Search
`
November 5, 2024

FERC Ties up Loose Ends in NJ Merchant Tx Saga

FERC on Thursday confirmed its denial of requests to change two merchant transmission facilities’ interconnection agreements, rejecting requests to rehear the orders (ER17-2073, ER17-2267).

But the commission’s procedural rulings were moot because it granted Hudson Transmission Partners and Linden VFT the substantive relief they sought nearly a year ago.

Linden VFT’s exterior | Joseph Jingoli & Son

Hudson and Linden had sought to amend their facilities’ interconnection service agreements (ISAs) to downgrade their combined 1,003 MW of firm transmission withdrawal rights, which include the right to schedule energy and capacity withdrawals from the PJM system, into non-firm transmission withdrawal rights that only include the right to schedule energy.

Citing transmission owner Public Service Electric and Gas’ opposition to the changes, FERC rejected them, saying PJM’s Tariff doesn’t allow it to alter agreements without approval of all the signatories. But the commission also initiated a Section 206 investigation of the Tariff language that required it to deny the requests. (See Rejecting PJM ‘Wheel’-related Requests, FERC Sets Inquiry.)

That investigation led the commission to rule last December that the Tariff language was unjust and unreasonable and that the facilities should have the ability to unilaterally change from firm to non-firm rights. (See NJ Merchant Tx Operators Win Relief on Upgrade Costs.)

In the interim, Linden and Hudson had filed for rehearing. In Thursday’s ruling, FERC stuck with its original reasoning rejecting arguments that the revisions were “a nonsubstantive change … akin to other ministerial amendments PJM regularly files unexecuted.”

There was no doubt that the switch to non-firm service was substantive, as they determined whether Hudson and Linden would be on the hook for the roughly $653 million in costs PJM allocated to them for upgrades to PSE&G’s transmission system.

— Rory D. Sweeney

FERC Rejects NESCOE Request on Scarcity Rules

By Rich Heidorn Jr.

FERC on Thursday rejected a request by the New England States Committee on Electricity to broaden the commission’s February ruling raising ISO-NE’s peak energy rent (PER) adjustment. The commission also approved the RTO’s compliance filing in the matter (EL16-120, ER17-2153, ER18-1153).

The commission had approved an uncontested settlement that resolved issues it set for hearing in 2017 after finding that the PER mechanism had become unjust and unreasonable because of the interaction between the mechanism and higher reserve constraint penalty factors (RCPF). The settlement covered the period of Sept. 30, 2016 — the date of the initiating complaint by the New England Power Generators Association — through May 31, 2018, the last day of the capacity commitment period for Forward Capacity Auction 8. (See FERC OKs Settlement on ISO-NE Scarcity Rules.)

The Feb. 20 order noted the settling parties did not agree on the application of the revised strike price methodology to FCA 9, the capacity commitment period beginning June 1, 2018.

NESCOE supported the adjusted PER strike price but protested continued use of the methodology after May 31. It asked FERC to require ISO-NE to reinstate, effective June 1, 2018, the method it used to calculate the PER strike price before the settlement period.

NESCOE said the settlement order did not address the circumstances when a PER event occurs prior to May 31, 2018. But because of the 12-month rolling average used in the PER calculation, such an event would affect ISO-NE’s calculation of the PER credit against the monthly payment that load must make to capacity resources after that date, NESCOE said.

The organization said the new methodology should not apply for FCA 9 because the auction was held in February 2015 — after the RCPFs were increased, which allowed resources to reflect the change in their supply offers.

NEPGA countered that NESCOE’s position “would deny capacity suppliers the full extent of the relief granted by the commission.”

The commission said NESCOE’s request would require Tariff changes under Federal Power Act Section 205 or 206 and was beyond the scope of the proceeding.

“NESCOE’s request would, in effect, mean that the PER payments to load (i.e., the credit against the monthly payment that load must make to capacity resources that is associated with PER events) starting on June 1, 2018, would be calculated as if each monthly PER amount for the 12-month averaging process were calculated using the original PER strike price for the Sept. 30, 2016, to May 31, 2018 period.”

FERC previously agreed to eliminate the PER adjustment effective with the capacity commitment period beginning June 1, 2019 (ER17-2153, EL16-120). ISO-NE said its Pay-for-Performance program and changes to the day-ahead energy market made the adjustment unnecessary beyond that date.

FCA 8 Challenge Rejected

In another ISO-NE ruling, FERC rejected as untimely a 2015 protest by the Utility Workers Union of America Local 464 (UWUA) over the results of FCA 8, which the union claimed was tainted by Energy Capital Partners’ decision to close its Brayton Point generating plant.

The Brayton Point Power Station in Somerset, MA went offline in June 2017.

In September 2014, the commission split 2-2 over whether it should reject the results from FCA 8 because of unchecked market power, allowing the 2017/18 auction results to become “effective by operation of law” (ER14-1409).

UWUA’s protest said the commission should have revisited the issue after it added a fifth commissioner able to break the 2-2 deadlock.

But the commission said protests were required to be filed by April 14, 2014, and that when the union filed its protest, FCA 8 was no longer pending.

FERC noted that it had rejected UWUA’s similar challenges to the results of FCA 9 and 10 after a nonpublic investigation that “found credible justifications for the owners’ retirement decision.” It also noted that its rulings were upheld on appeal in July. (See D.C. Circuit Dismisses Union Challenges to FCA Results.)

FERC Walks Back Salem Harbor Manipulation Case

By Rich Heidorn Jr.

In a stunning turnaround, FERC’s Office of Enforcement on Wednesday urged the commission to withdraw its Order to Show Cause alleging that the operators of the Salem Harbor Power Station misled ISO-NE with supply offers it could not meet because of insufficient fuel.

Enforcement litigation staff made the unusual recommendation based on Footprint Power’s Aug. 2 response to the order, which argued that Enforcement had overstated what ISO-NE expected from Salem Harbor Unit 4. (See Salem Harbor Operator Seeks Dismissal of ‘False Offer’ Case.)

Salem Harbor Power Plant | Tetra Tech

The Office of Enforcement’s June 18 show cause order said Footprint Power should forfeit more than $2 million in capacity payments Unit 4 received for a period in June and July 2013 during which the plant’s fuel supply prevented it from operating at its offered capacity. It also sought $4.2 million in civil penalties.

But in its new filing, staff said it was persuaded by new arguments that the commission had failed to consider the 17.5 hours that it took Salem Unit 4 to reach full output from a cold start (IN18-7).

“Although staff disagrees with most of the arguments that Footprint raises, staff finds merit in Footprint’s new defense relating to the start-up requirements of [Unit 4]. In consideration of that argument — one which Footprint had not fully raised … staff agrees with Footprint that its conduct during the June 27 through July 17, 2013, portion of the relevant period (i.e., June and July 2013) does not violate the four Tariff provisions and regulations at issue here.

“Staff still believes that Footprint violated those four Tariff provisions and regulations during the remaining portion of the relevant period, when Footprint submitted day-ahead limited energy generator (LEG) offers from July 18 to July 25, because the start-up requirements comprising Footprint’s new defense do not apply then.”

Enforcement recommended the commission vacate the Order to Show Cause and not assess a penalty or further pursue the matter because the reduced scope of the violations lessened the impact on the market.

“The extent of harm that resulted from Footprint’s conduct is uncertain but likely limited. Moreover, Unit 4 was retired in 2014 and has since been demolished. It is being replaced by a new modern gas plant. Consequently, this specific conduct (i.e., misrepresentations about how much fuel is in the tank) will not recur. For all of these reasons, staff does not believe that pursuing the case further is a prudent use of the staff’s resources.”

Footprint’s lead attorney, John N. Estes III of Skadden, Arps, Slate, Meagher & Flom,  said his client was “gratified” by FERC’s change of heart.

“We trust that the commission will act promptly to follow Enforcement staff’s recommendation and finally end this groundless and stale set of allegations,” he said.

Hearing Set for Louisiana’s Entergy Grand Gulf Complaint

By Tom Kleckner

FERC on Thursday established hearing and settlement procedures for a Louisiana Public Service Commission complaint against two Entergy subsidiaries (EL18-152).

The PSC alleged in a Section 206 complaint filed in May that System Energy Resources Inc. (SERI) and Entergy Services violated the filed-rate doctrine and FERC’s ratemaking and accounting requirements by billing ratepayers for the costs of the Grand Gulf Nuclear Power Station’s sale-leaseback renewals under a unit-power sales agreement between SERI and Entergy’s Arkansas, Louisiana, Mississippi and New Orleans operating companies.

Grand Gulf Nuclear Station | Entergy

FERC found the PSC’s complaint “raises issues of material fact that cannot be resolved based upon the record before us” and would be more appropriately addressed in settlement procedures. The commission set a refund date of May 18, 2018.

Louisiana’s regulators requested the hearing and asked that unjust and unreasonable costs be removed from billings.

The PSC’s complaint stemmed from SERI’s renewal of two sale-leaseback agreements in 2015 that dated back to 1988. The regulators said SERI originally sold to private-equity investors an 11.5% interest in Grand Gulf for $500 million and leased it back for 26.5 years. They said the original cost of the lease was $435 million with a net book value of $398 million, claiming SERI included the costs in its formula rate as rents for ratemaking purposes.

Galvez Building housing the Louisiana Public Service Commission | LA.gov

The PSC said SERI paid off the $500 million principal balance over the leaseback terms, which ended July 15, 2015, but ratepayers paid all of the costs except for an $11 million net-of-tax gain credited in rates pursuant to a 1991 settlement. SERI recovered $489 million plus interest paid to the lessor through its formula rate expense, more than the $398 million book value, the regulators said.

The PSC further argued that SERI double recovered the sale-leaseback costs by making capital additions to the 11.5% interest and separately charged ratepayers a return. SERI’s fair market value lease renewal cost of $17.2 million/year, which SERI has included in rates as rents since 1995, “constitutes double collection of the capital addition costs,” the PSC said. It asked FERC to exclude the lease payments from rates and to order refunds from the time of the sale-leaseback renewal or order another ratemaking adjustment.

The Louisiana regulators also asked the commission to investigate and ensure that consumers receive the entire benefit of a litigation payment SERI received for the Department of Energy’s failure to dispose of Grand Gulf’s spent nuclear fuel.

SERI, a wholly owned subsidiary of New Orleans-based Entergy, generates and sells nuclear power, primarily through its 90% ownership and leasehold interest in Grand Gulf. Entergy Services is a service subsidiary that provides accounting, legal, regulatory and other services to Entergy’s operating companies.

Ailing McIntyre Absent from FERC Open Meeting

By Michael Brooks

WASHINGTON — FERC Chairman Kevin McIntyre was absent from the commission’s monthly open meeting Thursday, citing his recovery following surgery for a brain tumor and a fall.

Commissioner Neil Chatterjee, who chaired the meeting, opened by reading a statement in which McIntyre apologized for his absence.

“I had fully intended to be present. However, my ongoing recovery prevents me from being here in person today,” McIntyre said.

FERC Open Meeting Kevin McIntyre
FERC Chairman Kevin McIntyre, with spokeswoman Mary O’Driscoll, speaks with reporters after July’s commission meeting. © RTO Insider

“While my health situation has impacted my mobility, it has not impacted my ability to get the commission’s work done,” he added, citing 151 orders since the July open meeting, an agreement with the Pipeline and Hazardous Materials Safety Administration over LNG terminal permitting and the appointment of Administrative Law Judge Stephanie Nagel.

McIntyre also expressed gratitude “for everyone’s concern regarding my ongoing recovery.”

Chatterjee ended McIntyre’s statement with his own comment, saying “I know I speak for my fellow commissioners when I say that we wish the chairman the best in his continued recovery.”

McIntyre revealed in March that he had had surgery for a brain tumor and was undergoing treatment. Shortly before July’s meeting, the chairman disclosed that he had compression fractures in two of his vertebrae, causing severe back pain, and that he had fallen and injured his arm on July 4.

At the July 19 open meeting, McIntyre remained seated throughout, and it was apparent that he was in pain. (See “McIntyre Toughs it out,” FERC Says Farewell to Powelson.) The commission does not meet in August.

McIntyre also was absent at the commission’s annual reliability technical conference July 31.

On Sept. 11, FERC posted an episode of its “Open Access” podcast, in which McIntyre said he was “well on the mend, and I’m feeling better every day.”

“I also am happy to report that I have continued to work full steam ahead with my colleagues, my personal staff and the commission’s professional staff to ensure that the commission’s work continues unabated. In fact, the August break wasn’t much of a break.”

However, sources have told RTO Insider that the chairman is often absent from FERC headquarters and that meetings with him have been frequently rescheduled as a result.

When asked how often McIntyre has been coming into headquarters for work, FERC spokeswoman Mary O’Driscoll said Thursday, “I can’t answer that; I don’t know.” She was incredulous when asked whether the chairman had considered resigning because of his health issues. “What? Where is that coming from? No. I don’t know. No.”

Another spokesman, Craig Cano, declined to comment.

In another departure from normal proceedings, the commission did not hold a press conference after the meeting. Despite being repeatedly asked, O’Driscoll refused to give reporters a reason for this.

“From time to time we do not have briefings. So it’s not breaking with tradition. I’ve been here 11 years, and I’ve done it at least once with each chairman I’ve served. … I don’t know why you’re making a big deal about this. No briefing. OK?”

FERC, PHMSA See Faster LNG Permitting Under Agreement

By Rich Heidorn Jr.

FERC and the Pipeline and Hazardous Materials Safety Administration on Thursday celebrated their agreement to coordinate the siting and safety reviews of LNG export facilities, saying their Aug. 31 memorandum of understanding will speed the process and make it easier for applicants.

FERC has authority under the Natural Gas Act for authorizing LNG terminals while the Department of Transportation’s PHMSA is responsible for establishing minimal safety standards under the Pipeline Safety Act of 1979.

James Danly, FERC General Counsel (left) and PHMSA Administrator Howard Elliot | © RTO Insider

In the past, FERC staff made preliminary determinations on whether a proposed LNG project could comply with DOT standards, FERC General Counsel James Danly said during a briefing at Thursday’s open commission meeting. But he said the process became problematic with the growing number of applications for LNG export terminals, which are more complex than import facilities.

“This required an extremely iterative process with multiple requests for information from the applicants and back and forth with PHMSA. The MOU that we’ve just signed is going to end that duplicative and iterative process, and now … the experts on this subject — PHMSA — are going to be the ones who make that preliminary determination,” Danly said.

The agreement should allow FERC to accelerate its review on a dozen pending applications, Danly said, “potentially allowing FERC to act by early 2020 on projects capable of exporting over 8 Tcf per year.”

“The numbers involved in the LNG industry are astounding,” said PHMSA Administrator Howard Elliott, who also appeared at the meeting. “A single export facility can deliver an economic impact of $10 billion or more per year, and strong demand from the Asia-Pacific region looks to likely drive those numbers higher over time.”

Commissioner Neil Chatterjee praised the agreement but said FERC should do more, suggesting the commission consider adding a regional office in Houston and boost salaries to make them competitive with industry “to improve retention and recruiting of top-tier engineers and attorneys.”

The U.S., which last year became a net exporter of natural gas, is shipping gas to more than 25 countries, largely through its two operating LNG export terminals, Cheniere Energy’s Sabine Pass in Louisiana and Dominion Energy’s Cove Point in Maryland. The Department of Energy is considering about 25 applications for LNG exports to countries lacking free-trade agreements with the U.S.

Dominion Energy’s Cove Point LNG terminal is the second operating export facility in the U.S. | Dominion Energy

“If the U.S. can ensure that adequate LNG export infrastructure is in place to meet that demand, it could mean thousands of additional jobs across the U.S.,” Chatterjee said. “But if we miss the window of opportunity because of bottlenecks in FERC’s LNG export facility application review process or because FERC lacks the resources to complete its review process in a timely fashion, those foreign trading partners will be looking elsewhere for their natural gas.”

FERC had announced its plan to reach an agreement with PHMSA in July. (See FERC Teaming up with PHMSA on LNG Applications.)

Although there is a consensus that exporting too much domestic natural gas could expose U.S. consumers, industrial users and electric generators to much higher world prices, there is no agreement on what that tipping point is, or how soon the U.S. could get there. (See Enviros, Industrials Challenge DOE Study on LNG Exports.)

MISO Recommending $3B MTEP 18 Draft Plan

By Amanda Durish Cook

ST. PAUL, Minn. — MISO on Tuesday unveiled an annual transmission plan consisting of 434 transmission projects valued at $3 billion.

This year’s proposal so far contains 85 more projects and about $100 million more in investment than the 2017 MISO Transmission Expansion Plan, which in its final form consisted of 349 projects at $2.9 billion.

MTEP 18 breakdown | MISO

MTEP 18 includes 85 baseline reliability projects at $607 million, 16 generator interconnection projects at $88 million and two transmission delivery service projects at about $290,000. But like last year’s plan, most projects fall under MISO’s “other” designation: those decided on by transmission owners that are not eligible for cost allocation and represent replacement of aging infrastructure, construction because of further reliability needs and modifications made for environmental purposes. The RTO this year is recommending 340 other projects at slightly more than $2.3 billion.

Most expensive MTEP 18 projects | MISO

In-service dates for the projects range from 2018 to 2027. Almost half are transmission line upgrades while 39% are substation projects. New transmission line projects represent just 6% of the projects.

Foxconn and Mackinaw

Among the priciest projects on the MTEP 18 list is the $140 million interconnection to plug Foxconn’s $10 billion plant into We Energies’ network in southeastern Wisconsin. MISO expedited its review of the project in February at the request of developer American Transmission Co. (See MISO Fast-Tracks ATC Foxconn Project Review.)

Aubrey Johnson (left) and Jennifer Curran | © RTO Insider

MISO is setting aside more time to discuss an equally costly project: ATC’s proposal to replace a 138-kV circuit connecting Michigan’s Upper and Lower peninsulas after two submarine cables were damaged in April, most likely by a passing vessel. ATC said one of the cables was rendered permanently inoperable. (See ATC Restores Tx Link Between Michigan Peninsulas.)

MISO Executive Director of System Planning Aubrey Johnson said further stakeholder discussion is needed to explore alternate proposals to the project.

“We expect to have a recommendation prior to December,” Johnson told the System Planning Committee of the Board of Directors during a Sept. 18 meeting.

TMEPs on the Way?

MISO executives said their final MTEP recommendation could contain targeted market efficiency projects (TMEPs), a smaller interregional project category MISO and PJM created in 2017. The RTOs are currently conducting a TMEP study and plan to submit project recommendations for approval by their respective boards in October. (See MISO, PJM Plan 2 Studies for Seams Projects.)

Market Congestion Planning Study

This year’s market congestion planning study identified three projects for possible MTEP inclusion: the $11 million rebuild of a 161-kV line in southern Minnesota; a $2 million, 138-kV reactor project in eastern Wisconsin; and a $16 million upgrade to a 161-kV line in southwestern Indiana. None of the projects passed MISO’s 345-kV threshold to qualify as a cost-shared market efficiency project, so if they proceed, all three will be considered “economic other” projects that don’t qualify for regional cost allocation, meaning costs are assigned locally.

At the meeting, some MISO directors asked why the range of projects resembles past MTEPs when the RTO is paying so much attention to portfolio evolution. They asked whether MISO should be presenting MTEPs that contain a different mix of transmission projects to support a changing generation mix.

System Planning Committee of the Board of Directors | © RTO Insider

MISO Vice President of System Planning Jennifer Curran said the RTO only recommends economic transmission with reasoned business cases that show benefits across multiple future scenarios. She added that MISO’s 2011 slate of multi-value transmission projects was designed with future needs in mind and is still reaping benefits. (See MISO Triennial Review Shows Multi-Value Project Benefits.)

Director Todd Raba asked if MISO is still justified in using its “limited fleet change” MTEP future, the 15-year scenario used to gauge project value in a hypothetical footprint where the RTO’s coal use remains strong and renewable generation remains a minority. The limited change fleet future is one of four futures MISO currently uses.

“We seem to have moved beyond that now,” Raba observed.

“Limited fleet change is not what we’re seeing right now,” Curran acknowledged, adding that MISO has most likely shifted to its continued fleet change future by now.

“We’ve got a lot of resource shift in front of us,” she added, pointing out that MISO’s 90-GW generation interconnection queue is dominated by renewable generation.

A final version of MTEP 18 will go before the board for approval in early December. MISO will hold a Nov. 13 conference call of the board’s SPC to discuss a more complete MTEP 18 and stakeholder reactions to the portfolio.

Emergency Ops, Calm Summer Top Talk at MISO Board Week

By Amanda Durish Cook

ST. PAUL, Minn. — A systemwide emergency, market innovations and the relatively calm summer conditions on the grid topped executive discussions at MISO’s Board of Directors meetings this week.

A Sept. 18 meeting of the Markets Committee of the Board of Directors began with an initial look into MISO’s Sept. 15 declaration of emergency conditions, issued just one a day after the RTO released a forecast showing a 19% chance of such an occurrence at least once this fall. (See MISO in Conservative Ops After Emergency Declaration.)

Shawn McFarlane | © RTO Insider

“Our fall outlook noted the potential for tight conditions, and that has indeed … been the case since Saturday,” MISO Executive Director of Market Operations Shawn McFarlane began.

At the time of the meeting, MISO was still under conservative operations, which remained in effect until Sept. 19.

McFarlane said the emergency was the result of high temperatures and the ramping up of planned fall outages, and noted that MISO lost a “significantly large” unit on Sept. 14, followed by the loss of smaller units the next day. As a rule, MISO does not reveal which companies experience unplanned outages, although Entergy reported that its Grand Gulf Nuclear Station on the Mississippi-Louisiana border went offline Friday because of feedwater system issues.

MISO made about 600 MW of emergency energy purchases during the event and for about 15 minutes exceeded its 3,000-MW north-to-south sub-regional contract limit on the SPP line linking its North and South regions.

However, McFarlane stressed that MISO coordinated with SPP and other parties to the contract ahead of the high flows.

“We will emphasize that we communicated with SPP and others ahead of time,” he said.

MISO Executive Director of Energy Rob Benbow said the RTO made emergency purchases from both SPP and Southern Co. He said that although communications regarding the purchases were effective, some Southern operators were confused about MISO’s process and that the RTO will reach out to company staff to better clarify processes.

Markets Committee of the Board of Directors | © RTO Insider

Benbow also said MISO brought in extra staff ahead of the event to oversee the system.

In his chairman’s report at the Sept. 20 Board of Directors meeting, Director Michael Curran praised SPP, Southern and the Tennessee Valley Authority for assisting MISO South during the emergency.

“It was a lot of good things at the seams. We have very good neighbors,” Curran said.

He also added a warning about thin reserves and increasing outages: “It’s not going to be just a weather pattern. … This is going to be the new normal.”

‘Missed’ Forecast

McFarlane said the determining factor in the emergency conditions was a MISO forecast that missed the mark by about 7% of actual conditions.

“A lot of others had difficulty forecasting the heat. It’s not an excuse, but many underestimated the high loads. … I would put this in our top three or four forecast misses. It was a significant miss since we began forecasting in 2005,” McFarlane said.

“This is one of seven forecasts where we missed it by 5% or more,” said MISO President Clair Moeller, adding that most of the midcontinent failed to accurately predict the heat.

Because the forecast became inaccurate so quickly, many units with long lead times could not respond in time, Moeller noted. CEO John Bear added that more fast-start resources will be needed as the generation fleet evolves.

McFarlane also said demand response was difficult to access during the event because of rapid heating and the fact that load-modifying resources aren’t obligated to offer beyond the summer months.

“This is an advertisement for Resource Availability and Need,” McFarlane said, referring to MISO’s initiative to change load-modifying resource and outage coordination rules. (See MISO Moving to Combat Shifting Resource Availability.)

Moeller said MISO is also examining how it plans for system conditions in light of the emergency.

“We’re doing something you shouldn’t do. We’re using historic performance to predict future performance. The question is how to adjust our math,” Moeller said. “The worst thing you can do to a gas pipeline is not give notice and take gas, and that’s what we love to do, not give notice and take gas.”

WPPI Energy’s Valy Goepfrich took the microphone at the board meeting to urge MISO leadership to “R-E-L-A-X.” She said that MISO’s supply has exceeded load for years, and that the RTO and utilities are only experiencing bumps in learning how to effectively balance a more equalized supply-to-load ratio.

Market Innovation

Richard Doying, executive vice president of market development strategy, said MISO is currently researching new distributed resource integration models and how it can use historical data to better compute and manage transmission constraints. The RTO is also continuing ongoing research into how renewable penetration changes the operations and economics of the grid, he said. (See MISO Renewable Study Predicts Later Peak, Narrower LOLE Risk.)

Richard Doying (left) and David Patton | © RTO Insider

Doying said in order to truly develop MISO’s market, RTO staff need to contemplate rebuilding the current system from scratch. He said if MISO were able to revisit 2004 knowing what it knows now, the markets system would have looked very different.

“We probably would have built a very different set of operating procedures,” he said.

MISO is also expanding its overall use of market improvement pilots and simulations, where it can test a full-scale change without impacting the grid, Doying said.

Director Thomas Rainwater urged leadership not to get stuck in a single line of thinking in market innovation, reminding the room that Betamax was once cutting-edge.

Doying said MISO’s ongoing market platform replacement will be flexible enough to accommodate a wide range of future market styles. He said the RTO will release a revised market strategy document in 2019.

However, Independent Market Monitor David Patton said market development should be an “evolution, not revolution,” and told RTO leadership to focus more on the efficient pricing of energy.

Solid Summer Performance

Despite last week’s emergency conditions, MISO said it was able to manage a relatively calm summer.

“There were a few operational challenges and overall — very benign. Nothing like the last few days,” McFarlane said.

“High level summary: It was hot,” he joked.

MISO’s system peaked in late June at 121.6 GW, about a month ahead the usual summer peak, McFarlane said. The RTO had predicted a 125-GW peak. Load averaged 86.6 GW, compared to 82.7 GW during last summer.

Patton said the heat caused a jump in energy prices over last summer, with prices averaging $31.12/MWh over the season, up 8.1% from 2017.

The loss of a 500-kV line in MISO South over June 3-4 highlighted the need to develop a 30-minute reserve product, according to Patton. The line trip caused transmission violations that were priced at $4,000/MW of flow, causing the Louisiana hub price to jump to $2,500/MWh for about an hour-and-a-half late on June 3, he said.

MISO also experienced its lowest wind output in the footprint ever on July 29: 1 MW out of about 18 GW of total wind capacity in the footprint. McFarlane said the RTO and the media often call attention to maximum wind output and wind records but don’t often highlight low wind generation and wind output volatility.

“What are the lessons then?” Rainwater asked.

“We have to be prepared for almost anything. If anyone has a better answer, let me know,” McFarlane said.

PJM Monitor Holding Firm on Opportunity Cost Calculator

By Rory D. Sweeney

PJM’s Independent Market Monitor has declined to budge from its position that the RTO allow market participants to use its opportunity cost calculator, arguing that it would be consistent with other RTO verification processes.

pjm opportunity cost calculator
Bowring | © RTO Insider

The Monitor suggested that PJM has two options. The first is to maintain the status quo in which stakeholders are required to choose their own values using PJM’s calculators and risk being referred for disciplinary action at FERC — the situation that brought the issue to a boil in August

The Monitor’s preferred process would require market participants come to agreement with it on an opportunity cost that it verifies is competitive before submitting it for PJM approval. All parties retain the right to petition FERC if they don’t agree with the final result. That would result in a practice consistent with the process PJM already uses for verifying cost-based offers, the Monitor said.

“The IMM requests that PJM clarify its preferred review process for opportunity cost calculations,” the Monitor wrote. “The IMM recognizes that PJM can impose the first option. The IMM recommends the second option. … The IMM routinely informs market participants that if its use of the PJM calculator results in an opportunity cost greater than that calculated by the IMM that the IMM is required by the Tariff to raise the issue with FERC.”

The two parties’ yearlong standoff was brought to a head at the August 23 meeting of the Markets and Reliability and Members committees, where stakeholders threatened to advance Tariff revisions that would require PJM to accept the Monitor’s calculator. PJM had announced earlier in the month that it would only accept opportunity cost calculations using its calculator after staff realized that in “the latter part of 2016” results between the two calculators, which had produced consistent results since 2010, began to diverge substantially. (See Stakeholder Proposal Aimed at Ending PJM-IMM Dispute.)

The RTO responded Aug. 29 with a letter outlining its requirements for accepting the IMM’s calculator. (See PJM Sets Terms for Using IMM’s Cost Calculator.)

In its Sept. 16 response, the Monitor said that divergences likely began in 2011 when it “enhanced” its calculator with an “optimization solver … to correctly model rolling constraints.” The Monitor says it outlined the differences between the calculators in meetings with PJM and as part of special sessions of the Market Implementation Committee.

The Monitor’s response included its oft repeated criticism of PJM’s calculator.

“PJM’s opportunity cost calculator demonstrably does not produce accurate results over the entire range of possible scenarios faced by real units. … The IMM has discovered that market participants have made mistakes related to input assumptions that significantly affected the outcomes. … PJM does not review the inputs to its calculator used by participants,” the Monitor wrote. “PJM does not approve the results of its own calculator. Yet PJM states that PJM’s calculator is the standard for evaluating opportunity costs.”

The Monitor said it holds “detailed discussions” with market participants about opportunity cost calculation inputs and results and that it has modified its view of specific calculations considering details provided by participants.

“The IMM has made mistakes. The IMM does not claim that the IMM model is perfect,” the Monitor acknowledged. “While it is important to have a complete and accurate model, opportunity cost calculations require case-by-case analysis and are not a simple matter of just running a model.”

NY Study: Minimal Price Impact from Carbon Charge

By Michael Kuser

RENSSELAER, N.Y. — A carbon charge would only slightly impact New York’s wholesale energy prices over the coming decade, with any increase offset by benefits, a new report commissioned by NYISO says.

“If you add a carbon charge, LBMPs are going to increase, and they do,” said Sam Newell of the Brattle Group, who on Monday presented a draft study of carbon pricing impacts to the state’s Integrating Public Policy Task Force (IPPTF). The analysis is based on the ISO’s straw proposal issued in May.

This chart shows the broad framework for analyzing the effect of a CO2 charge on the wholesale energy market. | The Brattle Group

“The effect of higher LBMPs on customer costs, however, is partially or fully offset by several factors,” Newell said. “Customer credits from emitting resources offset about 60% of the price increase, then you’ve got other potential benefits such as lower prices for renewable energy credits (RECs) and zero-emission credits (ZECs), increased value of transmission congestion contracts, a shift of renewable resources to regions with higher CO2 emissions to displace and other changes to the supply mix.”

The Sept. 17 discussions were part of issue “Track 5” in the group’s five-track effort to price carbon emissions. Brattle will present the final version of its customer impact analysis to the IPPTF on Oct. 15.

Key Assumptions

The study’s base case scenarios cover 2020, 2025 and 2030, and the study projects the carbon charge will spur the highest cost early on: a 2.2% increase in 2020, followed by a 0.04% increase in 2025 and a 0.01% decline at the end of the next decade.

This chart shows the key assumptions for each of the study years in the report. | The Brattle Group

The base cases reflect “most likely” conditions, supply and demand conditions and existing policies, including the Clean Energy Standard and Regional Greenhouse Gas Initiative, Newell said.

The conclusions are similar to those of the first Brattle Group report, released in August 2017, on pricing carbon into generation offers and reflecting it in energy clearing prices. The main difference between the two reports is that now Brattle has studied three years (2020, 2025 and 2030) and has used GE-MAPS to model the effects of carbon charges on unit commitment, dispatch, prices, settlement and emissions, Newell said.

Several stakeholders wanted to know more about the assumptions used in the report and asked if the ISO would make a more technical report available.

“Nothing is secret,” Newell said.

IPPTF Chair Nicole Bouchez, the ISO’s principal economist, confirmed all data, methodologies and key assumptions would be made available to stakeholders as soon as possible, with an expected availability date around the beginning of October.

Andrew Antinori, senior director of the New York PowerAuthority’s (NYPA) Market Issues Group, said it did not make sense to focus on the higher price increase listed for 2020 ($0.38/kWh) because NYISO recently concluded carbon pricing would not be implemented any earlier than the second quarter of 2021.

Antinori asked if the price would be lower if the study started with 2022, the first full year, but Newell would only say the price increase for that year would fall between those of 2020 and 2025.

NYPA Concerns

Mark Reeder, representing the Alliance for Clean Energy New York, said NYPA sales should be accounted for in the study because many of its customers pay a low non-market price. Therefore, an increase in NYISO market price doesn’t translate into a one-for-one increase in the prices paid by NYPA’s end users.

Warren Myers, DPS director of market and regulatory economics, said, “Whenever we first saw a waterfall chart, NYPA was so complicated, one of our first concerns was we wanted to see a consistent set of analyses of non-NYPA customers.”

This waterfall chart breaks down a carbon charge’s effect on wholesale energy prices. | The Brattle Group

The study assumes all customers are fully exposed to the LBMP, so it overstates customer costs to the extent NYPA does not, Newell said. “We didn’t include [NYPA] because it would have been quite messy to try to account for it.”

Mark Younger of Hudson Energy Economics said, “NYPA also does market-based sales for a certain amount of energy, and doing this creates a windfall for a state agency, which presumably goes to New York State residents,” possibly to be used for their benefit.

“Our analysis did not consider any special effects on NYPA,” Newell said.

Couch White attorney Michael Mager, who represents Multiple Intervenors, a coalition of large industrial, commercial and institutional energy customers, said profits on market-rate sales would likely incent more such sales, not more low-cost contracts for industrial customers.

Antinori said, “It’s not fair to say ‘windfall’ when discussing NYPA revenues as if no other generator gets such a benefit from a carbon charge.”

Mager said the study might be overstating savings on REC prices: “You identified this in your original report, that it’s not one-to-one price savings.”

Newell said, “There are a number of ways to structure this so there’s no risk on suppliers and you get one-on-one benefits to renewables … We’re using load forecasts that decline by six terawatt hours every five years.”

Environment and Reliability

Tariq Niazi, ISO senior manager and Consumer Interest Liaison, was scheduled to present an analysis of consumer impacts from a carbon charge but got bumped from the lineup due to the length of time spent on the Brattle study.

According to the report, to be presented at next week’s IPPTF meeting, adding a carbon charge would reduce CO2 emissions approximately 3% by 2030 and cause only limited fuel switching; most emission reductions would result from dynamic effects such as renewable shifts, nuclear retention and price-responsive load.

The report also says pricing carbon would spur investment in renewables, supporting reliability, and the ISO intends to develop a calculation using marginal units to estimate the LBMP carbon impact.

Bouchez informed stakeholders of a revised task force schedule, which foresees the presentation of a carbon pricing proposal and recommendations on Dec. 17. The task force next meets Sept. 24 at NYISO headquarters.