Search
`
November 2, 2024

ISO-NE Planning Advisory Committee

ISO-NE
ISO-NE Prices Transmission Upgrades Needed by 2050: up to $26B
Transmission upgrades that are needed to avoid overloads in a fully electrified New England by 2050 could cumulatively cost between $22 billion and $26 billion, ISO-NE told its Planning Advisory Committee.
© RTO Insider LLC
New England TOs Propose Asset Condition Project Database

The New England Transmission Owners outlined a proposal for a new asset condition project database at ISO-NE’s Planning Advisory Committee.

SayCheeeeeese, CC0 1.0 Public Domain, via Wikipedia
ISO-NE Projects Decrease in Gas, Increase in Coal and Oil for 2032
ISO-NE expects system emissions to fall by nearly half by 2032 as gas generation declines, but projects coal and oil generation to increase to cover winter peak loads.
ISO-NE
ISO-NE Outlines Economic Challenges of Decarbonization
ISO-NE told its Planning Advisory Committee that decarbonization may require increased dispatchable generation, storage and capacity.
National Grid
States Press New England TOs on Asset Condition Projects
NESCOE pressed transmission owners to increase the transparency of their asset condition projects and incorporate them into ISO-NE’s planning process.
ISO-NE
ISO-NE Planners Outline Potential Solutions for 2050 Tx Overloads
ISO-NE is studying line upgrades and new 345-kV and HVDC lines to address expected reliability violations in its 2050 Transmission Study.
ISO-NE
2050 Tx Study Finds Thousands of Miles of Overloads in ISO-NE
The preliminary results of ISO-NE’s 2050 Transmission Study suggests that New England will need to build new transmission and shift existing resources.
© RTO Insider LLC
ISO-NE Presents Preliminary 2050 Tx Study Scope
ISO-NE presented to the PAC its scope of work and modeling assumptions for its 2050 Transmission Study.
Shutterstock
ISO-NE Planning Advisory Committee Briefs: Oct. 20, 2021
The ISO-NE PAC received a project list update for the Regional System Plan that included 12 new projects to resolve thermal overloads and voltage violations.
Shutterstock
ISO-NE Planning Advisory Committee Briefs: Sept. 22, 2021
ISO-NE is proposing a pilot study to analyze the potential curtailments experienced by new generation from the addition of offshore wind on Cape Cod.

Want more? Advanced Search