The Midcontinent Independent System Operator is a regional transmission organization that plans transmission projects, administers wholesale markets for its membership and manages the flow of electricity in Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Montana, North Dakota, South Dakota, Texas and Wisconsin. 
Vistra
MISO Customers Ask for Penalty-free Load Reductions
MISO transmission customers argued to FERC that MISO should allow customers to decrement their load penalty-free to lessen the possibility of summer blackouts.
MISO
Midwest Capacity Shortage Leads to Must-offer Talk
MISO’s capacity auction shortfall has nearly doubled its probability of load shedding in its Midwest region, prompting discussion of must-offer requirements.
MISO, SPP
SPP, MISO Propose Scrapping Affected System Studies
MISO and SPP announced that they plan to ditch their current affected systems study process for more interregional transmission studies like their JTIQ study.
© RTO Insider LLC
FERC OKs MISO’s Bifurcated Cost-allocation Tx Design
FERC has allowed MISO to use a separate-but-equal postage stamp rate divided between MISO Midwest and MISO South for some of its major transmission buildout.
NOAA
Summer Forecasts Spark Warnings of ‘Reliability Crisis’ at FERC
FERC commissioners expressed alarm over forecasts of potential supply shortfalls this summer in the West, ERCOT, MISO and SPP.
NERC 2022 Summer Reliability Assessment
West, Texas, Midwest at Risk of Summer Shortfalls, NERC Says
Drought, wildfires, plant retirements and transmission outages have elevated the risk of supply shortfalls in the West, Texas, MISO and SPP, NERC said.
ICC
MISO Exec, IMM Debate Next Steps After Capacity Auction Shortfall
A month after its capacity auction revealed a Midwestern supply scarcity, MISO’s Independent Market Monitor and a MISO vice president debated the path forward.
© RTO Insider LLC
MISO, SPP Hold 1st Common Seams Initiatives Meeting
MISO and SPP’s inaugural Common Seams Initiatives meeting discussed transmission reconfigurations and the search for interregional transmission projects.
SPP
SPP Reviewing its M2M Processes After MISO Monitor’s Comments
SPP staff are conducting internal discussions on how they manage MISO constraints in the day-ahead market as part of the RTOs’ market-to-market process.
© RTO Insider LLC
Clogged Queues, Need for Tx Draws Packed Crowd at EBA
Anxiety over clogged interconnection queues and the need for more interregional transmission loomed large at the Energy Bar Association’s annual meeting.