Search
`
November 18, 2024

PJM: MISO Monitor Lacks Standing in Pseudo-tie Complaint

By Amanda Durish Cook

PJM has again moved to dismiss Potomac Economics’ complaint against its pseudo-tie construct, citing a recent court ruling that describes a limited role of RTO/ISO market monitors in legal proceedings.

Pseudo-tie MISO PJM Potomac Economics
Patton | © RTO Insider

MISO’s Independent Market Monitor filed a Section 206 complaint in April 2017 asking FERC to eliminate PJM’s existing pseudo-tie definition, claiming that the increasing use of pseudo-ties degrades reliability, hampers efficient dispatch and raises costs. (See Pseudo-Tie Feud Rises as Patton, NYISO Protest PJM Proposal.)

PJM is pointing to a June 15 D.C. Circuit Court of Appeals ruling that confirms FERC’s 2017 decision that Old Dominion Electric Cooperative cannot recover its operating costs incurred in excess of its filed rate during 2014’s polar vortex. The commission said such a move would constitute retroactive ratemaking (16-1111).

In its June 19 filing in the pseudo-tie complaint (EL17-62), PJM said the ODEC decision importantly included a denial of its own Independent Market Monitor’s motion to intervene. PJM said the court’s opinion shows that “a market monitor does not have standing to intervene in a proceeding on judicial review of commission orders” and that the case is “instructive” in its motion to dismiss the MISO Monitor’s complaint. PJM asked FERC to consider the precedent in its upcoming decision.

The court said that the PJM Monitor “has no legally cognizable interest” in the ODEC case and denied its motion to intervene.

The Monitor’s role, the court said, “is much in the nature of an auditor — it is largely confined to observing the market’s operations and then offering recommendations to PJM. The Monitor has no authority to enforce or to interpret the PJM [Operating] Agreement or Tariff, to direct changes in the market’s operations, to alter market rules or to police individual members’ compliance.”

The court added that “other than making some regulatory filings,” the Monitor is confined to informing FERC, other government agencies and RTO participating members “if it disagrees with PJM’s implementation of the market rules or operation of the PJM market.”

“Beyond its contractually assigned tasks, the Monitor has no independent legal interest of its own in the PJM markets,” the court determined. It characterized the PJM Monitor as “an outside observer hired to study and report objectively on the market’s operations … not a creature of statute, and operates under no affirmative duty imposed by public law.”

PJM originally asked FERC to dismiss the complaint last May on the grounds that Potomac “lacks the capacity by statute, order, contract or tariff to bring such a complaint in its role as an independent market monitor against PJM.”

CPUC Denies Pipeline, Inquires About Others

By Jason Fordney

The California Public Utilities Commission on Thursday denied a request to build a new natural gas pipeline after questioning Southern California Gas about why other major pipelines have been sitting out of service.

CPUC SDG&E SoCalGas
The CPUC denied a request by San Diego Gas & Electric and Southern California Gas to build a new pipeline | © RTO Insider

The commission rejected an application by San Diego Gas & Electric and SoCalGas to build a $639 million pipeline that would have stretched from Rainbow Station to Miramar, replacing the current Line 1600 built in 1949.

“The CPUC determined that the utilities’ most recent natural gas supply forecast and the CPUC’s reliability standard for gas planning do not demonstrate that there is a need for the proposed pipeline,” the commission said as it approved its proposed decision.

The commission directed SDG&E and SoCalGas to pursue other supply options for smaller amounts and for shorter periods of time than would have been provided by the proposed pipeline near San Diego. It also directed the utilities to ensure the safe continuing operation of Line 1600.

The applicants had said the sole purpose of the line was not to meet any short-term supply deficits but for emergency situations such as unplanned outages on Line 3010 or at the Moreno substation. They had also proposed derating Line 1600 from transmission service to distribution service.

The commission last week asked SoCalGas why it had not restored to service two pipelines, Line 3000 and Line 235-2. Line 3000 went out of service on July 29, 2016, and Line 235-2 ruptured and exploded on Oct. 1, 2017.

CPUC SDG&E SoCalGas
California Public Utilities Commissioners left to right: Martha Guzman Aceves, Carla Peterman, Chairman Michael Picker, Liane Randolph, Clifford Rechtschaffen | © RTO Insider

“Though such outages are to be expected periodically, the significant volumes associated with these facilities and the fact they have been out for lengthy periods during peak demand periods — nearly two years for one and over eight months for another — are causes for concern,” CPUC Energy Division Director Edward Randolph told SoCalGas President Bret Lane in a June 18 letter. Randolph questioned whether rates should be reduced if the lines are not providing benefits to ratepayers.

The Energy Division also issued a new report that cited the pipeline outages as a main reason it is recommending an increase in the allowed storage level at the Aliso Canyon facility from 24.6 Bcf to 34 Bcf. Comments on the proposal were due Monday.

Last month, the commission allowed SoCalGas to increase gas injections into Aliso Canyon but denied a request to increase the allowable capacity. (See CPUC OKs Temporary Increase in Aliso Canyon Injections.)

SPP: No Need for Joint Study with AECI in 2018

SPP staff told stakeholders last week that the RTO will not conduct a joint transmission planning study with Associated Electric Cooperative Inc. this year, saying they were unable to find any “reasonable projects on either side of line.”

spp aeci joint transmission planning study
Savoy | © RTO Insider

“The next shot will be in 2020,” said SPP’s Clint Savoy during a June 21 conference call of the SPP-AECI Interregional Planning Stakeholder Advisory Committee. “We will have plenty of time to get our hands around what we want to look at in the next study.”

A needs assessment along the seams identified more than 200 violations, but most were eliminated through model corrections or system adjustments, or because they were invalid contingencies. Most AECI violations were voltage issues, SPP said.

The RTO is proposing that one identified project, a 161-kV transmission line, be included in its 2018 near-term assessment.

A final report will be published at the end of July.

SPP and AECI have been performing joint studies every other year since 2010, as outlined in their joint operating agreement. Their only success was in 2016, when their study identified two projects near Springfield, Mo.: a new 345/161-kV transformer at AECI’s Morgan Substation and uprate to an existing 161-kV Morgan-to-Brookline transmission line, and installation of a new 345-kV 50-MVAR reactor at City Utilities of Springfield’s existing Brookline substation.

spp aeci joint transmission planning study
New Madrid Power Plant transmission lines | AECI

SPP would have been responsible for $17.1 million of the projects’ estimated $18.75 million cost, but FERC last year rejected the proposed cost allocation for both projects. The Brookline reactor project is now being addressed through the RTO’s regional planning process as part of the 2018 near-term assessment, and the Morgan transformer project is being prepared for another filing at FERC.

spp aeci joint transmission planning study
| SWEC

AECI, based in Springfield, is owned by and provides wholesale power to six regional generation and transmission cooperatives.

— Tom Kleckner

NYISO Business Issues Committee Briefs: June 20, 2018

RENSSELAER, N.Y. — NYISO power prices dropped in May but are up 37% year-to-date, Nicole Bouchez, ISO principal economist, told the Business Issues Committee on Wednesday.

Prices averaged $28.78/MWh in May, lower than $35/MWh in April and $31.74/MWh the same month a year ago.

Year-to-date monthly energy prices averaged $50.20/MWh through May, up from $36.54/MWh a year earlier. May’s average sendout was 397 GWh/day, compared with 390 GWh/day in April and 383 GWh/day a year earlier.

Transco Z6 hub natural gas prices averaged $2.55/MMBtu for the month, down 9.4% compared with last month and 8.8% year-over-year.

Distillate prices gained 6.4% compared to the previous month but were up 49.7% year-over-year. Jet Kerosene Gulf Coast and Ultra Low Sulfur No. 2 Diesel NY Harbor averaged $15.96/MMBtu and $15.92/MMBtu, respectively.

nyiso fixed price transmission congestion contracts
| NYISO

Total uplift costs and uplift per megawatt-hour rose from April with the ISO’s local reliability share 22 cents/MWh in May, up from 12 cents/MWh the previous month, while the statewide share climbed from -57 cents/MWh to -17 cents/MWh.

ISO Reviewing Rules on PJM Imports

Reviewing the Broader Regional Markets report, Bouchez described the ISO’s work on item 26, an effort to clarify the minimum deliverability requirements for capacity from PJM, the subject of three joint meetings of the Installed Capacity (ICAP) Working Group and Market Issues Working Group since February.

The ISO has prepared a detailed overview of the supplemental resource evaluation (SRE) process for external resources, the existing nonperformance penalties for external ICAP suppliers, and a draft proposal regarding SRE process improvements for external capacity resources.

Bouchez also reviewed item 28, a complaint filed with FERC in December by the New Jersey Board of Public Utilities challenging PJM’s and NYISO’s implementation of the mutual benefits provisions of their joint operating agreement and requesting amendments to the JOA.

FERC rejected the complaint on May 24 (EL18-54). The commission found that because the Bergen-Linden Corridor Project was planned by PJM, and without a voluntary commitment to share cost responsibility by NYISO, “it is just and reasonable for the costs of the project to be allocated solely within PJM.” (See PSE&G on the Hook for Bergen-Linden Costs.)

Proposal to Extend TCCs Advances

The BIC voted to recommend that the Management Committee approve Tariff revisions to provide extensions of historic fixed-price transmission congestion contracts (HFPTCCs), following a presentation by Gregory R. Williams, manager for TCC market operations.

FERC Order 681 requires that long-term firm transmission rights be made available to allow load-serving entities to support long-term power supply arrangements.

The HFPTCCs initiated by NYISO in 2008 allow LSEs to obtain such contracts for up to 10 years, with some service grandfathered for up to 12 years; 1,748 MW of HFPTCCs are currently active. Those offered in 2008 are now approaching the end of their 10-year term and will expire after Oct. 31.

As part of developing the HFPTCCs, the ISO had committed to explore an option to renew the contracts after the initial term.

Contract extensions would be made available to LSEs that convert existing transmission agreements to HFPTCCs and continued to purchase them throughout the entire 10- or 12-year term.

The ISO is required to make all transmission capacity not used to support existing TCCs available for sale in its centralized TCC auctions. The bidding and offering period for the first round of the fall 2018 centralized TCC auction is expected to begin in mid-August.

Assuming the current proposal is accepted by FERC, the ISO would need to seek a waiver for permission to reserve 256 MW of transmission capacity from the upcoming auction to support the potential award of HFPTCC extensions that would begin on Nov. 1, 2018, and ensure feasibility issues do not arise from offering such extensions to qualifying LSEs.

Michael Kuser

CORRECTED: FERC Seeks More Info on CPV Plant’s Ownership

By Rory D. Sweeney

Competitive Power Ventures must provide additional information to prove it adequately mitigated market power to continue making market-based sales at its newly opened Towantic Energy Center, FERC ruled Thursday (ER13-343-008, et al.).

FERC’s ruling came in response to CPV’s triennial market power update, which it filed on June 30, 2017, for Towantic, a 785-MW generator in Oxford, Ct., and three other gas-fired plants in CPV’s Northeast region.

CPV FERC pension funds
CPV Towantic Energy Center in early May, with construction nearly complete. | CPV

The commission’s market-based rate rules require applicants to provide information regarding affiliates and upstream ownership. It considers as affiliates any entity that owns at least 10% of the outstanding voting securities of the applicant.

Two pension funds indirectly own more than 10% of Towantic, but CPV argued that they are only allowed to vote 9% of their shares in an upstream entity. FERC said that doesn’t account for their entire ownership.

“Because the pension funds are included among the stockholders whose votes determine how the votes of the excess shares will be allocated, the sum of votes by the pension funds of their 9% of the shares plus the proportional vote of their excess shares gives the pension funds an effective vote greater than 10%,” the commission said.

It instructed the applicants to update their horizontal and vertical market power analysis with their affiliates’ generation and transmission assets and inputs to electric power production. FERC gave them 30 days to comply.

The updated market power analysis included Towantic and the 680-MW CPV Valley in Wawayanda, N.Y., both of which began operating this year and were granted market-based rate authority (MBRA) in March 2016 (ER16-700, ER16-701). (See CPV: Subsidies, not Gas Fears, Challenge for New Plants.)

The other plants are the 725-MW CPV Woodbridge Energy Center in Keasbey, N.J., and the 725-MW CPV St. Charles Energy Center in Waldorf, Md., which were granted MBRA in February 2013 (ER13-342, ER13-343).

[Editor’s Note: An earlier version of this story incorrectly stated that FERC was questioning the ownership of all four CPV plants and that they did not already have MBRA.]

FERC Broadens Challenge to TOs’ Tax Calculations

By Amanda Durish Cook

FERC on Thursday identified 13 additional transmission owners it said should change accounting practices that could inflate rates by underestimating tax credits.

The commission ordered a Section 206 proceeding investigating the companies’ use of a double averaging formula to calculate accumulated deferred income taxes (ADIT) (EL18-155, et al.). The utilities include two Ameren subsidiaries, American Transmission Co., GridLiance West Transco, ITC Midwest, Northern States Power, Public Service Company of Colorado, Southern California Edison, TransCanyon DCR, Southwestern Public Service and Virginia Electric and Power Co.

In April, FERC opened a similar investigation of five MISO TOs after rejecting proposed formula rate template revisions that would have applied the two-step averaging methodology in annual true-up calculations of ADIT balances.

The commission signaled it would probe whether the practice makes deferred income tax credits appear lower than they should be, possibly raising rates (ER18-224, EL18-138). The filers were ALLETE, Montana-Dakota Utilities, Northern Indiana Public Service Co., Otter Tail Power and Southern Indiana Gas and Electric Co.

The commission said that the TOs’ practice of averaging the prorated ADIT value for the year with the beginning-of-year ADIT balance “produces a result that is disproportionately skewed towards the beginning-of-year balance.”

“Because most companies tend to continuously make investments in plant[s], which in turn generates ADIT, plant and ADIT balances typically increase throughout the year,” the commission said.

MISO TOs Offer New Formula

On June 4, the five MISO TOs submitted revisions to remove the proposed double averaging and instead apply the IRS’ proration methodology in calculating the annual transmission formula rate true-up.

In last week’s order, FERC suggested that the 13 newly identified utilities would need to similarly revise their rates.

“Upon initial review, the concerns we identify might be addressed by revising respondents’ transmission formula rates to eliminate the use of the two-step averaging methodology to determine ADIT balances,” FERC said. “In particular, respondents could modify their transmission formula rates to apply the first step of the two-step averaging methodology to generate a prorated ADIT value for the year, without taking the second step of averaging the prorated value for the year with the beginning-of-year balance.”

Change of Heart

FERC noted that, in previous proceedings, it had allowed TOs to use the two-step methodology “based on the understanding that this methodology was necessary to comply” with the IRS’ normalization rules, an accounting system the Department of Treasury uses for regulated public utilities to reconcile accelerated depreciation of their public utility assets or investment tax credits with regulatory treatment.

However, FERC said in April that its opinion on the matter has since changed, guided by private letter rulings from the IRS. FERC said it now interprets updated IRS rules to “not require that any averaging convention applied to other elements of rate base also apply to taxpayer’s prorated [ADIT] balance.”

“We conclude that if the IRS’ proration methodology is applied to calculate ADIT balances in forward-looking formula rates — such as the Attachment O formula rate templates of certain MISO TOs — then the additional averaging step need not also be applied in order to comply,” FERC said.

NYISO BIC Backs AC Tx Projects; Losing Bidders Protest

By Michael Kuser

RENSSELAER, N.Y. — NYISO stakeholders last week backed joint proposals by North America Transmission (NAT) and the New York Power Authority to build two 345-kV transmission projects while several losing bidders cried foul.

In an advisory vote, the Business Issues Committee urged the Management Committee on Wednesday to recommend the Board of Directors approve the ISO’s draft AC Transmission Public Policy Transmission Planning Report. Dawei Fan, manager for public policy and interregional planning, said the report contains analysis of seven proposals to address persistent transmission congestion at the Central East (Segment A) electrical interface and six proposals for the Upstate New York/Southeast New York (UPNY/SENY, or Segment B) interface.

NYISO BIC North American Transmission NYPA
NYISO staff analyzed seven proposals to address persistent transmission congestion at the Central East (Segment A) electrical interface, and six proposals for the Upstate New York/Southeast New York (UPNY/SENY, or Segment B) interface. | NY PSC

Advised by consultant Substation Engineering Co. (SECO), ISO staff recommended two 345-kV transmission projects proposed jointly by NAT and NYPA. The BIC voted 76.33% in favor of the report and its recommendations.

Project T027 is a double-circuit 345-kV line from Edic to New Scotland for Segment A. Project T029 for Segment B is a standard 345-kV line from Knickerbocker to Pleasant Valley.

NYISO’s analysis was driven by a December 2015 order by the New York Public Service Commission on “Finding Transmission Needs Driven by Public Policy Requirements.”

T027 had higher costs than other Segment A proposals, but staff determined them warranted by benefits provided by the double-circuit design, including “significant increase in Central East voltage transfer capability, increased production cost savings, and excellent operability and expandability.”

T029 provides similar transfer incremental and production cost savings with the second-lowest cost, and demonstrates excellent operability, staff said. More important, the report said, “T029 poses the lowest siting risk due to the low structure height increase and more than 50% of its new structures with reduced height.”

Staff also said that T027 and T029 would result in cost savings when being built by the same developer simultaneously.

The ISO estimated T027 will cost $577 million to $750 million, the higher figure including a 30% contingency. T029 is estimated at $324 million to $422 million. Staff projected the in-service date for the selected projects in April 2023, “assuming the developer will start the Article VII preparation immediately following the approval of this report by the NYISO board.”

Challenges to Planning Process

Stakeholders abstaining or opposing the motion June 20 included utilities, transmission owners and other developers whose proposals were not selected for recommendation. Several of them submitted comments to the BIC or read statements.

John Borchert, senior director of energy policy and transmission development for Central Hudson Gas & Electric, which abstained, said his company wanted the benefits of improved transmission capability for its service area but was “dissatisfied with the NYISO’s work and its project evaluation.”

He said “the lack of transparency, the way that the aspects of the projects were treated during the evaluation, effectively disqualified projects, and the way that the local TO upgrades were handled during the process have led to frustration and confusion for both those developing projects and for those interconnecting transmission owners.”

Consolidated Edison and its subsidiary Orange and Rockland Utilities voted against the motion, and O&R submitted written comments.

“We don’t feel confident that the recommended selection for Segment B is in the customer’s best interest due to a lack of transparency in the selection process, and deficiencies in evaluation,” said Jane Quin, director of Con Ed’s energy markets policy group. “We are concerned that … NYISO has not considered the full costs associated with the proposed Middletown upgrades, which are local upgrades on the Orange and Rockland system … and could cost as much as 20% of the Segment B project cost.”

The ISO “failed to make clear the technologies and project attributes it would or would not consider, and the reasons for such decisions, and it did not consider stakeholder input on the matter,” Quin said.

Fan responded that the Middletown transformer “is just one of the distinguishing factors for Segment B projects … [for which] the major drivers are the magnitude of the power delivery and the structure design.” He said SECO had included $16 million for the Middletown transformer costs, which it deemed adequate.

Fan said the ISO had already had two meetings with developers and six meetings with the Electric System Planning Working Group and Transmission Planning Advisory Subcommittee to consider comments from stakeholders.

Looking for Fatal Flaws

Zach Smith, NYISO vice president for system and resource planning, noted that “any project recommended for selection does go through our interconnection process … there has been a system impact study that’s been done that’s up at [the Operations Committee] tomorrow for consideration.”

The next step after that is a facilities study, and “what’s key here to our evaluation is to understand whether there are any fatal flaws in our assessment,” Smith said.

Borchert said, “There was no reason why an interconnecting transmission owner should not be consulted if these solutions are talking about equipment that’s going to be installed in their service territory. And the process needs to be done if it’s part of the overall selection and it has an impact on the selection, and it needs to be done prior to the selection being made.”

Carl Patka, the ISO’s assistant general counsel, said, “When we designed the overall planning process, we did not require, and FERC did not approve requiring, a complete interconnection-level analysis for proposed projects. That was proposed during the Order 1000 process, it was proposed during the stakeholder process, and it was rejected. And the reason for that is people did not want to create a barrier to entry and proposal of new projects based upon information that competing developers could not have from the incumbent utility.”

Brian Duncan of NextEra Energy Transmission NY (NEETNY) made a presentation arguing that NYISO was picking winners for a $1 billion project “despite a virtual tie on project benefits” among competing projects, which included NEETNY’s T022 in Segment B.

The ISO “did not provide analysis on cost-contained pricing … and three other project combinations that are virtually identical, provide all the quantifiable and quantitative benefits [and] are within 1 to 5% of the cost estimate using SECO’s numbers,” Duncan said. He also questioned why NYISO made tower height a big issue in its selection when its solicitation made no mention of the factor.

Patka said the PSC order did not mandate the ISO to use cost-contained pricing but required developers to provide two sets of costs, “one based on raw construction costs and one on 80%/20% cost overrun/cost underrun language. … They said they hoped that FERC will adopt cost containment when they address the rate issue, but their words were exactly, ‘The NYISO should evaluate the costs based on raw construction costs.’”

Patka also said that tower heights were considered by NYISO as a risk of project delay and to project completion, as visual impact is a key environmental impact of transmission, and that the ISO had reviewed its analysis with New York Department of Public Service staff.

Duncan also took issue with the concrete pole installation cost estimates, saying that SECO used a metric of dollars per pound on the weight of the pole rather than a more logical figure of total costs, including labor. He also said the ISO’s estimate of 5% in synergy savings on the combined projects by one developer was “overstated.”

“If those issues are addressed, project T022 would be the lowest-cost project by millions of dollars, probably tens of millions of dollars,” Duncan said.

SECO Vice President Joe Allen said he agreed “there would be no synergy” between the two upgrades.

Smith said NYISO could “take that back, but it won’t affect the ranking at all.”

Kathleen Carrigan, New York Transco general counsel, read comments the company jointly submitted with National Grid.

NYISO BIC North American Transmission NYPA
Losing bidders cried foul last week over NYISO’s selection of North America Transmission and the New York Power Authority to build two 345-kV transmission projects to address public policy needs identified by the New York Public Service Commission. | NYISO

The two companies submitted proposal T019 for Segment B, including “a basic controllable series compensation element to preserve the proposed 345-kV transmission line physical designs that the commission deemed the most environmentally and siting friendly in the underlying AC transmission proceedings.”

Carrigan said series compensation technology is widely used across the U.S., and she submitted a study showing no detrimental system impacts from it. NYISO and SECO “considered proposal T019 as too risky due to the inclusion of the series compensation, despite no technical analysis in support of their conclusion,” she said.

Smith said that while the ISO does not oppose the use of series compensation as a technology, it did see potential problems with its application in the National Grid/NY Transco project. In a FAQ document posted with the BIC meeting materials, the ISO cited potential subsynchronous resonance and damage to generators as the major risk of series compensation technology.

Carrigan said NYISO’s own metrics show the National Grid/NY Transco proposal paired with T029 produces consistently better performance results than the ISO’s favored project.

For example, when combined, T027 and T019 increase voltage transfer across Central East by 875 MW and UPNY/SENY by 2,100 MW. “This is a far greater increase than the combination of T027 and T029, which only increases transfer capability along Central East by 825 MW and UPNY/SENY by 1,325,” she told RTO Insider after the meeting.

“Projects T027 + T019 have the highest Central East N-1-1 voltage transfer capability of any studied project combination and far surpass combination T027 and T029 with respect to the incremental UPNY/SENY N-1-1 thermal transfer capability. The baseline 20-year incremental energy produced by projects T027 and T019 nearly doubles that of projects T027 and T029 (40,089 GWh vs. 27,524 GWh); and finally, T027 and T019 produce the highest production cost savings than any other Segment B combination,” Carrigan said.

Monitor Garza Offers Glimpse of ERCOT in 2018

By Tom Kleckner

HOUSTON — While sharing her organization’s report on the state of the ERCOT market in 2017 last week, Potomac Economics’ Beth Garza was naturally asked her forecast of this summer’s energy prices.

ercot market monitor beth garza
Garza | © RTO Insider

“My title is not market predictor. It’s market monitor,” Garza, director of ERCOT’s Independent Market Monitor, reminded her luncheon audience June 21. “I get to watch and opine. I’m sorry to disappoint you.”

Speaking to those gathered at the Gulf Coast Power Association’s lunch in Houston, Garza shared highlights from the State of the Market report. Energy insiders listened attentively as she reviewed 2017 data — and even more so on the rare occasions Garza looked ahead to 2018.

Garza said reserve margins will be tighter this summer than last year, primarily because of the retirement of 4.2 GW of coal generation over the last 12 months. That dropped ERCOT’s planning reserve margin from 18.9% to 9.3% — since increased to 11% — and raised fears of potential shortages during a long, hot summer. (See ERCOT Gains Additional Capacity to Meet Summer Demand.) On Friday, as the system flirted with June’s demand record of 67.8 GW, the ISO still had more than 3.5 GW of operating reserves.

“We had an interesting test of the system in May,” Garza said, referring to the multiple demand records ERCOT set for the month in the face of above-normal temperatures. “But as others have said, a hot May does not necessarily portend a hot summer.”

Statewide temperatures have dropped since then, thanks to recent torrential rains. That has also dampened forward prices, which have settled at about $150/MWh after soaring above $250/MWh in May.

ercot market monitor beth garza
| Potomac Economics

“Is that a reaction to the rain and the temperatures?” Garza asked. “We got through May, but the rest of June has not been severe.”

Garza allowed herself some prognostication in addressing the forward prices.

“I can look at future prices and infer an estimate of how many hours of real-time prices at the 9,000/MWh cap we’ll see,” she said, noting ERCOT saw only 3.5 hours of prices above $1,000/MWh last year. Garza recalled a straw poll of attendees at the recent GCPA spring conference, with expectations of five to 10 hours at the $9,000/MWh cap this year.

“That’s what the future pricing seems to indicate, but that’s based on a $200 price. I haven’t done the math on $150 prices,” Garza said. “If we have 2 GW of wind generation on peak, it’ll be a high-priced day. If we have 10 GW of wind generation on peak, it’ll be a moderately priced day.”

ercot market monitor beth garza
Beth Garza discusses the IMM’s 2017 State of the Market Report at GCPA’s June 21st luncheon in Houston. | © RTO Insider

Garza also put in a plug for the addition of real-time co-optimization in the market, one of six recommendations the Monitor has made in each of its last few reports and one of several market improvements being considered by the Public Utility Commission of Texas. (See “Monitor Says Wholesale Market ‘Performed Competitively’ in 2017,” ERCOT Briefs.)

“It’s the key missing link in our market,” she said. “Our market is dependent on pricing during significant scarcity intervals. My fear is that as we get to where we see tight reserve margins, the likelihood of scarcity events and high prices increase, because of the ineffective allocation of reserves. If they were allocated differently [through real-time co-optimization], we wouldn’t see those high prices.”

NERC: Grid Resilience, Reliability Improved in 2017

NERC: Grid Resilience, Reliability Improved in 2017

By Rich Heidorn Jr.

The bulk power system showed improved ability to rebound from severe storms last year while continuing to improve on most other reliability metrics, NERC said last week.

NERC cited two Category 5 events — the most severe — last year in hurricanes Harvey and Irma. “While wind and water damage were record setting, the restoration efforts and subsequent recovery times were improved from historical benchmarks,” NERC reported in its State of Reliability 2018 report.

Harvey damaged 85 substations and more than 850 transmission line structures in South Texas, resulting in 225 transmission line outages. But utilities’ use of amphibious vehicles, airboats and aerial drones allowed them to perform damage assessments even before roads were clear of flooding and storm debris, NERC noted.

Irma caused a record number of electric outages in Florida, with 4.45 million customers losing power in Florida Power & Light’s territory, up from 3.24 million from Hurricane Wilma in 2005. But system hardening between the two storms reduced restoration time to 10 days from 18, NERC said.

The report recommended NERC encourage increased use of mutual assistance programs and drones and increase information sharing by publishing event reports and conducting other outreach on the lessons learned from the storms.

The storm observations were among six findings in the NERC report. The organization also found that:

The report said the only metric “indicating cause for concern” is planning reserve margins, with all regions except for the Texas Regional Entity projecting sufficient reserves for the next five years.

It cited ERCOT’s preliminary summer seasonal assessment of resource adequacy (SARA), which reported that operational tools such as load management and distribution voltage reductions could be needed to maintain sufficient operating reserves.

In its final SARA for summer, ERCOT reported that its anticipated resources had increased by 581 MW, NERC noted. (See ERCOT Sees Enough Generation Through 2022, 73-GW Peak for Summer.)

FERC Denies WestConnect’s Order 1000 Rehearing Request

By Tom Kleckner

FERC last week denied a rehearing request of its November 2017 order on remand regarding transmission cost allocation in the WestConnect planning region. WestConnect’s transmission providers requested the rehearing in December after FERC affirmed its original order in the proceeding (ER13-75-012).

In 2016, the 5th U.S. Circuit Court of Appeals remanded a commission order rejecting the utilities’ Order 1000 compliance filing.

Western U.S. transmission lines | Southwire

The utilities’ initial compliance filing included a provision stipulating that costs for projects selected in a regional plan would be allocated only to beneficiaries who agreed to participate in those projects. Other WestConnect members participating in the planning process would not be obligated to pay for those projects’ costs, a measure designed to avoid discouraging nonpublic utility transmission providers from participating in planning.

FERC found that WestConnect’s “non-binding” process did not comply with Order 1000, which prohibits planning participants from claiming an exemption from cost allocation merely by asserting they receive no benefits from the resulting infrastructure. The commission noted that the “fundamental driver” of Order 1000 was to minimize “free ridership” within the system.

westconnect ferc order 1000
WestConnect Planning Region | WestConnect

The court asked FERC for “additional factual findings” on WestConnect’s planning process, saying the commission’s mandates regarding the role of nonpublic utility transmission providers were arbitrary and capricious and that it had not shown its orders would not produce unjust rates.

FERC’s November order upheld the original ruling and added further explanation of its reasoning. (See FERC Affirms WestConnect Cost Allocation Ruling.)

The WestConnect transmission providers argued the order on remand did not address deficiencies identified by the court and therefore violated “both the express purpose of Order No. 1000 and the principle of cost causation under the Federal Power Act.”

FERC countered that the rehearing request relied primarily on WestConnect’s free-rider argument, and it said that its order on remand explained “at length” why the commission often “expects nonpublic utility transmission providers will accept allocation of the costs of transmission projects that benefit them (i.e., they will pay their share of the costs of those projects), and why any potential free ridership would occur for only a limited subset of transmission projects.”

“We continue to expect that free ridership in the WestConnect region will be limited, and we note that the complete elimination of free ridership is not required by the just and reasonable standard of the FPA or Order No. 1000,” FERC said.

The commission said attempts to eliminate free ridership “may not be feasible” given the region’s “uniquely integrated nature” and the fact that Order 1000’s requirements do not apply to nonpublic utility transmission providers. The group’s planning region covers Arizona, California, Colorado, Nevada, New Mexico, South Dakota, Texas and Wyoming.

“We continue to believe that the approach to regional transmission planning and cost allocation accepted in the compliance orders and order on remand is consistent with Order No. 1000 and will result in just and reasonable rates while taking into account the unique characteristics of the WestConnect region,” FERC said.