,” the commission said.

Operating Parameter Constraints

PJM IMEA Capacity Performance CP
IMEA Members | IMEA

The commission also rejected IMEA’s argument that PJM’s compliance proposal on operating parameter constraints failed to provide sufficient specificity or transparency.

IMEA said “it is critical that PJM be required to explicitly document the specific operating limitations it will impose on a given resource and the reasons justifying those limitations,” FERC explained.

In response, the commission reiterated its May 2016 order, finding that PJM’s provision of timelines and details specifying how the RTO will implement its process for reviewing unit-specific parameter limited schedules is sufficient.

The commission cited “provisions of PJM’s Tariff allowing for an annual review of unit-specific parameter limitations and a case-by-case procedure through which a resource can justify operating outside of its unit-specific parameters for purposes of receiving make-whole payments. The May 2016 order further interpreted PJM’s obligation to notify a seller in writing regarding PJM’s determination as a commitment to provide sufficient detail regarding its determination.”

Chairman Kevin McIntyre and Commissioner Robert Powelson did not participate in the ruling.

FERC Sides with Incumbent TOs; OKs Limits on Competition

By Rory D. Sweeney

In a win for PJM’s incumbent transmission owners, FERC ruled Thursday that transmission projects driven by TOs’ individual planning criteria are exempt from competitive bidding.

It also ruled against a competitive transmission developer’s request to allow bidding on some immediate-need projects (ER16-2401, EL16-96).

FERC transmission owner planning criteria
| © RTO Insider

The order approved Tariff and Operating Agreement revisions PJM proposed in response to FERC’s July 2016 show cause order initiating a Section 206 proceeding over inconsistencies in the OA. (See FERC Rejects PJM Cost Allocation on Dominion Project.)

PJM made revisions suggested by the commission to clarify that projects driven solely by a TO’s Form 715 local planning criteria are not subject to PJM’s competitive process because all the costs are allocated to the zone of the TO. PJM’s competitive process is limited to regionally allocated projects.

In the revisions, PJM also said it will identify local planning criteria transmission needs at the monthly Transmission Expansion Advisory Committee meetings so stakeholders can review and comment on them. The RTO will present its solutions to the issues, identifying applicable criteria, the project’s zone, alternatives it considered and an explanation of the decision to assign the project to the incumbent TO.

LSP Challenge

LSP Transmission, an LS Power subsidiary, challenged both the 206 proceeding and PJM’s filing in response. It said the RTO’s proposed revisions stifle competition and overlap with issues outstanding in other dockets, including a request for rehearing on an order that Form 715 projects aren’t eligible for regional cost allocation (ER15-1387). It also cited a show cause order in August 2016 questioning whether PJM TOs’ procedures for planning supplemental projects provided stakeholders opportunity for “early and meaningful input and participation,” as required by Order 890 (EL16-71).

Neither has been decided. In December 2016, the commission did reiterate an earlier ruling that Form 715 projects are not eligible for regional cost allocation. (See FERC Rejects Challenges on Local Tx Cost Allocations.)

Defining ‘Immediate Need’

LSP also argued that FERC “got it backwards” in directing PJM to clarify the three-year threshold for immediate-need reliability projects. LSP said immediate-need projects should only be exempt from competition if the in-service date of a solution is within three years, rather than also exempting those with a need date within that period.

PJM responded that it “makes no sense” to delay a project that cannot be built within three years to conduct bidding.

FERC agreed, saying, “The fact that it may take longer than three years to build a solution to an immediate reliability need is not a persuasive justification for potentially further delaying the solution.”

RTEP Approvals

In a related order, FERC on Thursday confirmed its approval of PJM’s cost allocations for projects added to its Regional Transmission Expansion Plan in March 2017 (ER17-1236). Commission staff had approved the allocation tentatively in June 2017 while the commission was without a quorum.

FERC denied a protest and request for rehearing from Dominion Energy, which had argued it shouldn’t be allocated all costs for two 500-kV facilities in its zone to address its Form 715 criteria. Dominion is appealing the order that allocated all Form 715 project costs to zones in which the criteria apply (ER15-1387).

Commissioner Cheryl LaFleur issued a separate concurrence, pointing out that she had dissented on the order Dominion is appealing.

“As explained in that dissent, I believe the commission should have retained regional cost allocation for transmission projects that are double-circuit 345 kV and 500 kV and above,” she wrote.

FERC Backs NERC Supply Chain Standards

By Michael Brooks

WASHINGTON — FERC on Thursday proposed to adopt several reliability standards intended to mitigate cybersecurity risks posed by the global supply chain of grid operation tools.

Multiple entities around the world may participate in the development of software or technology used by utilities to manage their reliability duties, exposing them to potential corruption.

FERC NERC cybersecurity supply chain

In a Notice of Proposed Rulemaking (RM17-13) FERC indicated its intention to approve a NERC critical infrastructure protection standard (CIP-013-1) that would require utilities to consider several cybersecurity issues when procuring these products for their medium- and high-impact systems. These issues include:

  • disclosure of known vulnerabilities in the products;
  • security event notifications;
  • coordination of vendor remote access;
  • notification when vendor employee remote or onsite access is terminated;
  • coordinated response to vendor-related cybersecurity incidents; and
  • verification of integrity and authenticity of all software and patches.

NERC noted that the standard does not “require that every contract with a vendor include provisions for each of the listed items.” Rather, utilities would need to “ensure that these security items are an integrated part of procurement activities, such as a request for proposal or in the contract negotiation process.”

The actual terms and conditions of utilities’ contracts with vendors are outside the scope of the standard, as are the activities of the vendors themselves. “A responsible entity should not be held responsible under the proposed reliability standard for actions (or inactions) of the vendor,” NERC said.

Reliability officials would evaluate and reapprove utilities’ procurement processes every 15 months under the standard.

FERC also proposed to adopt two additions to existing NERC standards, both to support the requirements in CIP-013-1. One (CIP-005-6) would require utilities to develop a method for identifying active remote access sessions by vendors. The other (CIP-10-3) would require utilities to verify the source of all software and patches before installing them.

Broader Scope, Tighter Deadline

NERC developed the standards in response to a FERC directive in July 2016, marking only the third time the commission has taken such initiative. (See FERC Orders NERC to Develop ‘Flexible’ Supply Chain Standard.) The organization submitted the proposed standards last September.

FERC found that NERC had generally satisfied the four objectives it had laid out in its order: software integrity and authenticity; vendor remote access; information system planning; and vendor risk management and procurement controls. The commission had also directed that the standard be flexible, leaving it to utilities to determine the best way to comply.

However, the commission directed NERC to include Electronic Access Control and Monitoring Systems (EACMS) — firewalls, authentication servers, security event monitoring systems and intrusion detection systems, for example — as part of the scope of the standard.

It also instructed NERC to evaluate the risks posed by Physical Access Control Systems (PACS) — such as motion sensors, badge readers and electronic locks — and Protected Cyber Assets (PCAs) — networked printers, file transfer servers and local area network switches — as part of a supply chain cybersecurity study the organization’s Board of Trustees ordered last August.

FERC also proposed to tighten the implementation deadline for the standards, shortening NERC’s proposed 18 months after commission approval to 12.

Commissioners: Good First Step

Commissioner Cheryl LaFleur, who had dissented from FERC’s earlier order, issued a lengthy concurrence to explain her vote. She had called the July 2016 directive too broad and lacking in guidance. She had also said the timeline for developing the standards was too short given the lack of stakeholder input.

At the commission’s open meeting Thursday, LaFleur said she still had some of those concerns, calling the standards “quite general.” But, she said, “I agree that they are an improvement over the status quo.

“I do not believe that remanding these standards or the larger supply chain issue to the NERC standards process would be a prudent step at this point,” she said. “Rather, I believe the better course of action at this time is to move forward with these standards and … improve them over time as needed.”

Her colleagues had similar sentiments.

“While the standard is not a panacea, it is an important step forward to tackle a tough problem,” Commissioner Neil Chatterjee said. “It will be particularly important to revisit the standard after several years of experience to see what is working and what aspects could be improved. But again, today’s order is a good step in the right direction.”

Commissioner Richard Glick also called the standards “an important first step,” but “I think more needs to be done.”

Comments on the proposal to adopt the standards are due 60 days after its publication in the Federal Register.

EOP Reliability Standards

FERC on Thursday also approved several updates to emergency preparedness and operations reliability standards proposed by NERC last March (RM17-12).

The revisions streamline existing standards and remove redundant language. The commission said they will ensure accurate reporting of events to NERC’s event analysis group; delineate the roles and responsibilities of entities involved in system restoration processes; and identify the elements required in plans for continuing operations when primary control functionality is lost.

FERC did not make any changes to the EOP standards since it proposed to adopt them last September, nor did stakeholders propose any. (See FERC OKs Rules on Balancing, Interconnection, Remedial Actions.) They will go into effect 60 days after their publication in the Federal Register.

FERC Denies FirstLight Hydro Capacity Change

By Michael Kuser

FERC on Thursday denied FirstLight Hydro Generating’s request to change reservoir levels this winter at a Massachusetts hydroelectric plant, citing inadequate time to assess the impact on the endangered shortnose sturgeon (P-2485-076).

FERC
Shortnose Sturgeon

FirstLight requested the temporary amendment to increase operational flexibility at its 1,167-MW Northfield Mountain Project in anticipation of potential reliability challenges in New England this winter. ISO-NE supported the request but did not say the extra capacity would be critical to reliability.

FERC sympathized with FirstLight’s intentions, but ultimately sided with the shortnose.

“While we are very sensitive to the need to take all feasible steps to ensure the reliability of the electric grid, and accordingly have approved previous amendment requests by FirstLight, the presence of an endangered species in the project reservoir that may be affected by the amendment is a significant new circumstance,” the commission said. “We could not lawfully approve the current amendment before completing consultation with the [National Marine Fisheries Service], a process that would require the gathering of information, followed by NMFS review and action.”

In comments filed with FERC last October, NMFS indicated the sturgeon had been found in Northfield Mountain’s lower reservoir, which was historically above the recognized upstream extent of the species’ range.

The commission ordered that “any future proposal of a similar nature should be filed a sufficient time before the winter season such that any necessary efforts with respect to [Endangered Species Act] consultation can be completed in a timely manner.”

Under federal regulations, NMFS has 135 days to complete a consultation. The commission said that “it did not appear possible” that the consultation process could be completed before March 31, the end of the period for which FirstLight requested the temporary amendment.

Technical Limits

FirstLight proposed reducing Northfield Mountain’s minimum reservoir elevation from 938 mean sea level (msl) feet to 920, and bumping up the maximum from 1,000.5 msl feet to 1,004.5, increasing the potential operating range from 62.5 feet to 84.5 and available storage from 12,318 acre-feet to 15,327. The company also sought unrestricted use of the extra capacity.

According to FirstLight, the additional 3,009 acre-feet of storage would increase the facility’s maximum daily generation by 2,050 MWh, or an additional 1.8 hours of generation at full load. Within current limits, it is capable of generating 8,729 MWh/day during peak load conditions.

But FERC signaled that it would seek limits on the flexibility offered by the adjustments. In its decision, the commission ordered that “any future proposal should be restricted to use during ISO-NE discretionary actions taken during emergency operations … unless FirstLight can provide sufficient evidence why a broader amendment is appropriate.”

The commission has previously granted six temporary amendments for the facility. The first three allowed FirstLight to modify operations only when ISO- NE declared an energy emergency, triggered by a forecast showing electric demand could exceed capacity reserves. The fourth and fifth did not restrict FirstLight’s use of the additional storage, but the sixth, most recent amendment also restricted the use of the additional storage to declared emergencies.

FERC Northfield Mountain FirstLight Hydro
Connecticut River at Turners Falls

Northfield Mountain includes an upper reservoir, an underground powerhouse containing four reversible pump-turbine generators and an intake/outlet structure in the Turners Falls reservoir. The 22-mile-long reservoir on the Connecticut River serves both Northfield Mountain and the Turners Falls Hydroelectric Project, for which FirstLight also holds the license.

FERC Northfield Mountain FirstLight Hydro
Northfield Mountain Environmental Impact Study | FirstLight Hydro

Northfield Mountain, Turners Falls and three other hydroelectric facilities directly upstream are all currently undergoing relicensing. As part of that process, the licensees are required to conduct studies for the five facilities to analyze interrelationships in project operations and environmental effects.

‘Horse is out of the Barn’ for CAISO RC Effort

By Jason Fordney

CAISO said Wednesday there is no turning back on its departure from Peak Reliability in September 2019.

CAISO RC reliability coordinator
Schmitt | © RTO Insider

California’s grid operator has been studying its recent move to become a reliability coordinator (RC) since early last year, and ISO officials have extensively reviewed the proposal to offer RC services to others, CAISO Vice President of Operations Eric Schmitt said during a Jan. 17 conference call.

“We didn’t wake up on that morning” and decide to become a RC, Schmitt said, noting that the ISO on Jan. 2 gave Peak notice that it was departing.

“We were reluctant to do that, to be honest with you,” Schmitt said. “But it’s pretty evident that the marketplace is changing.” He added that the Western Interconnection is “is going to be even more complicated as we go forward.” Having notified Peak, CAISO must now become its own RC. “The horse is out of the barn,” he added.

The ISO hopes other Western balancing authorities will sign up for its RC services. Its timeline calls for comments on the plan by mid-May, a rate proposal to be submitted to its Board of Governors in late June, a FERC filing in August and final approval in October. The effort also requires approval from the Western Electricity Coordinating Council, the Regional Entity that develops the West’s reliability standards.

CAISO RC reliability coordinator
CAISO’s planned timeline for RC services offering | CAISO

CAISO is asking that potential customers sign nonbinding letters of intent by March 1 that make them part of the implementation process and that in the future they will sign reliability service agreements.

Schmitt said CAISO will continue to work closely with Peak throughout the transition. “We have enjoyed a great relationship with Peak,” he said. “We expect that relationship will continue.”

When announcing its departure, CAISO cited its expectation that the Vancouver, Wash.-based Peak will be forced to increase its fees because of Mountain West Transmission Group’s likely departure from the RC, as well as Peak’s recent announcement that it has partnered with PJM to offer competitive market services in addition to reliability services in the West. (See Peak, PJM Detail Western Market Proposal.)

CAISO knows what it takes to obtain certification as an RC and has a transferable skill set for RC services, Schmitt said. The ISO is a registered balancing authority and already performs some reliability functions for its participating transmission owners, such as outage coordination, next-day planning analysis, and real-time grid monitoring and assessment.

New services in CAISO’s RC area would include system operating limit methodology, review of system-wide restoration plans, stakeholder processes and other services. It also plans to offer some non-RC services, such as hosting advanced applications and physical security risk assessment that will involve separate charges. CAISO will need to add personnel to support RC functions such as customer service, NERC/WECC compliance and technology positions. There would be an RC representative in each of the ISO’s two control centers located in Folsom and Lincoln.

The ISO had other public meetings on the RC proposal scheduled for Jan. 18 in Phoenix, Ariz., and Jan. 19 in Portland, Ore. Details of the initiative are provided on a new RC website.

NYISO Business Issues Committee Briefs: Jan. 17, 2018

NYISO power prices jumped sharply in December on the back of sharp gains for natural gas stemming from extreme cold weather at the end of the month.

Locational-based marginal prices (LBMPs) averaged $52.63/MWh for the month, up 58% from November and nearly 20% from the same period a year ago, Robert Pike, NYISO director of market design and product management, told the ISO’s Business Issues Committee (BIC) on Wednesday.

The ISO’s year-to-date monthly energy prices averaged $36.56/MWh in December, a 7% increase from a year earlier. The average daily sendout was 444 GWh/day, compared with 403 GWh/day in November and 433 GWh/day a year earlier.

NYISO natural gas prices
| NYISO

New York natural gas prices surged 260% over the previous month, averaging $7.59/MMBtu at the Transco Z6 hub. Prices were up 73% from a year ago. Natural gas prices for the month peaked at $31.16/MMBtu on Dec. 29, five days into a severe cold snap.

Distillate prices gained 20.1% year on year, with Jet Kerosene Gulf Coast averaging $13.47/MMBtu, up from $13.04 in November. Ultra Low Sulfur No. 2 Diesel NY Harbor averaged $13.91, compared with $13.70 a month earlier.

The ISO’s local reliability share was 9 cents/MWh, down from 20 cents/MWh from the previous month, while the statewide share dropped 18 cents/MWh from the previous month to -78 cents/MWh. Total uplift costs were lower than in November.

Ongoing JOA Dispute with New Jersey

Reviewing the Broader Regional Markets report, Pike noted that the New Jersey Board of Public Utilities last month filed a complaint with FERC against PJM, NYISO, Consolidated Edison, Linden VFT, Hudson Transmission Partners and the New York Power Authority. The complaint challenges the implementation of the mutual benefits provisions of the Joint Operating Agreement between NYISO and PJM and requests amendments to it.

Pike said the ISO last month jointly filed with the other respondents to request an extension of the Jan. 11 answer deadline to Feb. 23. The commission granted the extension, which was unopposed by the BPU.

The report also noted the ISO is taking further steps to improve modeling consistency between real-time commitment (RTC) and real-time dispatch (RTD) and examine changes to look-ahead evaluations to improve scheduling and price convergence. The ISO published a white paper on the topic last month and will further explore RTC-RTD convergence this year.

BIC Recommends ICAP Manual Revisions

The BIC also recommended revisions to the Installed Capacity (ICAP) Manual covering deliverability requirements for capacity imports from PJM, effective May 1.

Zachary Smith, NYISO manager of capacity market design, told the committee that the ISO finished modifying the documentation requirements for capacity imports across the PJM AC ties. His report outlined changes that would require PJM-based ICAP suppliers to provide NYISO with evidence of firm transmission service for all capacity import obligations on the day Spot Market Auction results are posted.

NYISO natural gas prices
| PJM

Suppliers that fail to provide documentation by the deadline would be subject to penalties and deficiency charges. Monthly deadlines, which will be posted on the ICAP event calendar, would be the same for all imports.

The committee will continue evaluating deliverability requirements for other interfaces and imports.

New Price Correction Deadlines

The committee also approved modifying price-correction deadlines by using business days rather than calendar days in the period calculation. If approved by NYISO’s Management Committee and Board of Directors, the Tariff revision would reset deadlines to four business days after the market day for real-time prices, and two business days after the market day for day-ahead prices. The change is subject to FERC approval.

Michelle Gerry, the ISO’s price validation supervisor, told the BIC that ISO-NE allows five business days for real-time price corrections and three days for day-ahead, while PJM stipulates 10 calendar days for both categories.

NYISO would continue to provide notice as soon as any price correction is processed and post a detailed correction within 10 days of each correction, as well as the quarterly price correction report recapping all corrections for each quarter.

NYISO Applies Wind Forecast Fee to Solar

The BIC voted to recommend Tariff changes that would charge New York’s utility-scale solar facilities for acquiring solar forecasts, similar to how the ISO currently recovers the costs for wind forecasts.

NYISO Natural Gas natural gas prices

The changes would be implemented in mid-2018 and would also apply to meteorological data requirements. The ISO will next year pursue Tariff modifications for the economic dispatch of solar.

In a report on solar integration, David Edelson, NYISO operations performance and analysis manager, explained that the grid operator procures a centralized solar forecast for each of its 11 load zones, for both behind-the-meter and individual utility-scale resources.

Edelson said the new cost recovery mechanism is modeled on the ISO’s wind forecasting fee, which is $500/month for each resource, plus $7.50/MW (nameplate) per month. The proposed Tariff changes would modify the forecasting fee rate to $6.20/MW (nameplate) per month for both wind and solar resources so that the fees remain in line with the costs NYISO incurs to develop the forecasts.

Applying these rules to front-of-the-meter solar resources will improve NYISO’s ability to reliably integrate higher levels of solar onto the grid, Edelson said.

— Michael Kuser

ERCOT, SPP Extend Winter Peak Records

Just as it projected a day earlier, ERCOT set a new winter peak of 65.73 GW Wednesday morning. The demand was almost 3 GW higher than the previous record of 62.86 GW on Jan. 3. (See SPP Resets Winter Peak Record, ERCOT Set to Follow.)

ERCOT SPP winter peak recordsThe ISO said historic low temperatures in Texas resulted in multiple new peaks before demand settled on the new record between 6 and 7 a.m. Single-digit temperatures extended from North Texas to the Gulf Coast overnight, stranding trucks on icy highways.

ERCOT said it has sufficient generation resources to meet forecasted demand, but it also issued a news release Wednesday offering conservation tips to consumers.

SPP also set yet another winter peak when it recorded demand of 43.58 GW at 7:23 a.m. Wednesday. That surpassed the Jan. 16 record of 42.71 GW.

MISO tweeted late Wednesday night that MISO South had also set a new winter peak but did not say the exact figure.

— Tom Kleckner