Search
`
November 2, 2024

PJM Transmission Expansion Advisory Committee (TEAC)

© RTO Insider LLC
PJM PC/TEAC Briefs: July 11, 2023
PJM's Planning Committee discussed the recommended load model to be used in the 2023 Reserve Requirement Study (RSS), while the TEAC gave an update on the ongoing third window of its 2022 RTEP and the opening of the 2023 RTEP later this month.
Dominion Energy
PJM PC/TEAC Briefs: June 6, 2023
The PJM Planning Committee approved documents to explore possible improvements to transferring capacity interconnection rights.
© RTO Insider LLC
PJM PC/TEAC Briefs: May. 9, 2023
PJM plans to allocate more than 2,000 MW of transmission headroom to generators that requested additional capacity rights under a transitional process.
© RTO Insider LLC
PJM PC/TEAC Briefs: April 11, 2023
State advocates would like to see more details when supplemental transmission projects are proposed to the Transmission Expansion Advisory Committee.
© RTO Insider LLC
PJM PC/TEAC Briefs: Feb. 7, 2023
An error in the power flow case for several generators caused minor impacts to the 2022 annual cost allocations and zonal charges for the units, PJM said.
PJM
Policymakers Working to Meet Spiking Demand of Data Centers in Virginia
Demand growth in Northern Virginia's power-hungry Data Center Alley is accelerating, and policymakers are trying to ensure new demand can be met reliably.
PJM
PJM PC/TEAC Briefs: Jan. 10, 2023
PJM stakeholders approved new generator deliverability tests and learned of a 3rd competitive window to address "unprecedented" data center load in Virginia.
AES Ohio
AES Ohio Proposes $145M Project for EV Manufacturing Loads
AES will spend $145 million to build substations and new transmission lines to meet over 1,000 MW in expected load growth from EV manufacturers.
DCO Energy
NY Stakeholders Balk at NJ OSW Cost Allocation
New York stakeholders are challenging a PJM rule change they say could hit them with some of the cost of New Jersey's transmission upgrades for offshore wind.
© RTO Insider LLC
PJM PC/TEAC Briefs: Nov. 1, 2022
The PJM Planning Committee continued fine-tuning the five remaining packages for assigning capacity interconnection rights to ELCC resources.

Want more? Advanced Search